B01_Responses_to_Questions_30JUL19.pdf

PDF 50 KB Posted

Attached to
Vindicator Security System Upgrade Federal contract opportunity
Solicitation number
W912SV19Q6005RFQ
Issued by
Department of the Army Massachusetts Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Vindicator Security System Upgrade, newest first.
File Type Posted
B08_Provisions_and_Clauses.pdf PDF
B08_B165_Vindicator_CAD.pdf PDF
A02_Sole_Source_Justification_Vindicator_Upgrade_REDACTED.pdf PDF
B08_B162_Vindicator_non-CAD_building_diagram.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION

Solicitation Number: W912SV-19-Q-6005

PROJECT TITLE: Vindicator Upgrades

Date: 30 July 2019

RFI

NO.

DATE OF

SUBMISSION

DATE TO

REQUESTOR/TECH

POC

DATE

RESPONSE

RETURNED

RESPONSE TO RFI DATE

RETURNED

TO KTR

23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019

Is there existing Comm paths to Base Vindicator headend system from/to each facility?

The Vindicator System located inside the building will have connectivity to the head end by connecting to one of the building’s switch stacks using a non-routable VLAN.

Contractor will need to provide path from Vindicator panel to switch stack.

1a.

23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019

Where is headend?

Headend is located at the Security Forces Squadron (SFS) building. Bldg. 197

1b.

23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019

If so where is the network that connects in each facility? And what type of Fiber is utilized? SM or MM

All OSP connections are SM and all ISP are MM fiber.

1c.

If not is contractor expected to provide comm paths?

Contractor will need to provide path from Vindicator panel to switch stack.

2.

23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019

Will contractors have access to Head-end to program new alarm points?

Or will site personnel program new alarm points?

Yes, as long as it is pre-arranged with SFS.

3. 23 July 2019 24 July 2019 30 July 2019 See answer below 30 July 2019

Does the base have a standard Card reader that the contractor needs to match?

HID Prox RFID Cred. - ISO Prox II Card pivClass Credential Reader w/Keypad, reads Prox and CACII

3a.

What is the card format being utilized on existing system?

HID Prox RFID Cred. - ISO Prox II Card

4.

30 July 2019 30 July 2019 30 July 2019 See answer below 30 July 2019

Is there or will there be existing conveyance installed for installation of IDS/CCTV equipment?

Security system infrastructure (conduit runs) are included on a separate contract for building 165’s renovation and are not included in this solicitation. The contractor selected for this requirement will coordinate with the contractor installing conduit runs to ensure continuity. Both contractors will be working off the same set of CAD drawings from Vindicator.

5.

Does proposal need to exclude taxes?

Yes

5a.

Will Contracting provide a Tax exempt letter to contractor?

Yes

PROJECT TITLE: Vindicator Upgrades
Date: 30 July 2019