W912WJ19B0014_AMND0001.pdf

PDF 534 KB Posted

Attached to
ANNISQUAM RIVER MAINTENANCE DREDGING
Solicitation number
W912WJ19B0014
Issued by

View the file

Other files

File Type Posted
Bid_Abstract_signed.pdf PDF
Bid_Snap_Shot.pdf PDF
GHDS_aerial_amendment2.pdf PDF
GHDS_Disposal_Target_sketch_amend2.pdf PDF
W912WJ19B0014_AMND0002.pdf PDF
W912WJ19B0014_Plans_07.12.2019.pdf PDF
W912WJ19B0014_Specifications_07.12.2019.pdf PDF
Specs_FINAL.pdf PDF
Plans.pdf PDF
Specifications.pdf PDF
W912WJ19B0014_Annisquam_Maintenance_Dredging_FINAL.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is issued to provide response(s) to Request for Information (RFI). All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Jul-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ19B0014

X 9B. DATED (SEE ITEM 11)

28-Jun-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Jul-2019

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ19B0014

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The following have been added by full text:

AMENDMENT 0001

RFI Questions – Annisquam River Maintenance Dredging – Solicitation W912WJ19B0014

QUESTION #1

Will the Lobster Cove base/option area be included in the area slated for mandatory first season dredging?

GOVERNMENT RESPONSE:

No, the Lobster Cove base and optional item areas will not be required to be completed in the first dredging season. The area required to be completed in the first dredge season only applies to the federal navigation channel.

QUESTION #2

Please confirm that the contractor is not required to use an environmental bucket while removing material except in areas expressly marked as silty areas on the plans. Please also confirm that no areas slated for mandatory removal in the 2019 season will require the use of an environmental bucket.

GOVERNMENT RESPONSE:

None of the base bid items will require the use of an environmental bucket. Contractor will only be required to use an environmental bucket for the optional items, if exercised, due to the silty properties of the material. This requirement will be in place regardless of which season the option(s) is/are exercised. The area required to be dredged in the first season is sandy material and therefore will not require the use of an environmental bucket.

(End of Summary of Changes)

File details come from the government source that posted it.