CTARNG_CST-RB_Bidders_Q-A_23JUN16.pdf
PDF 34 KB Posted
- Attached to
- CST Ready Building - Design Build Federal contract opportunity
- Solicitation number
- W91ZRS-16-R-0001
About this file
RFI- Answers 23JUN16
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 16-R-0001-0002.pdf | ||
| CTARNG_CST-RB_Bidders_Q-A_5_Jul_16.pdf | ||
| 6.01_Building_Life_Cycle_Analysis_Factors_160628b_.pdf | ||
| EXHIBIT_E-_DB_CTR_Proposed_Alternates-Betterments-Deviations.docx | DOCX document | |
| Sol_Phase2_W91ZRS-16-R-0001-Amendment-0001_20160603.pdf | ||
| Exhibit_D-DB_Cost_Breakdown_CST_W91ZRS-16-R-0001.docx | DOCX document | |
| Sol_Phase2_W91ZRS-16-R-0001-Amendment-0001_ConformedDoc_20160603.pdf | ||
| Q A_20160420.docx | DOCX document | |
| Q A_20160411.docx | DOCX document | |
| CST_EXHIBIT_F_Pre_Proposal_Inquiry_Form.docx | DOCX document | |
| CST_EXHIBIT_B.docx | DOCX document | |
| CST_EXHIBIT_A.docx | DOCX document | |
| W91ZRS-16-R-0001_CST_SOL_5APR2016.pdf | ||
| CST_EXHIBIT_C.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CST-Ready Building
Connecticut Army National Guard
PN 090071
DB-RFP
Bidder's Questions / CTARNG's Answers
6/23/2016
# Question Date Answer
1 Are CAD drawings available for the site? 21-Jun Refer to Part 2 - General Requirements Section 01 30 00.05 20
Para 1.6.
2 Will the Contracting Office hire the Commissioning Agent as stated on pg.67?
21-Jun Yes
3 If a solar hot water system is installed on the roof, will interior roof access be required?(pg.445 – Roof Hatches –not used).
21-Jun No
4 How many and what size above ceiling mounted, motorized projection screens are required? (pg.276)
21-Jun Refer to Part 3, Room Requirement Sheets, Classroom A1
5 What card access system is used at Camp Hartell? (asking for lithium battery operated locksets? – pg.424).
21-Jun Card key access system (electronic; not based on lithium battery locksets) will be government furnished - government installed
EXCEPT contractor shall provide power and pathway(s) (power & communications) as required for each noted Card Key Access location, terminating to the location to be designed for all system equipment. Contractor to coordinate installation of GFGI 'Galaxy
Card Access System' with CTARNG.
6 In the RFP room requirements it mentions “Raised Access Floors” and in the Specific Requirements it States “Betterment”. However as stated in
C103016 (Raised Access Flooring) it does not distinguish whether it is a betterment. Please clarify
22-Jun Engineering Systems Requirements (ESR) and Performance
Technical Specifications (PTS) generally define parameters for proposed Betterments and Options to be incorpoarated into the work should they be selected. ESR's and PTS's do not distinguish between base requirements, betterments and options.
Betterments and Options are indicated through-out Part 3, Chapters 1, 2, 3, 4 and 5. Raised Access Flooring is considered a betterment where indicated in Part 3 Chapter 5 Room
Requirements.