B2_W91QVN20R0218_DRAFT SOLICITATION.pdf
PDF 411 KB Posted
- Attached to
- Truck Mounted Stiff Boom Crane
- Solicitation number
- W91QVN20R0180
About this file
This is a solicitation for a Truck Mounted Stiff Boom Crane to be utilized by the United States Army Garrison Yongsan-Casey Department of Public Works. The crane must be easily maneuverable for urban worksite access and all operations must be performable by one operator. An optional man basket is also requested. Questions regarding the solicitation are due by September 10th at 0900 KST and offers must be submitted by September 17th at 1200 KST. This requirement is restricted to local contractors located within the soliciting agency's area of responsibility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B3_ W91QVN20R0180_ BETA SAM Solicitation amendment.pdf | ||
| B3_ W91QVN20R0180_ Draft Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011529203
Project # 22302, Repair Barracks, building No.4025
A. "THIS IS A NON-WORK PLAN TASK ORDER RFP TO MATOC AREA I AND II CONTRACTORS ONLY". Contract Numbers # W91QVN- 18-D-0021, 0022, 0023, 0025, 0026, 0027, 0028, 0030, 0031, 0042, 0044, 0045, 0046, 0050, 0051.
B. Site Visit: Offerors w ho intended to propose on this solicitation are strongly encouraged to attend site visit. See site visit clause FAR
52.236.27 in Section L.
C. If the contractor is unable to submit the proposal in response to this RFP, the contractor shall submit the "NO OFFER" by date and time specif ied in this solicitation.
D: SAEF NOTICE
SUBJECT TO THE AVAILABILITY OF END-OF YEAR FUNDS (SAEF)
"FUNDS ARE NOT PRESENTLY AVAILABLE FOR THIS ACQUISITION. NO CONTRACT AWARD
WILL BE MADE UNTIL APPROPRIATED FUNDS ARE MADE AVAILABLE."
SSG PROCTOR, TIANNA M. 755-0639
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
14-Sep-2020
(RFP)
(IFB)
X
CALL:
Repair Barracks, Building No. 4025, Camp Hovey
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
411TH CSB, KOREA - IMB
UNIT#15289
APO AP 96205
UNITED STATES
W91QVN
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
(hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
223002
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: 724-6977 TEL: FAX:
W91QVN20R0218 40
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
REPAIR BARRACKS #4025
FFP
SPECIFICATIONS FOR
PROJECT NO.: 223002
REPAIR, BARRACKS, BUILDING NO.4025
CAMP HOVEY, KOREA
FOB: Destination
PURCHASE REQUEST NUMBER: 0011529203
PSC CD: Z2FC
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Job Estimated Cost for War Hazard Losses
FFP
is Zero (0) FOB: Destination
PSC CD: Z2FC
NET AMT
Section C - Descriptions and Specifications
STATEMENT OF WORK
DEPARTMENT OF THE ARMY
US ARMY INSTALLATION MANAGEMENT COMMAND
HEADQUARTERS, UNITED STATES ARMY GARRISON, YONGSAN-
CASEY
UNIT #15543
APO AP 96224-
IMYN-C-PWF 24 July 2020
SPECIFICATIONS
FOR
PROJECT NO.: 223002
Repair barracks, building No.
4025 Camp Hovey, Korea
TABLE OF CONTENTS
1. Technical Provisions - I: Statement of Work
2. Technical Provisions - II: Technical Detail Specifications
3. Technical Provisions - III: Special Conditions
4. Appendix "A": List of Applicable Contract Drawings
5. Appendix “B”: List of materials for Material Approval Submittal
TECHNICAL PROVISIONS - I
STATEMENT OF WORK
PROJECT NO
TITLE
LOCATION
223002 Repair barracks, building No. 4025 Camp Hovey
1. DESCRIPTION: The work to be performed to repair barracks, building No. 4025 is described below and executed by one or more of the groups.
1.1. Work by Contractor: The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and in accordance with the specifications.
1.2. Work by In-House Labor: Not applicable to this project.
1.3. Work by Troop Labor: Not applicable to this project.
2. PRINCIPAL FEATURES: This project includes the following principal features:
2.1. Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.
2.1.1. Civil Work
2.1.1.1. Replace 1.2m width sidewalk.
2.1.1.2. Replace granite curb.
2.1.1.3. Replace shade shelter with two (2) movable wood picnic tables.
2.1.1.4. Mill and overlay with 50mm thickness Asphalt Concrete (AC) surface course.
2.1.1.5. Replace 8.0m width AC road.
2.1.1.6. Plant cherry blossom tree.
2.1.1.7. Upgrade drainage system with four (4) surface inlet (0.7m x 0.7m) and 300mm diameter Reinforced Concrete Pipe (RCP) to connect to existing concrete open ditch.
2.1.1.8. Paint 150mm thickness reflective white parking line.
2.1.1.9. Remove existing wood shelter.
2.1.1.10. Restore solid sodding with top soil.
TP I-1
2.1.2. Architectural Work
2.1.2.1. Floor work
2.1.2.1.1. Replace existing floor tile and rubber tile with new Polyvinyl Chloride Tile (PVCT) including Vinyl Cove Base (VCB) and Rubber Base (RB) as shown on new floor plan and interior finish schedule.
The existing concrete flooring shall be smooth, true, level plane with all defects such as rough or scaling concrete, low spots, high spots, painting, and uneven surface shall be corrected for new flooring. Provide leveling concrete for existing concrete slab with government approval.
2.1.2.1.2. Replace existing quarry tile including quarry tile base with new as shown on floor plans and interior finish schedule.
2.1.2.1.3. Replace existing Ceramic Mosaic Tile (CMT) with new including cement bond coat, waterproof membrane, and mortar bed as shown on floor plans, section and details drawings.
2.1.2.1.4. Replace existing concrete slab at corridor, each bath rooms, toilet, laundry, and mud room on 1st floor for mechanical sewer line works as shown on floor plan and mechanical drawings.
2.1.2.1.5. Apply epoxy coating with non-slip grits on existing floors as shown on floor plan and interior finish schedule.
2.1.2.2. Interior and exterior wall work
2.1.2.2.1. Replace existing all Gypsum Wall Board (GWB) walls with new GWB wall (Normal, water resistant or 'X' type) including metal studs as shown on floor plans, sections and detail drawings.
2.1.2.2.2. Paint all existing interior walls including Concrete Masonry Unit (CMU), metal, concrete surfaces, stairway, hand rails, and guard rails as shown on floor plan, detail drawings interior finish schedule.
2.1.2.2.3. Paint all existing exterior walls including Exterior Insulation and Finish System (EIFS), CMU, metal, woods, concrete surfaces, stairwells, hand rails, guard rails, and other components (bicycle rack, trash bin) of exterior surface of the building as shown on floor plan, detail drawings and pictures.
2.1.2.2.4. Apply texture coating with plastering at dressing room and closet as shown on floor plans, elevations and interior finish schedule.
2.1.2.2.5. Replace existing Glazed Ceramic Wall Tile (GCWT, full height) with new including cement bond coats, water proof membrane, plastering with metal lath, and waterproof GWB as shown on floor plans and sections.
2.1.2.2.6. Replace existing pipe chases and pipe cover with new CMU, waterproof type GWB pipe chases and metal cover including access door in each rooms for new mechanical piping system as per floor plans, sections, and detail drawing.
TP I-2
2.1.2.2.7. Replace existing Acoustical Wall Panel (AWP) as shown on floor plan and interior finish schedule.
2.1.2.3. Interior and exterior ceiling and roof work
2.1.2.3.1. Replace existing ceiling with new acoustical ceiling tiles including metal suspension systems as shown on floor plans and interior finish schedule.
2.1.2.3.2. Replace existing ceiling with new GWB (Normal, water resistant or 'X' type) ceiling including ceiling suspension system as shown on floor plans and finish schedule.
2.1.2.3.3. Paint all interior ceiling surfaces as shown on interior finish schedule and section.
2.1.2.3.4. Paint all existing exterior exposed metal, woods, fascia, and soffit as shown on floor plan and elevations.
2.1.2.3.5. Apply acrylic fluid-applied waterproofing coating on existing roof as shown on floor plan and sections.
2.1.2.3.6. Replace existing rain gutter with new at canopies as shown on floor plan and elevation.
2.1.2.4. Miscellaneous work
2.1.2.4.1. Replace existing doors and door frames with new including hardware sets as shown on new floor plan and door schedule.
2.1.2.4.2. Replace existing windows including insect screen with new aluminum thermal breaker type windows including glass as shown on floor plans, elevations and window schedule.
2.1.2.4.3. Replace existing window horizontal mini blinds with new, fireproof type.
2.1.2.4.4. Replace existing wooden head, jam & sill for all windows with new as shown on door and window schedule. (Natural color, oak)
2.1.2.4.5. Replace existing aluminum louver with new as shown on floor plans and louver schedule.
2.1.2.4.6. Replace existing Fire Extinguisher Cabinets (FEC) with new as shown on floor plans and detail drawing.
2.1.2.4.7. Replace existing all toilet accessories with new as shown on floor plans and detail drawings.
2.1.2.4.8. Replace existing all access doors on wall and ceiling with new as shown on floor plan and enlarged floor plan.
2.1.2.4.9. Replace existing kitchenette with new including base cabinet and upper cabinet as shown on floor plan, elevation and detail drawings.
2.1.2.4.10. Replace interior and exterior signages with new for all rooms as shown on floor plan, elevations and signage schedule.
2.1.2.4.11. Replace existing metal shelf with mop rack with new in janitor room. 2.1.2.4.12.
Replace existing gravel bed and concrete curb with new 100mm deep gravel bed including granite curb around building as shown on floor plan and detail drawing.
TP I-3
TP I-4
2.1.2.4.13. Replace existing trench covers, hooks, and hose bib with new, and paint steel cover at mud room as shown on floor plan and detail drawing.
2.1.2.4.14. Replace existing al grating covers with new for each vest as shown on floor plan and detail drawing.
2.1.2.4.15. Replace existing counter top and Stainless Steel (SST) shelves with new at laundry as shown on floor plan and detail drawing.
2.1.2.4.16. Replace existing iron board cabinet with new as shown on floor plan and detail drawing.
2.1.2.4.17. Replace existing exterior and interior bulletin boards, card holder, and flexi info with new as shown on floor plan, detail drawing and signage schedule.
2.1.2.4.18. Replace existing aluminum louvers with new as shown on floor plans and detail drawings.
2.1.2.4.19. Replace wooden shelf, SST rod, and drawer cabinet with new in each closet as shown on floor plan and details.
2.1.2.4.20. Replace existing fire rated access doors (1-1/2hrs) with new at laundry and stairwell as shown on floor plans.
2.1.2.4.21. Replace existing wooden chair rails and wooden hanger rails at each bed room, kitchen, lounge and game room with new as shown on floor plans and detail drawings.
2.1.2.4.22. Replace existing vanity cabinets including wall hung cabinet with new in all dressing room as shown on new floor plans and detail drawing.
2.1.2.4.23. Replace existing concrete stoops with new as shown on floor plan.
2.1.2.4.24. Replace existing 18mm thickness plywood shelves including plastic laminate at each storage bin as shown on floor plans and elevations.
2.1.2.4.25. Replace existing SST splash guard with new as shown on floor plan and exterior elevations.
2.1.3. Mechanical Work
2.1.3.1. Replace Heating, Ventilating, and Air Conditioning (HVAC) system with chiller, hot water boiler, air handling units, heating and ventilating units, fan coil units, exhaust fans, pumps, expansion tank, air separator, air conditioning units, unit heater, ducts, louvers, diffusers, grilles, range hood, valves, dampers, pipes, insulations, control work, equipment support (concrete pad), and all associated accessories as shown on drawings. (Existing domestic hot water heater excluded)
2.1.3.2. Provide new electrical unit heater and ceiling mounted exhaust fans for HVAC system as shown on drawings.
2.1.3.3. Perform Duct Air Leakage Test (DALT) and Testing, Adjusting, and Balancing (T.A.B) after construction to verify if the HVAC system works properly.
2.1.3.4. Replace existing all dryer vent and caps with new.
A‐9
2.1.3.5. Replace plumbing system with domestic cold and hot water piping system, sewer and vent piping system including domestic hot water storage tanks, pumps, plumbing fixtures, electric water coolers, valve boxes for washing machines, valves, pipes, insulations, control work, equipment support, and all associated accessories as shown on drawings.
2.1.3.6. Replace existing automatic fire protection sprinkler system and all associated accessories for fire protection system as shown on drawings.
2.1.3.7. Pre-air leaking test is required prior to repair infiltration and sealing at mechanical room. Repair infiltration and seal air leaking portions including clearance between wall, ceiling, and penetrators (duct, water piping, conduct pipe, and flue vent pipe) at mechanical room. Provide final-air leakage test report.
2.1.4. Electrical Work
2.1.4.1. Replace existing lighting fixtures, exit lights, exterior lights, toggle switches, 3-way switches, photocell, wires and conduits with new.
2.1.4.2. Replace existing receptacles and cover plates with new.
2.1.4.3. Replace existing safety switches, master control panel, combination motor starters, magnetic motor starters, manual motor starters, junction boxes, control system, wires and conduits for HVAC system with new.
2.1.4.4. Replace fire alarm control system with new addressable fire alarm control and mass notification system panel, manual pull station, smoke detector and relay module, visual signal strobes, microphone, speaker device, and associated wiring and conduit.
2.1.4.5. Remove and reinstall existing fire alarm building transmitter, antenna, and lighting arrester with new wiring and conduit.
2.1.4.6. Replace existing telephone outlets and cover plates with new.
2.1.4.7. Replace existing CATV outlets and cover plates with new.
2.1.4.8. Remove and reinstall existing CCTV system, cameras and LCD television. Replace CCTV wiring and conduit with new.
2.2. Schedule #II, New Construction (L): All work shall be in accordance with the attached drawings and specifications.
None
TECHNICAL PROVISIONS - II
TECHNICAL DETAIL SPECIFICATIONS
PROJECT NO TITLE LOCATION
97606 Repair building No. 4025 CAMP HOVEY
GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/2014-OMA-SPECS_REVISION- 1.pdf. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.
A‐
Changes to the Standard Technical Detail Specifications: None
TP II-1
TECHNICAL PROVISIONS - III
SPECIAL CONDITIONS
97606 Repair building No. 4025 CAMP HOVEY
1. The contractor shall have personnel on site for the sprinkler work and the fire alarm work upon Government's direction, who are certified by the National Institute for Certification in Engineering Technologies (NICET) Level III or equivalent. Equivalent Certificates in Korea are the followings which are issued by the Human Resource Development Service of Korea. If the contractor doesn’t have personnel who are certified by NICET, the contractor shall have two personnel that one is certified for (1) and the other for (2) below.
(1) Engineer Fire Fighting Facilities - Electrical (소방설비기사 -전기)
(2) Engineer Fire Fighting Facilities - Mechanical (소방설비기사 -기계)
2. Environmental Requirements in Contract
The Contractor shall perform work consistent with the relevant policy and objectives identified in Installation’s Environmental Management System (EMS). The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by Installation’s EMS, including pollution prevention, waste reduction, energy use, and natural resource protection. The Contractor shall provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In addition, the Contractor shall advise their employees of their roles and responsibilities identified by the EMS and how these requirements affect their work performed under this contract. The Contractor is responsible for ensuring that the Contractor and any persons involved in the supervision or performance of the contract complete all required Environmental training.
In the event of any environmental nonconformance or noncompliance associated with the contracted services, the contractor shall take corrective and/or preventative actions. In the event of any noncompliance with any federal, state, or local environmental law, regulation or requirement, the Contractor shall immediately respond by taking all appropriate corrective actions and notifying the Contracting Officer’s Representative (COR) and the Environmental Office. For any nonconformance with the EMS, the Contractor shall take corrective action and initiate further preventative action, as required by the Environmental Office.
All on-site contractor personnel shall complete necessary safety and environmental training specified for the type of work conducted on-site. Upon contract award, the COR will notify the EMS Manager to arrange Environmental training for appropriate staff.
TP III-1
Additionally, when ordering supplies for use on Installation, all contractor personnel must favor energy-efficient, recycled or reclaimed material whenever practicable.
The responsibilities of all contractor personnel include:
(1) Comply with all applicable environmental laws, regulations and installation environmental policies.
(2) Control and prevent spills or hazardous substances releases IAW installation Spill Prevention
Plan.
(3) Ensure dust, debris, materials, trash, etc., do not become air borne and travel off the project site.
(4) Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, topsoil and land forms without approval, except in areas indicated on the drawings or specified to be cleared.
(5) Monitor all water areas affected by construction activities to prevent pollution of surface and ground waters. Do not apply toxic or hazardous chemicals to soil or vegetation unless otherwise indicated.
(6) Open burning is prohibited on the Government premises IAW installation environmental policy.
(7) Participate in installation’s recycling program.
(8) Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content. Spills of hazardous or toxic materials must be immediately reported to the Contracting Officer and the Environmental Office.
Storage, describing, packaging, labeling, marking and placarding of hazardous waste and hazardous material IAW applicable environmental laws, regulations and local environmental policies. Transport hazardous waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.
(9) Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling. Handling, storage, and disposal of solid waste must be conducted to prevent contamination. Transport solid waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.
(10) Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must.
(11) When potential cultural or historic items are inadvertently found during construction activities, immediately cease activities in the vicinity of the discovery and report the findings to the Environmental Office.
TP III-2
(12) Participate in installation’s Integrated Pest Management (IPM) program whenever practicable.
(13) Minimize interference with disturbance to, and damage to fish, wildlife, and plants including their habitat.
3. CONTRACT REQUIREMENTS PACKAGE ANTITERRORISM/OPERATIONS SECURITY REVIEW
COVER SHEET
After Notice to process is issued, COR shall take following action, Section IV. Standard Contract Language/Contract Clause Applicability and/or Additional SOW Language.
A. AT Level I Training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 20 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 10 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.
B. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area.
Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
B-a. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
TP III-3
C. iWATCH Training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 10 calendar days of contract award and within 10 calendar days of new employees commencing performance with the results reported to the COR NLT 10 calendar days after contract award.
D. Requirement for OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
OPSEC training is available at the following website: http://cdsetrain.dtic.mil/opsec/
TP III-4
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government 0002 N/A N/A N/A Government
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
0002 N/A N/A N/A N/A
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 calendar days after notice to proceed(NTP) is issued. The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
Section G - Contract Administration Data
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
AUG 2020
Section J - List of Documents, Exhibits and Other Attachments
APPENDIX A
APPENDIX "A"
LIST OF APPLICABLE CONTRACT DRAWINGS
GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), issued by the Department of the Army, Installation Management Agency, Korea Region Office and located on http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/STANDARD-DETAIL- DRAWINGS-FOR-OMA-PROJECTS-KOREA_20151130.pdf, all of which form a part of the specifications.
Ring No. Sheet No. Description Date
1 T-1 TITLE SHEET 22 JUL 20
2 T-2 TITLE SHEET 22 JUL 20
CIVIL
3 C-1 LOCATION PLAN AND GENERAL NOTES 22 JUL 20
4 C-2 SITE LAYOUT PLAN AND SCOPE OF WORK 22 JUL 20
5 C-3 SHADE SHELTER 22 JUL 20
6 C-4 MISC. DETAILS - 1 22 JUL 20
7 C-5 MISC. DETAILS - 2 22 JUL 20
ARCHITECTURAL
8 A-1 1ST FLOOR PLANS AND GENERAL NOTES 22 JUL 20
9 A-2 2ND - 4TH FLOOR PLANS AND SCOPE OF WORK 22 JUL 20
10 A-3 ELEVATIONS AND SCOPE OF WORK 22 JUL 20
11 A-4 ELEVATIONS AND PICTURES 22 JUL 20
12 A-5 GENERAL SECTIONS 22 JUL 20
13 A-6 INTERIOR WALL SECTIONS-1 22 JUL 20
14 A-7 INTERIOR WALL SECTIONS-2 22 JUL 20
15 A-8 TYPICAL ENLARGED FLOOR PLANS 22 JUL 20
16 A-9 ENLARGED FLOOR PLANS AND FIRE RATED ACCESS 22 JUL 20
A-10
DOOR NOTES
INTERIOR ELEVATIONS-1
22 JUL 20
18 A-11 INTERIOR ELEVATIONS-2 22 JUL 20
19 A-12 INTERIOR ELEVATIONS-3 22 JUL 20
20 A-13 INTERIOR ELEVATIONS-4 AND DETAILS-1 22 JUL 20
21 A-14 DETAILS-2 22 JUL 20
22 A-15 DETAILS-3 22 JUL 20
23 A-16 DETAILS-4 22 JUL 20
24 A-17 KITCHEN CABINET DETAILS 22 JUL 20
25 A-18 CLOSET DETAILS 22 JUL 20
26 A-19 INTERIOR, EXTERIOR FINISH SCHEDULE AND 22 JUL 20
A-20
MATERIAL & COLOR SCHEDULE
DOOR, WINDOW & LOUVER SCHEDULE AND
A-21
HARDWARE SCHEDULE
DOOR, WINDOW & LOUVER ELEVATIONS, NOTES
A-22
AND DETAILS
SIGNAGES SCHEDULE
MECHANICAL
30 M-1 LEGEND & ABBREVIATION 22 JUL 20
31 M-2 GENERAL NOTES & SCOPE OF WORK 22 JUL 20
32 M-3 EQUIPMENT SCHEDULES - 1 22 JUL 20
33 M-4 EQUIPMENT SCHEDULES - 2 22 JUL 20
34 M-5 EXISTING AND REMOVAL MECHANICAL PLAN 22 JUL 20
35 M-6 NEW H.V.A.C PLAN (1st FLOOR) 22 JUL 20
36 M-7 NEW H.V.A.C PLAN (2nd - 3rd FLOOR) 22 JUL 20
37 M-8 NEW H.V.A.C PLAN (4th FLOOR) 22 JUL 20
38 M-9 MECH. ROOM DUCT PARTIAL PLAN, LAUNDRY 22 JUL 20
M-10
EXHAUST DUCT PARTIAL PLAN
NEW H.V.A.C PIPING PLAN (1st FLOOR)
40 M-11 NEW H.V.A.C PIPING PLAN (2nd - 3rd FLOOR) 22 JUL 20
41 M-12 NEW H.V.A.C PIPING PLAN (4th FLOOR) 22 JUL 20
M-13
M-14
MECH. ROOM PIPING PARTIAL PLAN, LAUNDRY &
MUD ROOM PLUMBING PIPING AND FUEL OIL PIPING
PARTIAL PLAN
NEW PLUMBING PIPING PLAN (1st FLOOR)
44 M-15 NEW PLUMBING PIPING PLAN (2nd FLOOR) 22 JUL 20
45 M-16 NEW PLUMBING PIPING PLAN (3rd FLOOR) 22 JUL 20
46 M-17 NEW PLUMBING PIPING PLAN (4th FLOOR) 22 JUL 20
47 M-18 BATH RM PLUMB. PIPING PARTIAL PLAN, LAUNDRY & 22 JUL 20
M-19
MUD ROOM PLUMBING PIPING ISOMETRIC DIAGRAM
BATH. RM. PLUMBING PIPING ISOMETRIC DIAGRAM
49 M-20 NEW FIRE PROTECTION PIPING PLAN (1st FLOOR) 22 JUL 20
50 M-21 NEW FIRE PROTECTION PIPING PLAN (2nd FLOOR) 22 JUL 20
51 M-22 NEW FIRE PROTECTION PIPING PLAN (3rd FLOOR) 22 JUL 20
52 M-23 NEW FIRE PROTECTION PIPING PLAN (4th FLOOR) 22 JUL 20
53 M-24 CONTROLS - 1 22 JUL 20
B‐
54 M-25 CONTROLS - 2 22 JUL 20
55 M-26 CONTROLS - 3 22 JUL 20
56 M-27 CONTROLS - 4 22 JUL 20
57 M-28 MECH ROOM AIR LEAKAGE TEST FLOW CHART AND 22 JUL 20
M-29
QUALIFICATION OF AIR LEAKAGE TESTING
MECH. DETAILS - 1
59 M-30 MECH. DETAILS - 2 22 JUL 20
60 M-31 MECH. DETAILS - 3 22 JUL 20
61 M-32 MECH. DETAILS - 4 22 JUL 20
62 M-33 MECH. DETAILS - 5 22 JUL 20
ELECTRICAL
63 E-1 LEGEND, GENERAL NOTES AND SCOPE OF WORKS 22 JUL 20
64 E-2 NEW 1ST FL LIGHTING PLAN 22 JUL 20
65 E-3 NEW 2ND-4TH FL LIGHTING PLAN 22 JUL 20
66 E-4 LIGHTING FIXTURE DETAILS-1 22 JUL 20
67 E-5 LIGHTING FIXTURE SCHEDULE AND LIGHTING 22 JUL 20
E-6
FIXTURE DETAILS-2
NEW 1ST FL POWER PLAN
69 E-7 NEW 2ND-4TH FL POWER PLAN 22 JUL 20
70 E-8 TYPICAL MODULE ELEC. PLAN-A & PLAN-B, MECH. 22 JUL 20
E-9
RM POWER & CONTROL PLAN
NEW 1ST FL FIRE ALARM / MASS NOTIFICATION
E-10
SYSTEM PLAN
NEW 2ND-4TH FL FIRE ALARM / MASS NOTIFICATION
E-11
SYSTEM PLAN
NEW FIRE ALARM / MASS NOTIFICATION SYSTEM
E-12
DIAGRAM
NEW 1ST FL CCTV / CATV / TEL PLAN
75 E-13 NEW 2ND-4TH FL CCTV / CATV / TEL PLAN 22 JUL 20
76 E-14 CCTV SYSTEM DIAGRAM 22 JUL 20
A-3
APPENDIX B
APPENDIX "B"
List of materials for Material Approval Submittal
Submittal
Identification Description of Submittal
LC-1 Ready Mixed Conc. 240kg/cm2
LC-2 Steel Bar Reinforcing
LC-3 Base Course
LC-4 #8-150x150 WWF
LC-5 Hot mixed Asphalt Concrete #67
LC-6 CHERRY BLOSSOM TREE
LC-7 Granite Curb
LA-1 Vapor barrier, 0.1mm
LA-2 Waterproofing wall membrane with asphalt primer, compound & felt
LA-3 EIFS incl. mesh, base coat, finish coat and control joint
LA-4
Steel thermal insulated blast double door w/steel frame door size: 1,714 W X 2150 H X 44.5 Thk.
LA-5
Steel thermal insulated double door w/steel frame door size: 1,714 W X 2133 H X
44.5 Thk. w/louver
LA-6
Steel insulated thermal blast door with steel frame door size; 915W. X 2133H. X
44.5 Thk. 100 X 600 insulated fire glass
LA-7
Steel insulated thermal blast door with steel frame door size; 915W. X 2133H. X
44.5 Thk.
LA-8
Steel hollow core door, 3/4 hrs fire rate w/frame door size; 915W. X 2133H. X 44.5 Thk. 100 X 600 insulated fire glass
LA-9
Steel hollow core door, 1 hrs fire rate w/frame door size; 915W. X 2133H. X 44.5 Thk.
LA-10
Steel hollow core single door w/frame door size; 915W X 2133H. X 44.5 Thk., 100x600 tempered glass
LA-11
Wood solid core double door w/frame door size; 1,714W X 2133H X 44.5 Thk.
W/100 X 600 insulated glass
LA-12
Wood solid door, 20 Min fire rate door, w/frame door size; 864W. X 2133H. X 44.5 Thk.,STC door
Description of Submittal
LA-13
Wood solid core single door w/frame, 19mm under cut door size; 714W. X 2033H.
X 44.5 Thk.
LA-14
Hollow wood flush door, single sliding pocket door w/wood frame door size; 914W X 2133H X 34.9 Thk. Mirror Glass 600x1200
LA-15 Wood full louver door with wooden frame;714W. X 2033H. X 44.5 Thk.
LA-16 Wood solid door w/frame door size; 900W X 2085H X 44.5 Thk
LA-17
Electronic card key lockset,HT-24 ONITY Co.,4ea card key, 3ea mechanical key, master key system including 4ea of battery
LA-18 Exit device, type 2, F-01
LA-19 Exit device, type 2, F-08
LA-20 Lockset, F-07
LA-21 Lockset, F-75
LA-22 Lockset, F-76
LA-23 Lockset, F-82
LA-24 Lockset, F-86
LA-25 Dead bolt, E0161
LA-26 Dead bolt, E0151
LA-27 Sliding door lock, E8231
LA-28 Door closer, C02021
LA-29 Door closer, C02011
LA-30 Hinge, butt, 127X114 (NRP)
LA-31 Hinge, butt, 114X114 (NRP)
LA-32 Hinge, butt, 114X114
LA-33 Hinge, B013514
LA-34 Door stop & holder L01371
LA-35 Door holder , L01381
LA-36 Door stop , L02161
LA-37 Door stop , L02141
LA-38 Push plate, J301
LA-39 Pull plate, J405
LA-40 Door pull, J401
LA-41 Automatic door bottom Roy 335
LA-42 Kick plate, J102
LA-43 Door viewer, L03221
LA-44 Flush bolt, L04081
LA-45 Astragal
LA-46 Adjustable astragal
Description of Submittal
LA-47 Soundproof seal R0Y265 for head and jam
LA-48 Weather stripping, R0y165&415
LA-49 Card holder, AL, 125 x 125
LA-50 Plexi-info holder, acrylic case, 224 x 287 x 6THK w/double emulsion form tape
LA-51 Threshold, aluminum, 150W, SGL
LA-52 Threshold, aluminum, 150W DBL
LA-53 SSM Thresholder, 150w x 800mm
LA-54 Key box, E8351
LA-55 Box Track Support D8271 & D8281
LA-56 Semi Auto Closing system, sliding, DAIKEN HLS-80
LA-57 Sliding door lock, E8231
LA-58 Door pull, D8421
LA-59
Aluminum blast window thermal break type, sliding window, 1220x1016, 26.75thk Low-e insulated glass, insect screen
LA-60
Aluminum blast window thermal break type, sliding window, 1061x900, 26.75thk Low-e insulated glass, insect screen
LA-61
Aluminum blast window thermal break type, sliding window, 610x1061, 26.75thk Low-e insulated glass, insect screen
LA-62
Aluminum sliding window thermal break type, sliding window, 1200x1016, 24.3thk Low-e insulated glass, insect screen
LA-63
Aluminum sliding window thermal break type, sliding window, 1220x1016, 10 THK tempered glass
LA-64 Horizontal blinds, 1" aluminum slats
LA-65 C-150 x 75 x 25 x 3.2 (8.27kg/m)
LA-66 Chemical Anchor M-08
LA-67 Metal stud, 0.8 mm x 45 mm x various W/expansion bolt
LA-68 Metal runner, 0.8 mm x 45 mm x various W/expansion bolt
LA-69 Metal ceiling suspension system for GWB
LA-70 Acoustical ceiling suspension system, aluminum
LA-71 Gypsum board, 15mm thk x1,200 x2,400, normal
LA-72 Gypsum board, 15mm thk x1,200 x2,400, fire resistant or X
LA-73 Gypsum board, 12mm thk x1,200 x2,400, normal
LA-74 Gypsum board, 12mm thk x1,200 x2,400, water resistant or X
LA-75 Gypsum board, 12mm thk x1,200 x2,400, fire rated
LA-76 Acoustical tile, 600x600x16mm thk.
LA-77 Non-sip ceramic floor tile
LA-78 Epoxy joint grout mortar
Description of Submittal
LA-79 Glazed ceramic wall tile with accessories
LA-80 Quarry tile and quarry tile base
LA-81 PVC tile, KCC Neo Sense, 450 x 450 x 3Thk
LA-82 Vinyl cove base w/adhesive
LA-83 Rubber stair treads, 480 x 1200 x 3THK
LA-84
Rubber tile, size 500mm x 500mm x 3 THK, I-BADKA rubber flooring
LA-85 Rubber Base, 2THK
LA-86 Rubber stringer & risers, 178mm H X 2 THK
LA-87 Adhesive for flooring
LA-88 Paint, MPI 57, varnish
LA-89 Paint, MPI 11, acrylic emulsion, exterior
LA-90 Paint, MPI 54, latex, interior
LA-91 Paint, MPI 47, enamel, interior
LA-92 Paint, MPI 94, enamel, exterior
LA-93 Paint, MPI 79, primer for metal
LA-94 Texture coat, terracotta 25kg w/finish coat
LA-95
Noroo Paint, MPI 77, Epoxy Epoxy Paint Include Surface Preparation Base, Cleanpoxy3100, MPI77, 0.175L/M2 Mid, Cleanpoxy3100, MPI77,0.15L/M2 Top, Cleanpoxy3100, MPI77,0.15L/M2
LA-96 Toilet tissue dispenser, Double Roll, Horizontal Type
LA-97 Paper towel dispenser
LA-98 Towel bar
LA-99 Soap holder, recessed type
LA-100 Mirror, 1000 x 1420 with plywood back board
LA-101 Shower curtain with rod, 1,800W Curtain
LA-102 Medicine cabinet with mirror, 410MMx510MM
LA-103 Soap dispenser, liquid, wall type, SST
LA-104 Mop rack with STS shelf
LA-105 SST metal shelf for laundry room, 3500 x 300 with accessories
LA-106 S.M.L.D (Shelf Metal Light Duty)
LA-107 Brass hook, STS & Wood, 3450mm LG, 8 Hooks
LA-108 Signage, interior
LA-109 Signage, exterior
LA-110 Card holder, AL, 125 x 125
Description of Submittal
LA-111 Plexi-info holder, acrylic case, 224 x 287 x 6THK w/double emulsion form tape
LA-112 Kitchen Cabinet base & top, SSM Counter Top W/Plastic Laminate Finish
LA-113 Vanity cabinet, laminated counter top
LA-114 Wooden shelf w/STS hanging rod for closet
LA-115 Window trim, oak, 110W x 90W x 18Thk
LA-116 Wooden hanging rail, oak, 100W x 40Thk
LA-117 Plastic laminated
LA-118 Fire extinguish cabinet
LA-119 Plywood 18T with plastic laminate
LA-120 Acrylic fluid applied waterproofing
LA-121 Fiber glass, FG. 24K. 100mmThk
LA-122 Fiber glass, blanket w/VB. FG. 24K. 50mmThk
LA-123 EPDM roof 1.52T, Insulation 110T and top coating
LA-124 Access door, 250x250
LA-125 Access door, 450x450
LA-126 Access door, 600x600
OA-1
Wood solid door, 45 Min Fire Rate Door, door size; 1066W. X 2133H. X 44.5 Thk., 100x600 fire glass
OA-2 Sound absorption wall panel, Tectum standard, 50T
OA-3 Exit device, type 3, F-08
LM-1 Air Cooled Water Chiller
LM-2 Air Handling Unit, various capacity
LM-3 Split type air conditioning unit
LM-4 Fan coil unit, various capacity
LM-5 Thermostat for FCU
LM-6 Balacing valve cock
LM-7 Ball valve cock
LM-8 Fresh air wall box w/ motorized air demper
LM-9 Flue vent
LM-10 Black steel pipe line including fittings & pipe hangers, various size
LM-11 Pipe flexible cellular insulation w/adhesive, various size
LM-12 Gate valves, various size
LM-13 Balancing valve, various size
LM-14 Y-type strainer
LM-15 Diffusers, various size
LM-16 Registers, various size
LM-17 Duct w/accessories, various size
Description of Submittal
LM-18 Duct insulation w/accessories, various size
LM-19 Volume dampers, various size
LM-20 Pipe flexible connector
LM-21 Volume dampers, various size
LM-22 Water closets
LM-23 Lavatories w/ faucet
LM-24 Shower units
LM-25 Kitchen sinks w/ faucet
LM-26 Laundry sinks, double compartment
LM-27 Service sinks with faucet
LM-28 Hot water storage tank
LM-29 Water hammer arrester, various size
LM-30 Copper tube water line, including fittings & pipe hangers, various size
LM-31 Galvanized steel pipe with fittings & hangers, various size
LM-32 Vent thru roof
LM-33 Cast iron soil pipe with coupling incl accessories, various size
LM-34 P-trap, cast iron soil pipe, various size
LM-35 Floor cleanouts, various size
LM-36 Floor drains
LM-37 Grooved 90, elbow, various size
LM-38 Grooved tee, various size
LM-39 Grooved cap
LM-40 Grooved coupling, various size
LM-41 Valve flange adapters, various size
LM-42 Clevis pipe hanger, various size
LM-43 4-way bracing, various size
LM-44 Pipe support
LM-45 Hanger rod
LM-46 Sprinkler system shop drawing, calculatio, test & report
OM-1 Hot Water Boiler
OM-2 Hot water circ. Pump
OM-3 Domestic hot water circ. pump
OM-4 Domestic hot water re-circ. pump
OM-5 In-line duct mounted fan, various capacity
OM-6 Ceiling mounted exhaust fan, various capacity
OM-7 Roof mounted exhaust fan, various capacity
OM-8 Unit heater
Description of Submittal
OM-9 Elec. Unit heater
OM-10 Expansion tank
OM-11 Air separator
OM-12 Chemical feeder
OM-13 O.A. moptorized damper motor
OM-14 Duct mounted heating thermostat
OM-15 Freezestat
OM-16 7-day timer
OM-17 O.A. thermostat
OM-18 Ventilation thermostat
OM-19 Aquastat for pipe mtd
OM-20 Duct mounted smoke detector
OM-21 Pressure gauge
OM-22 Auto air vent
OM-23 Pressure gauge
OM-24 Suction diffuser
OM-25 Range hood
OM-26 Electric water cooler
OM-27 Backflow preventer
OM-28 Pressure reducing valve
OM-29 3-way thermostatic mixing valve
OM-30 Hose bibb
OM-31 Washer connector box
OM-32 Alarm check valve
OM-33 Backflow preventer
OM-34 OS & Y valves, various size
OM-35 Tamper switch
OM-36 Ball valve switch
OM-37 Pressure switch
OM-38 Water motor alarm bell
OM-39 Check valve
OM-40 Fire department connection
OM-41 Ball drip valve
OM-42 Teat header
OM-43 Hose valve w/cap & chain
OM-44 Test valve
OM-45 Water flow switch
B‐8
Description of Submittal
OM-46 Sight glass
OM-47 Smooth bore corrosion resistant
OM-48 Residential pendent sprinkler head
OM-49 Quick response pendent sprinkler head, various size
OM-50 Quick response up-right sprinkler head, various size
OM-51 Quick response dry wall type sprinkler head
OM-52 Spare sprinkler head cabinet
LE-1 Lighting fixture, exit sign stencil face LED, red lamp, LED lamp, type "NS-3"
LE-2 LED lighting fixture, 25 Watt, recessed mounted, type "NS-4a & 4b", power unit
LE-3 LED lighting fixture, 45 Watt, recessed mounted, type "NS-5a & 5b", power unit
LE-4 LED lighting fixture, 18 Watt, surface mounted, type "NS-6", power unit, wet location
LE-5
LED lighting fixture, 18 Watt ,wall mounted, type "NS-7",power unit (AC to DC), mirror top
LE-6
LED lighting fixture, 18 Watt, recessedl mounted, type "NS-8",power unit (AC to DC), down light
LE-7 LED lighting fixture, 50 Watt , pendant mounted, type "NS-9a & 9b", power unit
LE-8
LED lighting fixture, 18 Watt, recessedl mounted, type "NS-10",power unit (AC to DC), down light w/dimming control
LE-9 LED lighting fixture, 50 Watt, recessed mounted, type "NS-11a & 11b", power unit
LE-10
LED lighting fixture, 45 Watt, surface mounted, type "NS-12a & 12b", power unit, down light
LE-11 LED lighting fixture, 22 Watt, wall mounted, type "NS-13", power unit, exerior type
LE-12 LED lighting fixture, 18 Watt , type "NS-14",power unit (AC to DC), under cabinet
LE-13 SingleJack Outlet for "Telephone" system
LE-14 Coaxial Cable, RG11/U
LE-15 Coaxial Cable, RG6/U
LE-16 Pullbox w/ 8-way tap off and locking device
LE-17 Cable TV Outlets w/screw-tight cover
LE-18 Electric wires various
LE-19 Rigid steel conduit various
LE-20 Shop drawing for fire alarm control system
OE-1 Toggle switch, w/plate, 1P-20A-120VAC
OE-2 3-way toggle switch, w/plate, 1P-20A-120VAC
OE-3 Dimmer switch
OE-4 3-position sellector switch, "HAND-OFF-AUTO", "WP" housing
OE-5 Photoelectric control , 1P-120V, 1800 Watt max.
OE-6 Duplex receptacle, w/plate, 2P-20A-125VAC, gnd. Type
W91QVN20R0218
Description of Submittal
OE-7 Single receptacle, w/plate, 2P-20A-125VAC, gnd. Type
OE-8 Duplex receptacle, w/plate, 2P-20A-125VAC, GFCI Type
OE-9 Single receptacle, w/plate, 3P-30A-4W-125/250VAC, gnd. Type
OE-10 Single receptacle, w/plate, 4P-30A-4W-125/250VAC, gnd. Type
OE-11 Single receptacle, w/plate, 3P-50A-4W-125/250VAC, gnd. Type
OE-12 Safety switch, 3PST 600A-240V, 450A fuses, NEMA 3R. Encl
OE-13 Combination type magnetic motor starters
OE-14 Magnetic motor starters
OE-15 Manual motor starter
OE-16 Branch ciircuit breakers
OE-17 Advanced watt hour meter
OE-18 CATV cabinets
OE-19 Addressable fire alarm/mass notification control panel
OE-20 Addressable smoke detector w/sound base
OE-21 Combination fire alarm & MNS Speaker/Strobe
OE-22 Combination fire alarm & MNS Speaker "WP"
OE-23 Addressable module
OE-24 Addressable manual pull station
OE-25 Addressable carbon monoxide detector
OE-26 Coaxial cable, w/connector, type 1 and 2
Section K - Representations, Certifications and Other Statements of Offerors
CLAUSES INCORPORATED BY REFERENCE
52.203-2 Certificate Of Independent Price Determination APR 1985
52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (AUG 2020)
The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in the provision at 52.204-26, Covered Telecommunications Equipment or Services--Representation, or in paragraph (v) of the provision at 52.212-3, Offeror Representations and Certifications-Commercial Items.
(a) Definitions. As used in this provision-
Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services."
(d) Representations. The Offeror represents that--
(1) It [ ] will, [ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds "will" in paragraph (d)(1) of this section; and
(2) After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that--
It [ ] does, [ ] does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.
(e) Disclosures.
(1) Disclosure for the representation in paragraph (d)(1) of this provision.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .