REQUEST FOR INFORMATION

Solicitation Number: W912SV-18-Q-6015

PROJECT TITLE: IRP Climbing Gear

Date: 14 Aug 2018

RFI

NO.

DATE OF

SUBMISSION

DATE TO

REQUESTOR/TECH

POC

DATE RESPONSE

RETURNED TO KO

RESPONSE TO CLARIFICATION

REQUEST

DATE

RETURNED

TO KTR

14 Aug 2018 14 Aug 2018 14 Aug 2018 See Answer Below 14 Aug 2018

What is the hub height of the two GE turbines there (GE-3 and GE-4)?

Hub Height – 80 m (262 ft)

14 Aug 2018 14 Aug 2018 14 Aug 2018 See Answer Below 14 Aug 2018

What is your timeline for installation?

30 Days ARO