W91QVN18R0231
Section SF 30 - BLOCK 14 CONTINUATION PAGE
SUBJECT TO THE AVAILABILITY OF END-OF YEAR FUDNS (SAEF)
"Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available."
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Job |
REPAIR LIGHTS W/NEW LED, S-4203
FFP
REPAIR LIGHTS W/NEW LED, S-4203, YONGSAN.
FOB: Destination
PURCHASE REQUEST NUMBER: 0011223829
PSC CD: 5670
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Estimated Cost for War Hazard
FFP
is Zero(0).
FOB: Destination
NET AMT
Section C - Descriptions and Specifications
TECHNICAL PROVISIONS - I
STATEMENT OF WORK 11 July 2018
| PWO |
| TITLE |
| LOCATION |
| 194345 |
| REPAIR DETERIORATED LIGHTS WITH NEW LED, |
B-4203 Yongsan
1. DESCRIPTION: Contractor shall provide all labor, tools, equipment, supplies, and any other resources necessary to accomplish the scope of work contained herein and as included in the drawings and specifications.
2. PERFORMANCE PERIOD: The contractor shall complete this project within 60 days after NTP is issued.
3. PRINCIPAL FEATURES: This project includes, but will not be limited to, the following principal features:
A. Repair and Maintenance ("K" work)
1) Electrical:
a) Replace deteriorated existing lighting fixtures and EXIT lights with new(LED).
* LED types
· NS-3: wall or ceiling surface mounted light emitting diode(LED) EXIT light fixture, 1PH, 120V, 4.99W(max input), battery back-up with battery charger, single face as required.
· NS-4a & 4b: ceiling recessed mounted light emitting diode (LED) fixture, 1PH, 120V, 45W, with converter & accessories (NS-4a) & with EM unit (NS-4b) as required.
· NS-5a & 5b: ceiling recessed mounted light emitting diode (LED) fixture, 1PH, 120V, 50W, with converter & accessories (NS-5a) & with EM unit (NS-5a) as required.
· NS-6a & 6b: ceiling recessed mounted light emitting diode (LED) fixture, 1PH, 120V, 50W, with converter (dimming control) & accessories (NS-6a) & with EM unit (NS-6b) as required.
· NS-3: wall surface mounted light emitting diode (LED) fixture, 1PH, 120v, 18W, with converter & accessories as required.
· NS-8: wall mounted LED light fixtrure, 1PH, 120V, 22W, wet location type, with converter & accessories as required.
· NS-9: ceiling surface mounted light emitting diode (LED) fixture, 1PH, 120V, 18W, with converter & accessories, wet location shower light trim, UL listed power unit as required.
· NS-10a & 10b: ceiling recessed mounted light emitting diode (LED) fixture, 1PH, 120V, 25W, with converter & accessories (NS-10a) & with EM unit (NS-10b) as required.
· NS-11: ceiling surface mounted LED light fixture outdoor type, 1PH, 120V, 22W w/converter & accessories as required.
· NS-12a & NS-12b: ceiling surface/pendant mounted light emitting diode (LED) fixture, 1PH, 120V, 45W, UL listed, with converter and accessories (NS-12a) and EM unit (NS-12b) as required.
· NS-13: under cabinet LED light fixture 1PH, 120V, 18W, converter and accessories as required.
* Note
i. The furniture movement which is associated with the contractor’s responsibility.
ii. Contractor should install additional power wiring for emergency light sets if not exist where as required on this contract drawing.
iii. Paint if require, depending on the work.
TECHNICAL PROVISIONS – II
TECHNICAL DETAIL SPECIFICATIONS
GENERAL: The specification sections listed below, but not limited to, are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the 411th CSB Web Page, http://www.usfk.mil/Resources/ContractingwithUSFK.aspx. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.
STANDARD TECHNICAL SPECIFICATIONS FOR O&MA
PROJECT TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
| 01 30 00 | ADMINISTRATIVE REQUIREMENTS |
| 01 32 01.00 10 | PROJECT SCHEDULE |
| 01 33 00 | SUBMITTAL PROCEDURES |
| 01 35 26 | GOVERNMENTAL SAFETY REQUIREMENTS |
| 01 45 00.00 10 | QUALITY CONTROL |
| 01 50 00 | TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS |
| 01 58 00 | PROJECT IDENTIFICATION |
| 01 78 00 | CLOSEOUT SUBMITTALS |
| 01 78 23 | OPERATION AND MAINTENANCE DATA |
DIVISION 26 – ELECTRICAL
| 26 00 00.00 20 | BASIC ELECTRICAL MATERIALS AND METHODS |
| 26 51 00 | INTERIOR LIGHTING |
TECHNICAL PROVISIONS - III
SPECIAL CONDITIONS
1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which form a part of the contract.
2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours, from 1 October through 30 April and from 0730 hours through 1930 hours from 1 May through 30 September, Mondays through Saturdays, except for Korean Legal Holidays: Any proposed change in working hours should be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR). The contractor will not be permitted any construction work during scheduled (15 days in March and 15 days in August) and unscheduled training/exercises. The contractor shall remove heavy equipment and field offices from CP Tango and K-16 training sites during the training/exercises periods.
3. WINTERIZATION: The contractor may be required to perform weather sensitive work during the winter season, which may cause additional costs to be incurred for the contractor. These additional costs are the contractor’s responsibility in the event you are required to work during the winter. Your responsibility regarding the preparation of the proposal is to reflect these additional costs in your proposal.
4. ESCORT PRIVILEGE: The contractor shall be responsible for requesting escorting privileges on base passes for Project Manager, Quality Control Manager, Safety Specialist and Foremen. The maximum number of escorted employee will be three persons and the number of escorted vehicle will be one. The contractor shall ensure that the escorting employee has full control of all escorted individuals at all times. Any individual found on the installation unescorted will be removed from the installation and the escort employee’s escorting privileges will be withdrawn. Any individual removed from this installation will not be authorized further access to this installation.
5. DISPOSAL OF CONSTRUCTION DEBRIS/WASTE MATERIALS: The Contractor shall be required to dispose all construction debris and waste materials in strict accordance with disposal requirements of Section 024100, Demolition and Deconstruction, and local laws and regulations at the Contractor’s responsibility and his own expense. The waste/unsalvageable materials shall be disposed at the location(s) approved and designated by the local authorities.
Section F - Deliveries or Performance
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 calendar days after notice to proceed (NTP) is issued.
* The time stated for completion shall include final cleanup of the premises.
(End of clause)
Section G - Contract Administration Data
Section H - Special Contract Requirements
AT/OPSEC
ANTITERRORISM/OPERATIONS SECURITY REVIEW COVER SHEET
1. AT Level 1 Training: All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 14 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 14 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.
1. Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
1. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 14 calendar days of contract award and within 14 calendar days of new employees commencing performance with the results reported to the COR NLT 14 calendar days after contract award.
1. OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
Section J - List of Documents, Exhibits and Other Attachments
LIST OF APPLICABLE CONTRACT DRAWINGS
GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), located on the 411th CSB Web Page, http://www.usfk.mil/Resources/ContractingwithUSFK.aspx all of which form a part of the specifications.
| Ring No. |
| Sheet No. |
| Description |
| Date |
| 1 |
| T-1 |
| Title Sheet |
| 11 Jul 18 |
ELELCTRICAL
| 2 |
| E-1 |
| Legend, General notes and Scope of work |
| 11 Jul 18 |
| 3 |
| E-2 |
| Lighting plan |
| 11 Jul 18 |
| 4 |
| E-3 |
| Lighting fixture details |
| 11 Jul 18 |
SUBMITTAL REGISTER
NOTE 1. See the attachment.
NOTE 2. The Submittal Register in Section J above, identifies the documentation that will be made available for approval and review by the Government in the performance of this task order. It is the contractor's responsibility that this data is in compliance with the corresponding OMA specification that is referenced.
Section K - Representations, Certifications and Other Statements of Offerors
52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)
(a) The offeror certifies that --
(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –
(i) Those prices,
(ii) The intention to submit an offer, or
(iii) The methods of factors used to calculate the prices offered:
(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and
(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.
(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --
(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or
(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);
(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and
(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.
(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.
(End of Provision)
252.209-7999 Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction under any Federal Law REPRESENTATION BY CORPORATIONS REGARDING AN UNPAID DELINQUENT TAX LIABILTIY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW (DEVIATION 2012-00004) (JAN 2012)
1. In accordance with sections 8124 and 8125 of Division A of the Consolidated Appropriations Act, 2012, (Pub. L. 112-74) none of the funds made available by that Act may be used to enter into a contract with any corporation that-
(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless the agency has considered suspension or debarment of the corporation and made a determination that this further action is not necessary to protect the interests of the Government.
(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless the agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.
1. The Offeror represents that –
(1) It is ( ) is not ( ) a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with authority responsible for collecting the tax liability,
(2) It is ( ) is not ( ) a corporation that was convicted of a felony criminal violation under a federal law within the preceding 24 months.
(End of provision)
5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS
(a) SUBCONTRACTING:
If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.
(b) AFFILIATED OFFERORS:
(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.
(2) Each offeror shall furnish, below, the following information:
(i) Whether the offeror has any affiliates;
(ii) The names and addresses of all affiliates of the offeror; and
(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.
AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)
(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):
Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.
(d) STANDARDS OF CONDUCT CERTIFICATION:
This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.
(i) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
(ii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
(iii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
Firm ____________________________________________________ Name _____________________________________________________ Signature __________________________________________________
Title _____________________________________________________ Date of Execution ____________________________________________
(e) TAXES:
(1) References:
(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."
(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.
(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.
(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.
(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
This item will be imported specifically for this contract? Yes _____ No _____
(ii) Special Excise Tax:
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
Name of item manufacturer
(iii) Value Added Tax (VAT):
Input VAT on materials purchased for this contract. 10% _____ Input VAT on transportation leased/rented for this contract.10% _____ Input VAT on equipment leased/rented for this contract. 10% _____ Input VAT on services purchased for this contract. 10% _____ Output VAT on total contract amount. 10% _____
(iv) Special Excise (Petroleum) Tax:
No. of U/P Liters w/o Tax Tax/Unit Total Tax Amount Regular Gasoline ________ (L) ________ w________ w_____________ Premium Gasoline ________ (L) ________ w________ w_____________ Diesel ________ (L) ________ w________ w_____________ Other ________ (L) ________ w________ w_____________
(v) Education Tax.
(3) Name of the oil company from which POL products will be purchased:
Oil Company: _________________________________________ (Name only)
(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.
Signed (Chop)
(f) CERTIFICATIONS AND REPRESENTATIONS
By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation. The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.
Section L - Instructions, Conditions and Notices to Bidders
INSTRUCTION TO OFFEROR
SECTION L
1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL:
The Government intends to award without discussion, but reserves the right to conduct discussions if deemed necessary and to establish a competitive range for efficiency in accordance with FAR 52.215-1(f)(4).
Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted.
2. SUBMISSION OF PROPOSAL:
i) FBO SUBMISSION REQUIRED: Offers shall be submitted to the Federal Business Opportunities (FBO) website (https://www.fbo.gov/), or if FBO is not available, email to chusong.yi2.ln@mail.mil with the evidence document such as screen shot. The FBO unavailability is limited to only FBO server problem not individual failure/problem. All questions should be emailed to chusong.yi2.ln@mail.mil within five (5) days after the solicitation is issued.
ii) CLOSING DATE: The electronic offer shall be submitted by 1500 hours on the closing date of RFP.
iii) SUBMISSION REQUIREMENTS
a) PRICING PROPOSAL: The pricing proposal must clearly indicate prices for each Contract Line Item Number in Section B - Supplies or Services and Prices.
b) DETAILED OFFER BREAKDOWN: The detailed offer breakdown must clearly identify all costs that can materially impact the statement of work.
c) SECTION K - Representations, Certifications and Other Statements of Offerors
SECTION K-TAXES: Offerors must complete all tax portions of SECTION K. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, offerors shall propose exemptions of specific ROK taxes that are legitimate, attributable to the contract, and authorized by the applicable stated references.
SECTION K-OTHER: Offerors must complete all Non-Tax related portions of SECTION K.
iv) COMPLIANCE WITH SOLICITATION: Failure to submit the above requirements under SECTION L may be grounds for determining the proposal to be non-compliant. For example, if a detailed offer breakdown is not submitted, the contracting officer will be unable to find the offeror's pricing proposal acceptable and the offeror's proposal will be ineligible for award. Non-compliance will only be cured if the government holds discussions as detailed in SECTION L.
52.232-18 AVAILABILITY OF FUNDS (APR 1984)
Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.
(End of clause)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for--
When: 23 Aug 2018, 15:00 Where: B4203, Yongsan POC: Mr. Kim, Chong Pil, DSN)724-4490, Cell: 010-4289-7000
(End of provision)
5152.236-4011 CONSTRUCTION PRICE RANGE
Pursuant to FAR 36.204 the estimated price range is between $ 25,000 and $ 100,000.
Section M - Evaluation Factors for Award
BASIS OF AWARD
Electronic offers submitted by 1500 hours on the closing date of RFP shall be considered timely.
i) EVALUATION CRITERIA
The pricing proposal shall be evaluated to determine whether it is complete and reasonable. A complete and reasonable pricing proposal will be deemed acceptable.
The detailed offer breakdown will be used by the contracting officer to determine whether proposed prices are complete and reasonable. A detailed offer breakdown may be used by the contracting officer to determine whether an offeror is able to complete the requirements under the contract, and/or whether discussions will be conducted pursuant to instructions to the offerors.
ii) SECTION K - Representations, Certifications and Other Statements of Offerors
a. SECTION K-TAXES will be evaluated to determine whether it is complete. In addition, propose exemptions of specific ROK taxes will be evaluated to determine whether they are legitimate, attributable to the contract, authorized, and reasonable. A complete SECTION-K that only proposes exemptions of specific ROK taxes that are legitimate, attributable to the contract, necessary to complete the Task Order, do not improperly overstate any proposed tax exemption, authorized, and reasonable will be deemed acceptable.
b. SECTION K-OTHER will be evaluated to determine whether it is complete. A complete SECTION K-OTHER will be deemed acceptable.
BASIS FOR AWARD: Award shall be made to the responsible offeror submitting the lowest priced offer that is evaluated as acceptable for all evaluation criteria.
image1.wmf image2.wmf