Steam Turbine Generator Rebuild
Solicitation number
RFQQ 8777784-TD
Issued by
King County, Spokane City, Washington

About this file

This is a Request for Quotes and Qualifications (RFQQ) issued by the University of Washington for steam turbine generator rebuild services. The University is seeking qualified contractors to provide maintenance, inspection, repair support, reassembly, alignment, and related services for the TG-3 steam turbine following a forced outage event at the University of Washington Power Plant in Seattle, Washington. The solicitation was released on Wednesday, June 17, 2026, with an optional virtual pre-bid meeting scheduled for Wednesday, June 24, 2026, at 12:30 PM Pacific Time and an optional pre-bid site walk on Friday, June 26, 2026, at 10:00 AM Pacific Time. The question period closes on Monday, July 6, 2026, at 3:00 PM Pacific Time, and responses are due on Monday, July 20, 2026, at 3:00 PM Pacific Time. All solicitation activities, including addenda, messages, documentation, and submissions, are conducted exclusively through the University of Washington's Workday Strategic Sourcing system, with the reference number RFQQ 1226144-TD.

No specific pricing terms, set-asides, incumbent information, or funding details are provided in the available documentation. The University reserves the right to modify the timeline as needed and will notify all bidders of any modifications through the Workday Strategic Sourcing system.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTES AND QUALIFICATIONS

STEAM TURBINE GENERATOR REBUILD

REFERENCE# RFQQ 1226144-TD

Workday Strategic Sourcing Event:

https://university-of-washington.public-portal.us.workdayspend.com/bid-details/1226144

The University of Washington (“University” or “UW”) is soliciting quotes and qualifications from qualified contractors to provide maintenance, inspection, repair support, reassembly, alignment, and related services for the TG-3 steam turbine rebuild following a forced outage event. The unit is located at the University of

Washington Power Plant in Seattle, Washington.

Partial Schedule of Events:

This RFP is being conducted solely through the University of Washington’s Workday Strategic Sourcing system. UW reserves the right to modify the above timeline as needed and will notify all of the Bidders of any modifications via the Workday Strategic Sourcing system.

All addenda, messages and documentation will only be available on the UW Sourcing Site.

All communications and responses must be submitted Via the Workday Strategic Sourcing system.

Solicitation Released Wednesday June 17, 2026

Optional Virtual Pre-Bid Meeting via Zoom Wednesday June 24, 2026, 12:30PM Pacific

Optional Pre-Bid Site Walk Friday June 26, 2026, 10:00AM Pacific

Question Period Closes Monday, July 6, 2026, 3:00PM Pacific

Submission Response Due Monday, July 20, 2026, 3:00PM Pacific Time

REQUEST FOR QUOTES AND QUALIFICATIONS

File details come from the government source that posted it. Updated .