Amendment W912WJ19Q0113-0002

View the file

Other files

File Type Posted
Amendment_W912WJ19Q0113-0001.pdf PDF
Solicitation_W912WJ19Q0113.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W13G86914816380001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment is necessary to provide responses to a Request for Information. Closing w ill be extended until August 9, 2019 at 5:00 PM.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 31-Jul-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ19Q0113

X 9B. DATED (SEE ITEM 11)

11-Jul-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-Jul-2019

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

Sheila.M.Winston@usace.army.milEMAIL:978-318-8159TEL:

SHEILA M WINSTONVINCUILLA / CONTRACT SPECIALIST

W912WJ19Q0113

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUEST FOR INFORMATION

1. What are the specifications for the limit switches that will be required.

Answer: The limit switches shall be those of a make and model that are compatible with the Programmable Logic Controller (PLC).

2. Will aluminum conduit be an approved equal to stainless steel conduit?

Answer: Conduit shall be stainless steel. Aluminum will not be approved.

3. Will the existing operators be able to be temporarily energized electronically so the existing conduit can be removed leaving space for the new conduit?

Answer: Disconnecting the electrical connection should be done in a manner to minimize down time for the operators. Portable actuators (drills) are available to serve as backup to move operators while the power is disconnected.

4. Do you have examples of vandal proof lighting you would like to see used?

Answer: Vandal proof lighting shall have the following characteristics:

1. All metal wire guard

2. Minimum of 7 GA steel round wire

3. Screw eyes for mounting

4. Material shall be stainless steel

5. The specifications talk about operating at six inches per minute, is this assumed to be done via variable frequency drives, or gearing? And will speeds vary?

Answer: The current operators utilize gearing. The minimum speed that will deemed to be acceptable is six inches per minute. Speeds may be increased to more than six inches per minute with the new operators, but may not be lower than six inches per minute.

6. The lead time from a local manufacturer is 10 weeks for the operators. Can the Period of Performace be extended to account for the manufacturer lead time?

Answer: The Period of Performance has been revised in the Statement of Work from 90 days after Notice to

Proceed to 120 days from Notice to Proceed.

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 02-Aug-2019 05:00 PM to 09-Aug-2019 05:00 PM.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

STATEMENT OF WORK

WEST HILL DAM

SLUICE GATE OPERATOR AND CONTROL REPLACEMENT

US ARMY CORPS OF ENGINEERS

STATEMENT OF WORK

UXBRIDGE, MA

I. GENERAL

1. Scope Furnish all equipment, materials and labor for the West Hill Dam sluice gate operator and control replacement (x3), at the West Hill Dam Project in Uxbridge, MA, for the purpose of facility maintenance.

2. Location The required services shall be performed at the following project site location:

518 East Hartford Ave, Uxbridge, MA.

3. Site Visits and Requests for Information Contact the Technical Point of Contact, Joe Zanca 978-318-8419 or joseph.l.zanca@usace.army.mil to arrange a site visit.

4. Schedule The period of performance shall be 90 120 days from Notice to Proceed. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:30 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.

5. Safety The contractor will comply with all pertinent provisions of the latest edition of the U.S.

Army Corps of Engineers Safety and Health Requirements COE EM 385-1-1. A copy of COE EM 385-1-1 is available for reference at the project office or the manual may be viewed at the following link http://www.usace.army.mil/SafetyandOccupationalHealth/EM38511,2008BeingRevised.

aspx The contractor shall also comply with all OSHA work safety standards. The project staff can and will order the cessation of work at any time should the safety of employees and visitors become jeopardized.

6. Preconstruction Conference Prior to the start of any site work, the Technical Point of Contact will schedule and conduct a “Preconstruction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No site work may be performed under this contract prior to this conference. The purpose of the conference is to enable the

Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Preconstruction conference the contractor shall provide to the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Preconstruction Conference:

Authority of the Technical Point of Contact.

Contractor’s Safety Program (including sub-contractors).

Accident Prevention Plan and Activity Hazard Analysis.

Weekly Safety Meetings (Documented on NED Form 251) Accident Reporting (ENG Form 3394) Safety Data Sheet (SDS) requirements Correspondence, Communication and Administrative Procedures.

Invoice and payment.

7. Permits

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Security The contractor will comply with all established security policies at the Project. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor’s ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent service in an area. The Contractor shall be given at least 24 hour notice of any such closure.

9. Payment Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice and a completed, signed US Army Corps of Engineers ENG93 form to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days the contractor may request progress payment.

Invoice/Forms shall be mailed to:

US Army Corps of Engineers 518 East Hartford Ave., Uxbridge, MA 01569-1209 or emailed to joseph.l.zanca@usace.army.mil or faxed to the office at (508) 278-4234.

10. Damage to Government and Private Property The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the firm’s operation. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm’s operations. The Contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person resulting from the firms’ operation.

11. Point of Contact Requirements The Contractor shall provide to the Technical Point of Contact a telephone number and a point of contact for discussion of any contractual matters.

II. TECHNICAL

Requests for Information:

Requests concerning the work of this project should be directed to the Technical Point of Contact. Joe Zanca at (978) 318-8419 or joseph.l.zanca@usace.army.mil Submittals:

Although the Government technically reviews submissions required by this scope of work, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the government prior to the commencement of any field activities.

Product specification sheets and cut sheets for actuator accessories and equipment.

Product specification sheets and cut sheets for all associated electrical panels, controls and equipment.

Manufacturer Warranty for all equipment and hardware.

Accident Prevention Plan (AAPP) and Activity Hazard Analysis (AHA).

Clean Up:

The Contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work in an area the contractor shall remove any tools, equipment, and materials that are not the property of the government.

Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

Government Resources:

The contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources.

Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

Quality Assurance:

The contractor is responsible for the quality control of the contract work. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor, or by Government employees.

Environmental Protection:

Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis. No burning is permissible. Water, air and land resources shall not be adversely impacted during the course of the work. Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.

Sustainability:

EPA Designated: Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials, and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels.

Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.

Bio-based: The United States Department of Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio based content level requirements.

Receiving and Storing Materials:

The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods.

Government employees will not receive material or supplies for the contractor and will not be responsible for damage to contractor equipment or material.

General:

Existing Conditions:

West Hill Dam is controlled by three, five by five foot sluice gates which were installed in 1963. In 1992, three Rotork model 30A actuators were installed, with an electro mechanical remote control panel inside the gate house building.

West Hill Dam is a dry bed reservoir. No pool or lake is held behind the Dam under normal operation.

Products:

Electronic, electrical and mechanical components will meet or exceed national electrical codes and specifications as listed specifications

1. Sluice Gate Operator (x3):

a. Shall be compatible with existing sluice gate mechanicals.

b. Shall be 240v single phase.

c. Enclosure shall be rated a minimum of NEMA 4x.

d. Shall operate at a minimum rate of six inches per minute in both raising and lowering.

e. Shall provide new or reuse the existing metal stem level indicator system.

f. Shall have operating functions and features on actuator, as listed below in “Sluice Gate

Control System”.

g. Shall operate in temperature range of -10 to +120 degrees Fahrenheit.

h. Shall have heaters to prevent moisture buildup in outdoor housing.

i. Shall have internal limit switches and automatically stop at 0.0 feet and +5.0 feet.

j. No component shall overhang into the concrete deck wearing surface of the bridge.

k. Shall include a clear, non-yellowing, stem cover, sealed from the elements, to protect the stem and stem level indicator system.

2. Sluice Gate Control System :

a. Shall consist of two operating methods, mechanical and electrical.

i. Mechanical:

1. Operation will be made by a hand wheel being attached to the actuator and manually rotating the wheel to operate the gate.

ii. Electrical:

1. Operation will consist of two systems: Remote/PLC( Programmable Logic Controller):

inside the West Hill Dam gate house using the PLC and Local: at the sluice gate operator using push buttons.

i. Remote/PLC:

Unit shall be a Programmable Logic Controller (PLC), with uninterruptable power supply battery backup, surge suppressor.

PLC Color Touch screen- Shall be standalone (not integrated within the PLC), minimal screen size to be 14”x14”, with a color high resolution screen.

PLC and PLC color touch screen will be installed in a NEMA 4x control cabinet on an inside wall of the gatehouse at a location approved by the technical point of contact.

Graphical interface programmed as described in SOW and directed by Technical Point of Contact.

Shall measure and track in 0.1 feet increments, operate in a range from 0.0 feet to +5.0 feet.

Shall stop in either direction at 0 and each whole foot.

Shall operate in temperature range of -4 to +120 degrees Fahrenheit.

Shall be able to keep current sluice gate level after power interruptions.

PLC Touch Screen Graphical User Interface (GUI):

a. PLC Color Touch screen will have 2 graphical user screens.

b. Screen 1 will be for operation of each Sluice Gate Actuator, with virtual buttons placed to control the Gate ( “RAISE”, “LOWER”, “STOP”). A Gate Level indicator will display the Gate position in two increments of feet with 0.1 foot accuracy (0.0 ft).

c. Screen 1 will also have a graphical image that represents each gate and its current setting.

d. Screen 2 will have a list (summary) of logged data, collected (time, date, gate number, gate level and sum of gate levels once every movement) with the ability to scroll thru the logged data, at a minimum of the last 15 days.

e. Final Design of input/output screens will be approved by the Technical Point of Contact.

iii. Local:

Shall be rated for a corrosive and wet environment.

Shall have weather proof, momentary contact pushbuttons for “RAISE”, “LOWER” and

“STOP” gate functions.

Shall have a three way lockable switch, for LOCAL, OFF and REMOTE operation.

Shall have vandal proof indicator lights for open, close and fault functions.

3. Electrical and control conduit, wire, fittings, fasteners and support structure:

a. Rigid conduit and fittings shall be stainless steel.

b. Flexible conduit and fittings shall be waterproof.

c. Electric and control system components will be properly grounded and tied into the lightning protection system.

Execution:

Sluice Gate Operator and Control Replacement shall occur in accordance with the statement of work, local and federal laws, and the National Electric Code. One Sluice Gate shall be worked on and completed before moving to the next Sluice Gate. Sequence of replacement will be approved by the technical point of contact.

1. Work area will be restricted to contractors and USACE Employees.

2. Remove and replace one Sluice Gate Operator, electrical and control wires and conduit at a time (x3).

3. Inspect, clean and lubricate, if necessary, all mechanicals.

4. Replace existing remote control panel with new PLC remote control system and connect new sluice gate actuator to new remote control system.

5. Program PLC control system.

6. Set and adjust electromechanical sluice gate actuator stopping limits at 0.0 ft. and 5.0 ft.

positions.

7. Test Sluice Gate Operator with the technical point of contact.

a. Mechanically:

1. Operate each sluice gate operator system using hand wheel, one inch of movement in each direction.

b. Electrically:

1. Operate each sluice gate operator control system type (remote/PLC and Local) in each direction (raise/lower) three full cycles.

2. Each Sluice Gate Operator will operate electrically at the specified speed and stop independently at specified increments.

3. Make necessary adjustments to system.

8. Contractor will be responsible for disposal of all items removed in this contract.

9. Contractor is responsible for the cleanup of the site.

(End of Summary of Changes)