Amendment_0001.pdf

PDF 137 KB Posted

Attached to
Joint Seal Replacement project, Bourne and Sagamore Bridges, Cape Cod Canal
Solicitation number
W912WJ18B0002
Issued by

About this file

Amendment 0001

View the file

Other files

File Type Posted
Amendment_0003.pdf PDF
Amendment_0002.pdf PDF
Informational_Drawings.pdf PDF
Specifications.pdf PDF
W912WJ18B00002.pdf PDF
Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is being issued to revise the Definitive Responsibility Criteria, revise clause 52.211-10, provide a Point of Contact for questions and requests for information (RFI), and move the bid opening date from 2:00 PM on November 10th to 2:00 pm on November 13th.

All other aspects of this solicitation remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Oct-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912WJ18B0002

X 9B. DATED (SEE ITEM 11)

11-Oct-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Oct-2017

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ18B0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Note to bidders

From October 18th to November 1st, the point of contact for this solicitation will be Erin Bradley.

Phone: (978) 318-8195 Email: Erin.E.Bradley@usace.army.mil

Any correspondence sent to the current point of contact, Alysha MacDonald, will not be viewed or answered until after November 1st. As such, please be sure to send questions directly to Erin Bradley.

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 10-Nov-2017 02:00 PM to 13-Nov-2017 02:00 PM.

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been revised:

1.2 DEFINITIVE RESPONSIBILITY CRITERIA

After bid opening but prior to award, the apparent low bidder will be required to furnish documentation that meets the following criteria:

1. Demonstrated experience in each of the three following components: Installation of bridge joints, concrete replacement or repair work associated with bridge joints, and traffic control on limited access Interstates, State Routes, or US Routes. More than one project may be used in order to substantiate experience on each of these criteria.

2. Firms may use subcontractor experience to demonstrate experience with the Definitive Responsibility Criteria, but the role and work performed by each team member (prime and subcontractors) on projects as used to demonstrate that team member's experience with the Definitive Responsibility Criteria shall be the same as the role for that team members' role under this procurement.

The apparent low bidder will have two (2) working days after bid opening to submit the documentation demonstrating that it meets the above definitive responsibility criteria, and will receive award of the contract if otherwise eligible and responsible. If the apparent low bidder cannot provide this documentation or if the documentation it submits does not show that it meets these criteria, the apparent next low bidder will be requested to provide this documentation, and if timely provides the documentation within two (2) days of the Government’s request therefor, it will receive award of the contract if otherwise eligible and responsible. This process will be followed until the low bidder who meets the requirement can document that it meets the definitive responsibility criteria or the Government cancels the solicitation.

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, (c) complete work on the Sagamore

W912WJ18B0002

bridge by May 23rd, 2018, (d) vacate the Bourne Bridge and remove all traffic control devices during the time periods specified in Section 01 11 00, and (e) complete the entire work ready for use not later than 365 days from notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of Summary of Changes)