Specs_(1).pdf

PDF 2 MB Posted

Attached to
Gate 1 Replacement, Ball Mountain Dam
Solicitation number
W912WJ18B0029
Issued by

About this file

Specifications

View the file

Other files

File Type Posted
BidAbstract.pdf PDF
Bid_Summary.pdf PDF
Amendment_2_Photo.pdf PDF
W912WJ18B0029_Amendment_0002.pdf PDF
W912WJ18B0029_Amendment_0001.pdf PDF
W912WJ18B0029.pdf PDF
Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912WJ18B0029

Gate 1 Replacement

Ball Mountain Dam, Jamaica, Vermont

Construction Solicitation and Specifications

July 2018

Gate 1 Replacement, Ball Mountain Dam, Jamaica, VT

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 MEASUREMENT AND PAYMENT

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20 ENVIRONMENTAL PROTECTION

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

DIVISION 05 - METALS

05 59 13 FABRICATION OF HYDRAULIC STEEL STRUCTURES

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 16.53 VERTICAL LIFT GATES

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.2 WINTER SHUTDOWN PERIOD

1.3 SITE CONDITIONS

1.4 REFERENCES

1.5 SUBMITTALS

1.6 DESIGN REQUIREMENTS

1.6.1 General

1.6.2 Designer Registration

1.6.3 Welds

1.6.4 Load and Resistance Factor Design Method (LRFD)

1.6.5 Allowable Strength Design (ASD)

1.6.6 Performance Factor

1.6.7 Design Criteria

1.6.7.1 Downthrust

1.6.7.2 Coefficient of Friction

1.6.8 Design Package

1.6.8.1 3-D Analysis

1.6.8.2 Design Package

1.6.8.2.1 Government Review

1.6.8.3 Shop Drawings

1.6.9 Final Approved Design Package

1.6.10 Definition of Gate

1.6.11 Fracture/Failure Critical Members (FCM)

1.6.12 FCM Connections

1.6.13 Limit States

1.6.14 Design Life

1.6.15 Inspection

1.6.16 Tack Welds

1.7 PERFORMANCE TESTS

1.8 SUPERINTENDENCE BY THE CONTRACTOR

1.9 COORDINATION AND DIRECTION DURING CONSTRUCTION

1.10 PROJECT/SITE CONDITIONS

1.10.1 Site Security

1.11 WORK SEQUENCE AND SCHEDULING

1.11.1 Hours of Operations

1.11.2 Work Sequence

1.11.2.1 General

1.11.2.2 Initial Project Schedule

1.11.2.3 Periodic Schedule Updates

1.11.3 Organization at the Site

1.11.3.1 General

1.11.3.2 Rate of Progress

1.12 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES

1.13 CONTRACTOR USE OF PREMISES

1.13.1 Access to the Site and Storage/Staging Areas

1.13.2 Temporary Facilities and Utilities, and Storage Areas

SECTION 01 11 00 Page 1

1.13.3 Work Limits

1.13.4 Protection and Security

1.13.5 Work By Other Contractors

1.13.6 Emergency Contacts

1.13.7 Damaged Property

1.13.8 Contractor's Receipt of Supplies

1.13.9 Daily Clean Up

1.13.10 Government Sanitary Facilities

1.14 QUALITY ASSURANCE

1.15 GENERAL SAFETY REQUIREMENTS

1.15.1 General

1.15.2 Contractor's Project Superintendent

1.16 ENVIRONMENTAL PROTECTION

1.17 PRECONSTRUCTION CONFERENCE

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

SECTION 01 11 00 Page 2

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.

The work of this project involves design, fabrication, and installation of one new stainless steel hydraulic vertical lift gate at Ball Mountain Dam in Jamaica, Vermont.

The work covered consists of the design, fabrication, shop assembly and testing, delivery, installation and site testing of one new stainless steel hydraulic vertical lift gate. Also included is the furnishment and installation of stainless steel gate and frame seals compatible with both the existing gate frame and new gate, new compatible babbitt, as well as reassembly of the operating machinery, including the reassembly of the hydraulic control system, prior to new gate commissioning. The gate and accessories shall operate properly with minimal gate leakage as defined in the specifications. All embedded portions of the existing gate frame shall remain in place. Existing babbitt and remaining side seals shall be removed. The hydraulic operating machinery is currently disassembled and approximately 500 gallons of hydraulic fluid from the system has been stored in the gatehouse (see photographs attached at the end of this section). The Contractor shall remove the stored hydraulic fluid and supply new hydraulic fluid per the specifications. Any work associated with the hydraulic system shall be considered subsidiary.

The Contractor shall remove and properly dispose of the existing Gate 1 after all installation work has been completed. Any remaining paint on the existing Gate 1 is lead based and shall be handled and disposed of accordingly.

The gate, seals and appurtenances shall be designed, supplied and guaranteed by one supplier who shall be solely responsible for the proper operation of all components as a single system.

The design of the lift gate shall meet the design requirements of

ETL 1110-2-584.

Gate Installation and Hydraulic Fluid Removal: The operator of the hoist must be a Class 2 licensed operator and the operation is considered a critical lift. Refer to the 1957 as-builts for details on the hoist and hydraulic system. The Contractor shall take care to control and contain any hydraulic fluid leakage during this operation. The Contractor shall prepare and submit a Gate Installation Work Plan for government review.

The plan shall outline the steps and procedures proposed for reinstalling the gate. All work in the conduit is identified as a confined space and shall adhere to the permit requirements for a confined space work environment.

SECTION 01 11 00 Page 3

1.2 WINTER SHUTDOWN PERIOD

This project will contain a Winter Shutdown period extending from 1 December 2018 to 31 March 2019. This shutdown period is due to the potential of sustained below freezing temperatures leading to ice buildup in the conduit and disruption of crane systems. During this period, no physical work shall be performed inside the gatehouse or conduit. The Contractor will continue progress on all other offsite design and fabrication work as well as preparation of submittals so as to meet the total project period of performance.

1.3 SITE CONDITIONS

This project consists of replacing existing lift gate #1 (north gate) as well as the gate seals. The existing gate frame shall remain in place.

The bonnet and hydraulic cylinder are currently disassembled and stored in the control tower directly adjacent to the gate slot (see photgraphs attached at the end of this section). Gate #1 has already been removed and is available at Ball Mountain Dam for review. There is some leakage through the hydro-electric gate upstream of the lift gate. The Contractor shall be responsible for managing all water resulting from the hydro-electric gate leakage. Also, the pool elevations and discharges through the other two gates vary depending on environmental requirements and seasonal rainfall to ensure minimum flows are met.

Service Bridge Load Capacity: The service bridge is HS20 rated and has a load capacity of 31.6 tons.

The gate lifting eye(s) (as shown on record drawing CT-1-4415, Sheet 66 of 86, Detail 62) are not available, and therefore cannot be utilized for placement of the new gate.

1.4 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA C561 (2014) Fabricated Stainless-Steel Slide Gates

AMERICAN WELDING SOCIETY (AWS)

AWS D1.6/D1.6M (2017) Structural Welding Code - Stainless Steel

U.S. ARMY CORPS OF ENGINEERS (USACE)

ETL 1110-2-584 (2014) Design of Hydraulic Steel Structures

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SECTION 01 11 00 Page 4

SD-01 Preconstruction Submittals

Initial Project Schedule; G, RO

In accordance with the contract clauses, the Contractor shall, within 5 days after receipt of Notice to Proceed (NTP) or as otherwise determined by the Contracting Officer, submit for approval a practicable project schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the Contracting Officer.

Design Package; G, DO

Gate Installation Work Plan; G, DO

SD-07 Certificates

Periodic Schedule Updates; G, RO

Request Application; G, RO

Request Application to work outside the hours of operation. See Subpart "Hours of Operations" in this section of the specifications.

1.6 DESIGN REQUIREMENTS

1.6.1 General

Design of HSS members shall be in accordance with the current edition of the American Institute of Steel Construction (AISC) Steel Construction Manual and ETL 1110-2-584.

1.6.2 Designer Registration

The designer of the replacement gate shall be a Registered Professional Engineer.

1.6.3 Welds

Welds shall comply with AWS D1.6/D1.6M.

1.6.4 Load and Resistance Factor Design Method (LRFD)

Design of HSS members shall be based on LRFD Method.

1.6.5 Allowable Strength Design (ASD)

ASD shall only be used on those structures where the LRFD method has not been developed.

1.6.6 Performance Factor

Design shall use a Performance Factor of 0.85 applied in accordance with

ETL 1110-2-584.

SECTION 01 11 00 Page 5

1.6.7 Design Criteria

The new gate shall utilize the existing bonnet, bonnet cap, cylinder and stem. The new gate shall be fully compatible with the existing conduit geometry and operate properly within the existing gate frame. The new gate shall be constructed to ensure an adequate connection to the existing stem that is similar to the existing lift gate. The new gate shall be designed to meet the current operating system capabilites and no modification to the current system is allowed.

The new gate shall not exceed the weight of the existing gate which is approximately 10,300 lbs and shall function properly with the existing operating system.

The gate shall meet the following design criteria:

1. Inlet invert is at elevation 805.5 ft (NGVD).

2. On rare occasions, the reservoir could reach elevation 1,052.0 ft (NGVD). At that point, no water releases will be made through the inlet structure and the lift gates will be in the fully closed position, except when the pool rises to the following levels:

Operational Loads (Pool Elev., Ft) Operation Required

Elev. 1,032 ft (NGVD) 3 gates 3' open

Elev. 1,037 ft (NGVD) 3 gates 6' open

Elev. 1.042 ft (NGVD) 3 gates fully open

The pool elevations for the load categories shall be as follows:

LOADING

CATEGORY: USUAL

LOADING

CATEGORY:

UNUSUAL

LOADING

CATEGORY: EXTREME

RETURN PERIOD 1 to 10 Years 10 to 300 Years Over 300 Years

POOL ELEVATION

(NGVD29)

870.5 FT to

986.5 FT

986.5 FT to

1,023.7 FT

1,023.7 FT to

1,052.0 FT

ANNUAL CHANCE OF

EXCEEDANCE

1 to 0.1 0.1 to 0.003 Less Than 0.003

TEMPERATURE: -30 degrees F MIN, 100 degrees F MAX

1.6.7.1 Downthrust

The downthrust (df) value shall be 93 feet. This value is based on USACE Hydraulic Design Criteria, Volume II, Sheets 320-2 to 320-2/3, 1961. An alternative downthrust value may be used with approval from the Contracting Officer. The Contractor shall submit all supporting design calculations and design references for the alternative value.

SECTION 01 11 00 Page 6

1.6.7.2 Coefficient of Friction

The coefficient of friction between the gate and the gate frame shall be no greater than 0.6. The original design of the gate travel is 1 ft/min.

This speed shall be used for the design of the new gate.

1.6.8 Design Package

1.6.8.1 3-D Analysis

A 3-D analysis shall be performed to determine the gate stresses.

Verification shall include simplified 2-D analysis.

1.6.8.2 Design Package

All software files utilized to perform the 3-D and 2-D analysis, along with related sketches and diagrams, and including output files in pdf format, shall be submitted to the Contracting Officer for documentation and review.

1.6.8.2.1 Government Review

The Contracting Officer shall perform the review of the Design Package submittal within 30 calendar days from the delivery date.

1.6.8.3 Shop Drawings

The shop drawings shall not be submitted until the approval of the design package has been granted.

1.6.9 Final Approved Design Package

The final approved design package, including the approved shop drawings, shall not exceed twelve (12) weeks from Contractor receipt of the Notice to Proceed. Refer to Section 05 59 13 FABRICATION OF HYDRAULIC STEEL STRUCTURES for additional shop drawing requirements.

1.6.10 Definition of Gate

The gate is defined as a Vertical Lift Gate and therefore shall be designed in accordance with ETL 1110-2-584, Appendix E - Vertical Lift Gates.

1.6.11 Fracture/Failure Critical Members (FCM)

All Fracture Critical Members (FCM) shall be identified on the drawings.

1.6.12 FCM Connections

Any fracture fritical element connections shall be detailed by the designer (i.e., the designer cannot leave connection detailing to the steel fabricator).

1.6.13 Limit States

Gate shall be designed to be fully operational for all limit states (Strength, Service, Fatigue, Fracture, and Extreme). Refer to ETL 1110-2-584 for load frequencies and load cases.

SECTION 01 11 00 Page 7

1.6.14 Design Life

Gate shall have a design life of 100 years.

1.6.15 Inspection

Design shall ensure that all portions of the gate are accessible for inspection purposes. Closed or uninspectable intercostal spaces shall not be allowed unless approved by the Contracting Officer.

1.6.16 Tack Welds

Tack welds shall not be used on Failure Critical Members.

1.7 PERFORMANCE TESTS

After completion, seating and wedging surfaces shall be cleaned thoroughly of foreign materials and final adjustments made. The gate shall then be shop-operated from the fully closed to the fully opened position to verify that the assembly is workable. A shop leakage test meeting the requirements of Section 5.2.1 of AWWA C561 shall be performed by the Contractor. The Contractor shall notify the Contracting Officer a minimum of seven days prior to the performance of the shop leakage test.

Seating Head: Under the design seating head, the leakage shall not exceed

0.1 gpm per foot of seating perimeter.

1.8 SUPERINTENDENCE BY THE CONTRACTOR

a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.

b. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

c. Failure to comply with these requirements shall be deemed as cause for a non-compensatory stoppage and suspension of work until the deficiency is remedied.

1.9 COORDINATION AND DIRECTION DURING CONSTRUCTION

a. The Contractor shall not take or accept any direction or instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer that changes the terms and conditions of contract actions, the scope, or any change that impacts the cost, price, or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the changes clause of this contract when the Contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contracting Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer.

SECTION 01 11 00 Page 8

b. The Contracting Officer Representative (COR) is limited to the authorities stated in the COR appointment letter. If a COR is appointed under this contract, they will be appointed by written letter from the Contracting Officer to the Contractor and COR specific to this contract only. COR appointment letters from previous contracts are not valid for this contract. See the Contracting Officer’s Representative clause of this contract.

1.10 PROJECT/SITE CONDITIONS

1.10.1 Site Security

The Contractor shall report any vandalism, suspicious activities or devices to the Contracing Officer or local police as soon as possible. The Contracting Officer will notify the Contractor of any heightened security measures and will expect vigilant monitoring of equipment, grounds and security fencing while working. At a heightened security posture, there may be work areas that are restricted. The Contracting Officer will notify the Contractor of these restricted areas, and work may be delayed or restricted or will be performed in these areas under the direct supervision of U.S. Army Corps of Engineers personnel.

1.11 WORK SEQUENCE AND SCHEDULING

1.11.1 Hours of Operations

Normal work hours are from 7:00 a.m. through 3:30 p.m., Monday through Friday. The Contractor will not be permitted to work on Saturday, Sunday or legal holidays unless otherwise authorized by the Contracting Officer.

The exclusion of work on Saturday, Sunday and legal holidays has been considered in computing the performance time of this contract. The following legal holidays are observed:

January 1st Third Monday in January Third Monday in February Last Monday of May July 4th 1st Monday of September 2nd Monday of October 11th of November Fourth Thursday of November 25th of December

When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.

Work outside the normal hours of operation requires Contracting Officer approval. The request to work outside the hours of operation shall be made in writing to the Contracting Officer 10 calendar days prior to such work to allow arrangements to be made by the Government. The request application shall include specific dates, hours, location, type of work to be performed, contract number and project title, and names of all individuals who will be working outside the hours of operations. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.

SECTION 01 11 00 Page 9

1.11.2 Work Sequence

1.11.2.1 General

There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. Minor variations in the sequence of the items of work as specified may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE, entitled "SCHEDULES FOR CONSTRUCTION CONTRACTS". Variations shall be approved by the Contracting Officer prior to implementation.

1.11.2.2 Initial Project Schedule

The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart. This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. Anticipated adverse weather delay days shall be included and clearly indicated in the schedule.

The initial schedule shall be cost and resource loaded for contract monitoring and control purposes. Schedules shall be established using a standard critical path method (CPM), or other industry approved standard.

Each activity shall have an early start/finish date, late start/finish date, task duration, and total float clearly indicated.

1.11.2.3 Periodic Schedule Updates

An updated schedule showing actual progress shall be submitted monthly and with each pay request. Changes to the base-line schedule shall be outlined in a narrative describing the reason for the change.

1.11.3 Organization at the Site

1.11.3.1 General

The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Clause

COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984) FAR 52.211-10.

1.11.3.2 Rate of Progress

Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.

SECTION 01 11 00 Page 10

1.12 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES

The Contractor shall be responsible for the following:

(1) Determining the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.

(2) Complying with all local, State, and Federal regulations and restrictions when using any facilities or hauling routes.

1.13 CONTRACTOR USE OF PREMISES

1.13.1 Access to the Site and Storage/Staging Areas

Access to the project site is available for construction traffic. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.

Access to temporary facilities and storage/staging areas shall be as specified in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS and as shown on the contract drawings.

1.13.2 Temporary Facilities and Utilities, and Storage Areas

The Contractor shall conform to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS regarding temporary facilities, temporary utilities, and storage areas. Confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

1.13.3 Work Limits

Work shall be restricted to the limits of the work as shown on the contract drawings and to storage areas as indicated in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, as shown on the contract drawings, and as indicated by the Contracting Officer.

1.13.4 Protection and Security

a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.

b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.

c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.

1.13.5 Work By Other Contractors

During the performance period of this contract, no other work is anticipated to occur by other contractors.

1.13.6 Emergency Contacts

The Contractor shall provide a list of emergency contacts in the event of

SECTION 01 11 00 Page 11 an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.13.7 Damaged Property

Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.

1.13.8 Contractor's Receipt of Supplies

The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.

1.13.9 Daily Clean Up

The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.

1.13.10 Government Sanitary Facilities

Toilet facilities are not available on site for Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION

FACILITIES AND CONTROLS.

1.14 QUALITY ASSURANCE

a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.

b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.

Government-designated Quality Assurance Representatives (GQARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.

c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.

d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.

e. The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.

f. The Contractor shall not conceal any work unless the Contracting

SECTION 01 11 00 Page 12

Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.

1.15 GENERAL SAFETY REQUIREMENTS

1.15.1 General

The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.

1.15.2 Contractor's Project Superintendent

The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.

1.16 ENVIRONMENTAL PROTECTION

To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 20 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.

1.17 PRECONSTRUCTION CONFERENCE

The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

SECTION 01 11 00 Page 13

Photo 1 - Gate slot with temporary covering

Photo 2 - Stored hydraulic fluid

Photo 3 - Stairwell and cylinders for Gate 2 and Gate 3

Photo 4 - Gate 2

Photo 5 - Disassembled Gate 2 bonnet and cylinder

Photo 6 - Stored hydraulic fluid

Photo 7 - Disassembled Gate 2 bonnet and cylinder

Photo 8 - Disassembled gate hanger for Gate 1

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

1.2 BIDDING SCHEDULE - PAYMENT ITEMS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.2 BIDDING SCHEDULE - PAYMENT ITEMS

Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below. All costs for items of work, which are not specifically mentioned to be included in a particular Bidding Schedule job or unit price payment item, shall be included in the listed item most closely associated with the work involved.

a. Item Number 0001, "Design of Stainless Steel Hydraulic Vertical Lift Gate".

All costs for labor, equipment, and materials for the design of one stainless steel hydraulic vertical lift gate, as shown on the contract drawings and in accordance with Sections 05 59 13 FABRICATION OF HYDRAULIC STEEL STRUCTURES, 35 20 16.53 VERTICAL LIFT GATES, and other appropriate sections of the specifications.

Unit of Measure: Job.

b. Item Number 0002, "Fabrication of Stainless Steel Hydraulic Vertical Lift Gate".

All costs for labor, equipment, and materials for the fabrication of one stainless steel hydraulic vertical lift gate, including shop testing, as shown on the contract drawings and in accordance with Sections 05 59 13 FABRICATION OF HYDRAULIC STEEL STRUCTURES, 35 20 16.53 VERTICAL LIFT GATES, and other appropriate sections of the specifications.

Unit of Measure: Job.

c. Item Number 0003, "Installation of Stainless Steel Hydraulic Vertical Lift Gate".

All costs for labor, equipment, and materials for the installation of one stainless steel hydraulic vertical lift gate and appurtenant items, SECTION 01 22 00 Page 2 as shown on the contract drawings and in accordance with Sections

05 59 13 FABRICATION OF HYDRAULIC STEEL STRUCTURES, 35 20 16.53

VERTICAL LIFT GATES, and other appropriate sections of the specifications. This item includes prepatory work, delivery, installation, reassembly of operating machinery and controls, removal of existing hydraulic fluid, and field testing and commissioning.

Unit of Measure: Job.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

1.4.1.1 Approval Codes

1.4.2 Information Only

1.4.3 Sustainability Reporting Submittals (S)

1.5 PREPARATION

1.5.1 Transmittal Form

1.5.2 Source Drawings for Shop Drawings

1.5.2.1 Terms and Conditions

1.6 QUANTITY OF SUBMITTALS

1.7 INFORMATION ONLY SUBMITTALS

1.8 VARIATIONS

1.8.1 Considering Variations

1.8.2 Proposing Variations

1.8.3 Warranting That Variations Are Compatible

1.8.4 Review Schedule Is Modified

1.9 SUBMITTAL REGISTER

1.9.1 Use of Submittal Register

1.9.2 Contractor Use of Submittal Register

1.9.3 Approving Authority Use of Submittal Register

1.9.4 Copies Delivered to the Government

1.10 SCHEDULING

1.11 GOVERNMENT APPROVING AUTHORITY

1.11.1 Review Notations

1.12 DISAPPROVED SUBMITTALS

1.13 APPROVED SUBMITTALS

1.14 APPROVED SAMPLES

1.15 WITHHOLDING OF PAYMENT

1.16 STAMPS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings and specifications.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to start of construction (work) or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates of insurance

Surety bonds

List of proposed Subcontractors

SECTION 01 33 00 Page 2

List of proposed products

Construction Progress Schedule

Network Analysis Schedule (NAS)

Submittal register

Schedule of prices

Accident Prevention Plan

Work plan

Quality Control(QC) plan

Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within two years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

SECTION 01 33 00 Page 3

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements shall be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further qualify the orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

SD-09 Manufacturer's Field Reports

Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.

Factory test reports.

1.2.2 Approving Authority

Office or designated person authorized to approve submittal.

1.2.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G, RO

1.4 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical

SECTION 01 33 00 Page 4 materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.

Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."

1.4.1.1 Approval Codes

a. Construction Division {"AO" (Area Office), "RO" (Resident Office), or "PO" (Project Office) Reviewer}: An "AO", "RO", or "PO" in column "f" indicates that the submittal review action is by New England District Construction Division. Send all such submittals to the project Resident or Area Engineer, as applicable.

b. Engineering Division {"DO" (District Office) Reviewer): A "DO" on the attached submittal register, column "f" indicates that the submittal review action is by the New England District, Engineering Division, or other organization in the District Office. Send all such submittals to the project Resident or Area Engineer for distribution to the appropriate approving authority.

d. Government acceptance is required for submittals with a "G, A" designation.

1.4.2 Information Only

Submittals not requiring Government approval will be for information only.

They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.4.3 Sustainability Reporting Submittals (S)

Submittals for Guiding Principle Validation (GPV) or Third Party Certification (TPC) are indicated with an "S" designation. Submit the information required by the technical sections that demonstrates compliance with the sustainable requirement, and for inclusion in the Sustainability eNotebook if required by Section 01 33 29 SUSTAINABILITY REPORTING. A full submittal for an item may be provided under another SD; however, for the "S" submittal, only provide that portion of the submittal that demonstrates compliance with the sustainable requirement. If the sustainable submittal does require Government Approval, it may be tagged under another SD with a "G."

Schedule submittals for these items throughout the course of construction as provided; do not wait until closeout.

1.5 PREPARATION

1.5.1 Transmittal Form

Use the attached sample transmittal form (ENG Form 4025) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor and are included in the QCS software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

SECTION 01 33 00 Page 5

1.5.2 Source Drawings for Shop Drawings

The entire set of Source Drawing files (DWG) will not be provided to the Contractor. Only those requested by the Contractor to prepare shop drawings may be provided. Request the specific Drawing Number only for the preparation of Shop Drawings. These drawings may only be provided after award.

1.5.2.1 Terms and Conditions

Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.

The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic Source Drawing files are not construction documents.

Differences may exist between the Source Drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).

1.6 QUANTITY OF SUBMITTALS

Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. In addition to the electronic submittal, provide seven hard copies of the submittals. for submittals which include drawings, two copies shall include full sized drawings.

Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.

SECTION 01 33 00 Page 6

Email electronic submittal documents fewer than 10MB to an email address as directed by the Contracting Officer. Provide electronic documents over 10MB on an optical disc, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:

https://safe.amrdec.army.mil/safe/.

Up to two additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the Government.

1.7 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.

The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications, will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work, and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.8 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

1.8.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation that results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.8.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.

Clearly mark the proposed variation in all documentation.

Check the column "variation" of ENG Form 4025 for submittals that include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.

The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

SECTION 01 33 00 Page 7

1.8.3 Warranting That Variations Are Compatible

When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.8.4 Review Schedule Is Modified

In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.

1.9 SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and

(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM). The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Column (c): Lists specification section in which submittal is required.

Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.

Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.

1.9.1 Use of Submittal Register

Submit submittal register. Submit with QC plan and project schedule.

Ver…

This is the start of the file's text. The full file is on GovTribe.