About this file
This document is a Request for Qualifications (RFQ) from the Warren County School System for a Guaranteed Energy Savings Performance Contract. The school system is seeking qualifications from Energy Services Companies (ESCOs) to design and implement energy conservation measures across its facilities in accordance with Georgia legislation. The selected ESCO will be required to conduct an investment grade audit, identify and engineer appropriate conservation measures, install and maintain the approved solutions, and provide financing options. Responses are due by 2:00 pm on April 19, 2024, and the school system expects to formally select an ESCO partner and execute a Project Development Agreement by May 14, 2024.
The intent of this project is to enable the Warren County School System to improve its facilities through guaranteed energy, operational, maintenance, and capital cost avoidance savings, as well as new revenue sources. The school system is seeking ESCOs that can demonstrate relevant experience, including multiple-phase projects, in implementing Guaranteed Energy Savings Programs, particularly within the state of Georgia.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Qualifications
Guaranteed Energy Savings Performance Contract for
Warren County School District
RFQ for Guaranteed Energy Savings Performance Contract Release date: March 22, 2024
Due Date: April 19, 2024 Time: 2:00pm Right to Reject: In submitting a response to this RFQ, it is understood by the respondent that the right is reserved by Warren County School District to accept or reject any and all responses, and to waive any irregularities or informalities when to do so is in the best interest of Warren County School District
I. Introduction and Background Warren County School System requests qualifications from interested Energy Services Companies (ESCO’s) for the design and implementation of a Guaranteed Energy Savings Performance Contract in various facilities, in accordance with (OCGA Title 50, Ch. 37 or O.C.G.A. § 20-2-506) or other Georgia legislation.
This Request for Qualifications requires the selected ESCO to conduct an investment grade audit. The selected firm will be required to identify, engineer, design, install, maintain, and provide financing options for approved energy conservation measures in a fixed cost scenario.
The intent of this project is to provide Warren County School System the means to improve its designated facilities through guaranteed energy, operational, maintenance and capital cost avoidance savings, as well as new revenue sources.
II. RFQ PROCEDURES
A. Point of Contact Questions concerning this RFQ and the procedures for responding to the RFQ should be directed to:
Dr. Christopher Harris Sr.
charris@warren.k12.ga.us
B. Submission of Responses Responses must be received by 2:00pm on April 19, 2024. Respondents should submit three (3) paper copies and one (1) electronic copy of the response to:
| Dr. Christopher Harris Sr. | |
| Superintendent | |
| 115 Gibson Hwy, Warrenton, Ga 30828 |
“Proposals Enclosed – Guaranteed Energy Savings Contract”
Responses received after the time and date specified above will be disqualified as unresponsive.
C. Schedule of Events
The following time frame is expected to be followed during the procurement period of this RFQ. This is a tentative schedule, and dates are subject to change.
· Release of RFQ – March 22
· RFQ Response Due – 2:00pm April 19
· Review of Submissions – April 19- April 24
· Formal selection of an ESCO partner – April 25
· Project Development Agreement executed with the selected ESCO – May 14
III. FORMAT AND CONTENTS
Responses must be submitted in the format outlined in this section. Responses must be no more than twenty-five (25) pages total, single-sided, with a minimum 10-pt. font. Note: Cover Page, Cover Letter, Table of Contents, and Annual Reports / Audited Financials do not count toward the page limit. Warren County School District reserves the right to eliminate from further consideration any submittal deemed to be substantially or materially unresponsive to the requests for qualifications contained herein.
A. Executive Summary
Responses shall include a concise abstract stating the respondent’s understanding of the district’s goals and objectives. The ESCO’s submission should identify the firm’s ability to satisfy Warren County School District’s unique financial, technical, and strategic goals and objectives.
B. Company Background & Experience
1. Provide a company overview/history of the organization.
2. Describe prior relevant work experience and provide a minimum of ten (10) references of Guaranteed Energy Savings Programs implemented by your organization. Provide the customer’s name, total project cost, Contact name, telephone number and email of contact, and a brief description of the project. Preference will be given to ESCOs that demonstrate multiple-phase projects with the references mentioned above.
3. Provide a comprehensive list of all Guaranteed Energy Savings Programs implemented by your organization in the state of Georgia.
C. Project Development
1. Provide a description of your organization’s project development process and typical schedule.
2. Provide an overview of any additional service offerings currently being offered by your company. Highlight the specific ways that you believe Warren County School System could benefit from these services.
3. Include a comprehensive list of any products or materials that would be offered by your company as part of this project which are manufactured, produced, owned by your company or its affiliates.
D. Project Management
1. Provide a description of your organization’s approach to project management.
2. Provide a description of your organization’s approach to the ongoing maintenance (service) of the installed equipment.
3. Provide a description of your organization’s approach to warranty issues.
E. Financial
Provide your two (2) most recent Annual Reports or Audited Financials.