B01_Responses_to_Questions_30JUL19.pdf
PDF 50 KB Posted
- Attached to
- Vindicator Security System Upgrade Federal contract opportunity
- Solicitation number
- W912SV19Q6005RFQ
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Provisions_and_Clauses.pdf | ||
| B08_B165_Vindicator_CAD.pdf | ||
| A02_Sole_Source_Justification_Vindicator_Upgrade_REDACTED.pdf | ||
| B08_B162_Vindicator_non-CAD_building_diagram.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION
Solicitation Number: W912SV-19-Q-6005
PROJECT TITLE: Vindicator Upgrades
Date: 30 July 2019
RFI
NO.
DATE OF
SUBMISSION
DATE TO
REQUESTOR/TECH
POC
DATE
RESPONSE
RETURNED
RESPONSE TO RFI DATE
RETURNED
TO KTR
23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019
Is there existing Comm paths to Base Vindicator headend system from/to each facility?
The Vindicator System located inside the building will have connectivity to the head end by connecting to one of the building’s switch stacks using a non-routable VLAN.
Contractor will need to provide path from Vindicator panel to switch stack.
1a.
23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019
Where is headend?
Headend is located at the Security Forces Squadron (SFS) building. Bldg. 197
1b.
23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019
If so where is the network that connects in each facility? And what type of Fiber is utilized? SM or MM
All OSP connections are SM and all ISP are MM fiber.
1c.
If not is contractor expected to provide comm paths?
Contractor will need to provide path from Vindicator panel to switch stack.
2.
23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019
Will contractors have access to Head-end to program new alarm points?
Or will site personnel program new alarm points?
Yes, as long as it is pre-arranged with SFS.
3. 23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019
Does the base have a standard Card reader that the contractor needs to match?
HID Prox RFID Cred. - ISO Prox II Card pivClass Credential Reader w/Keypad, reads Prox and CACII
3a.
What is the card format being utilized on existing system?
HID Prox RFID Cred. - ISO Prox II Card
4.
30 July 2019 30 July 2019 30 July 2019 See answer below 30 July 2019
Is there or will there be existing conveyance installed for installation of IDS/CCTV equipment?
Security system infrastructure (conduit runs) are included on a separate contract for building 165’s renovation and are not included in this solicitation. The contractor selected for this requirement will coordinate with the contractor installing conduit runs to ensure continuity. Both contractors will be working off the same set of CAD drawings from Vindicator.
5.
Does proposal need to exclude taxes?
Yes
5a.
Will Contracting provide a Tax exempt letter to contractor?
Yes
| PROJECT TITLE: Vindicator Upgrades |
| Date: 30 July 2019 |