AMEND_SECTION_B_FOR_W9133L-14-R-0053.docx

DOCX document 20 KB Posted

Attached to
GSU PHASE V
Solicitation number
W9133L-14-R-0053
Issued by

About this file

Revised Schedule B

View the file

Other files

File Type Posted
AMENDMENT_06_FOR_W9133L-14-R-0053_GSU.doc DOC document
14_R-0053_AMEN_05_GSU.doc DOC document
W9133L-14-R-0053_AMENDMENT_4.doc DOC document
W9133l-14-r-0053_amendment_03_revised.doc DOC document
r-0053_first_page.doc DOC document
GSU_ANSWERS__Answers_Part_2.doc DOC document
Phase_VI_W9133L_14_R_0053_Questions_PART_1.xls XLS spreadsheet
A6X-14-015_GSU_POC_List_for_Phase_6.docx DOCX document
Amendment_3_of_14R0053.doc DOC document
GSU__answers_part_3.doc DOC document
gsu_revisePWS.docx DOCX document
GSU_AMEDNMENT_2.doc DOC document
AMENDMENT_01.doc DOC document
A6X-14-015_PWS_GSU_MOD_ITS_Project_v3_GSU_VI.docx DOCX document
Solicitation_W9133L-14-R-0053.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised SECTION B FOR W9133L-14-R-0053

Section SF 1449 - CONTINUATION SHEET

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

LABOR

FFP

lABOR COST FOR A6 GSU INFORMATION TRANSPORT SYSTEM PHASE VI WHICH CONSIST OF SITE SURVEYS AND DESIGN FOR 9 GSU'S FOB: Destination

PURCHASE REQUEST NUMBER: F9WFC44135AC02

SIGNAL CODE: A

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

TRAVEL FOR A6 GSUS

TRAVEL COST FOR A6 GSU INFORMATION TRANSPORT SYSTEM PHASE VI GSUFOR SITE SURVEYS FOR 9 GSU'S.

FOB: Destination

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
$2,732,048.20 NTE
$2,732,048.20 NTE

MATERIALS FOE A6 GSUS

NTE

MATERIALS COST FOR A6 9GSUS INFORMATION TRANSPORT SYSTEM PHASE VI FOR 9GSUS SEE LIST OF MATERIALS..

FOB: Destination

NET AMT
$2,732,048.20 NTE
ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
$2,556,938.52 NTE
$2,556,938.52NTE

LABOR FOR A6 INSTALLATION FOR GSU'S

NTE

LABOR COST FOR INSTALLATION OF A6 GSU INFORMATION TRANSPORT SYSTEM PHASE VI FOR 9GSUS.

FOB: Destination

NET AMT $2,556,938.52 NTE

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot

TRAVEL FOR A6 GSU'S

TRAVEL COST FOR A6 GSU INFORMATION TRANSPORT SYSTEM PHASE VI FOR 9 GSUS.

FOB: Destination

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1
Lot
$424,491.10 NTE
$424,491.10 NTE

OTHER DIRECT COST FOR A6 GSU PROJECT

OTHER DIRECT COST FOR A6 GSU INFORMATION TRANSPORT SYSTEM PHASE VI FOR 9 GSU'S.

FOB: Destination

NET AMT $424,491.10NTE

0007 TOAL AMOUNT FOR CLIN 00001-0006 _________________________________________

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN
INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
0001
Destination
Government
Destination
Government
0002
Destination
Government
Destination
Government
0003
Destination
Government
Destination
Government
0004
Destination
Government
Destination
Government
0005
Destination
Government
Destination
Government
0006
Destination
Government
Destination
Government