W912QR21Q0052 - Solicitation.pdf
PDF 3 MB Posted
- Attached to
- DFAS Chilled/Hot Water Pump Distro Replacements
- Solicitation number
- W912QR21Q0052
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMDT 0002 - W912QR21Q0052.pdf | ||
| AMDT 0001 - W912QR21Q0052.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W912QR21Q0052 19-Apr-2021
b. TELEPHONE NUMBER
502.315.6179
8. OFFER DUE DATE/LOCAL TIME
11:00 AM 19 May 2021
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912QR9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
JESSICA K MOSS
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
W22W9K10434292
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 9655AH 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
WRIGHT-PATT RESIDENT OFFICE
RESIDENT ENGINEER
2475 K STREET
BLDG 52, RM 113
WRIGHT-PATTERSON AFB OH 45433-7645
TEL: 937.656.9109 FAX:
502.315.6195 OR 6193FAX:
TEL: 502.315.6172 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$16,500,000
NAICS:
238220
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF52
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W912QR21Q0052
Section SF 1449 - CONTINUATION SHEET
SPECIAL INSTRUCTIONS
This Request for Proposal (RFP) is for a contract to provide and install six (6) pumps and motors to replace the current chilled and hot water pumps and associated motors in DFAS Building 21A in accordance with the included Performance Work Statement.
LOCATION:
DFAS Building 21A 3990 E Broad St.
Whitehall, OH 43213
This procurement is 100% set-aside for Small Business, NAICS 238220, Plumbing, Heating & Air Conditioning Contractors (Size Standard $16.5M).
Method of Payment under this contract will be Electronic Funds Transfer (EFT) to a commercial bank account specified by the Contractor.
One award will be made from this Solicitation. The contract award will be based on Lowest Price to the Government.
Note: In addition to the completed price breakout schedule/price proposal, the Offeror must complete their Representation and Certifications located in the solicitation.
Proposals are due 19 May 2021, 11:00 AM Eastern Time. Please submit proposals to jessica.k.moss@usace.army.mil. Fax submittals will not be accepted.
All contractors must be registered in the System for Award Management (www.SAM.gov) prior to award of a contract. All proposed contractors are highly encouraged to review FAR Clause 52.232-33 Payments by Electronic Funds Transfer – System for Award Management, which indicates “All payments by the Government under this contract shall be made by electronic funds transfer (EFT).” Those not currently registered can obtain registration by going to the website http://www.SAM.gov. The process can usually be completed from 24 to 48 hours after submission. Contractors will need to obtain a Unique Entity Identifier (formerly DUNS number) for processing their registration. If you do not already have a Unique Entity Identifier, one can be obtained from http://www.SAM.gov.
Refer to www.SAM.gov for information formerly found in CCR, EPLS, ORCA and FedReg.
Please begin the registration process immediately in order to avoid delay of the contract award should your firm be selected.
ALERT: You must submit a notarized letter appointing the authorized Entity Administrator before your registration will be activated. This requirement now applies to both new and existing entities. Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required before the GSA Federal Service Desk (FSD) will activate the entity's registration.
Effective 29 June 2018, vendors creating or updating their registration can have their registration activated prior to the approval of the required notarized letter. However, the signed copy of the notarized letter must be sent to the GSA Federal Service Desk (FSD) within 30 days of activation or the vendor risks no longer being active in SAM.
Vendors can check whether an account is active by performing a query by their CAGE or Unique Entity Identifier (known as DUNS). The new registration process may now take several weeks, so vendors are highly encouraged to begin registering as soon as possible to avoid any possible delays in future contract awards. Remember, there is no cost to use SAM.To find out additional information about the changes of the SAM registration process, contractors should visit the Frequently Asked Questions (FAQ) link located at the top of the SAM homepage (www.sam.gov).
Note: Page numbering in this document may not be accurate.
PRICE BREAKOUT SCHEDULE
LINE ITEM DESCRIPTION QTY UNIT OF MEASURE UNIT PRICE TOTAL PRICE
0001 Replacement pumps/motors 6 JOB $ $
Miscellaneous parts & supplies for replacements 6 JOB $ $
Labor to remove and dispose of existing pumps/motors 6 JOB $ $
0004 Labor to install pumps/motors 6 JOB $ $
Commissioning of replacement pumps/motors 6 JOB $ $
TOTAL BASE $ $
The total price includes shipping and/or delivery.
Contractor Name:
Address:
Phone Number:
Point of Contact:
Federal Tax ID:
DUNS Number:
Date:
PROJECT: CHILLED & HOT WATER PUMPS REPLACEMENT, DSCC, COLUMBUS, OH
Performance Work Statement
The contractor is to supply and install the following supplies identified in the product specifications to:
DFAS Building 21A
3990 E Broad St.
Whitehall, OH 43213 for the quoted price in this document. The total price includes shipping and/or delivery as well as storage. The
Federal Government is exempt from state sales tax and will furnish the tax exempt # upon request.
The contractor shall provide and install six (6) pumps & motors to replace the current chilled and hot water pumps and associated motors in Building 21A. These pumps shall be “drop-in” replacements for the existing.
The contractor shall also provide one (1) additional 40 HP pump as a spare. Within 90 days from award of the contract, all pumps/motors must be procured, delivered, fully installed, and operational. The contractor shall include delivery to the site as well. The contractor shall follow the requirements regarding the pump replacements provided in Section 01 20 00.00 06.
Special Requirements:
1. All contractors will supply Federal Tax ID, Unique Entity Identifier (formerly DUNS number), and be registered in SAM before this contract will be awarded.
2. Damages: The contractor shall be responsible for all damages to government or private property resulting from negligent operations during the course of this contract. The contractor shall have appropriate insurance to cover liability and damages.
3. Hours of work: Construction work may be conducted between the hours of 7:30 a.m. and 5:00 p.m. EDT, Monday through Friday. No work shall be performed on Saturday or Sunday or on federally observed holidays, i.e., Memorial Day, 4th of July, and Labor Day unless approved by the COR.
4. Safety: All work will be conducted in a safe manner and in accordance with all applicable Federal, State and local regulations, as well as EM 385-1-1, Appendix A. Follow requirements under EM 385-1-1, Appendix A, paragraph 3, subparagraph k for abbreviated Accident Prevention Plan for service contracts. Coordinate plan with the COR in the field.
5. Security: All contractor employees shall be escorted by a facility representative.
Payment:
Payment will be made by Electronic Funds Transfer (EFT), upon acceptance of the completed work and providing final invoice. The contractor is required to provide a Unique Entity Identifier and must be registered with SAM.
Failure to provide all information requested on the quote sheet and to complete SAM registration may be grounds for considering the quote unresponsive.
Completion Date: This contract has a completion date of 90 days from date of award. All contract work shall be completed and approved by this date.
P2: 489828 DFAS Chiller & Hot Water Pumps Replacement
DSCC, Columbus, OH
SECTION 01 20 00.00 06
SECTION
01 20 00.00 06
Task Order SCOPE OF WORK
1.0 PROJECT INFORMATION
1.1 GENERAL
The Contractor shall provide all labor, equipment, supplies, and consultant services as required for the replacement of Chilled and Hot Water Pumps at
DFAS Building 21A, DSCC, Columbus, OH to result in a complete and useable
Facility.
1.2 SCOPE OF WORK
The scope of work is to provide and install six (6) new pumps to replace current chilled and hot water pumps in Building 21A. The new pumps must be suitable as “drop-in” replacements of the existing (i.e., no rework to piping and/or foundations is required). Pumps must also meet the electrical efficiency requirements shown in Section 10.0. All pumps must be installed and fully operational within 90 days from contract award. The pumps shall be installed and tested in a manner to prevent disruptions to the heating and/or cooling of buildings and their occupants.
1.3 SITE LOCATION
This project is located in Building 21A, at DSCC, Columbus, OH.
1.4 EXISTING SITE UTILITIES
1.4.1 The contractor shall verify the capacity of all utilities serving the building. Upgrading the existing utilities, (unless noted otherwise) outside the limits of construction, is not a part of this project.
1.5 NOT USED
1.6 NOT USED
1.7 PERMITS
The Contractor shall investigate and submit any permits necessary for the construction of this project. All permit applications shall be completed by the
Contractor and provided to the Contracting Officer for submittal to the appropriate agency. Contractor shall pay all permit fees. Copies of all permits shall be provided to the USACE.
1.8 ENVIRONMENTAL REQUIREMENTS
1.8.1 Environmental Compliance: The contractor shall comply with the
National Environmental Protection Act and all other Air Force Environmental regulations.
1.8.2 Dust Control: Contractor shall maintain all work areas free from excess dust to such reasonable degree as to avoid causing a hazard to base personnel or surrounding facilities. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs.
1.8.3 Asbestos: No asbestos containing material shall be used.
1.8.4 SDS Sheets: A Safety Data Sheet (SDS) is required for all building materials except for wood, glass, or steel. The SDS will be submitted to the
Contracting Officer within seven (7) calendar days after the NOTICE TO PROCEED.
1.8.5 Hazardous Materials Management: Contractor will provide the
Contracting Officer (CO) the Safety Data Sheets (SDS) for chemical materials to be used during the project prior to the contract award in accordance with FAR
Clause 52.223-3. The Contractor will provide SDSs’ to the Contracting Officer for review prior to the contractor bringing products on the installation. The contractor must inventory all chemical materials, including but not limited to:
solvents, paints, degreasers, greases, Ozone Depleting Substances, and oils, brought on base. A chemical material inventory must be maintained when used containing the nomenclature, manufacturer, part number, quantity, storage location, and the process in which the material is used. All chemical materials will be managed in accordance with federal, state, local, and Installation regulations.
1.8.6 Paint: All paints must meet Green Seal Certification and be low VOC.
See the table below for additional guidance. Paint containing lead will not be used during any painting process. An SDS will be submitted for all paint products used.
For this kind of product:
VOCs (in g/L) shall not exceed:
Flat Topcoat 50
Non-Flat Topcoat 100
Primer or Undercoat 100
Floor Paint 100
Anti-Corrosive Coating 250
Reflective Wall Coating 50
Reflective Roof Coating 100
1.8.7 NOT USED.
1.8.8 Potable Water: If construction or modification of a potable water system is included as a part of the task order scope of work, the contractor is responsible to insure that all potable water connections are protected adequately with anti-siphon devices in accordance with the plumbing code. An
ASSE approved anti-siphon device shall be attached to the hose bib prior to mixing chemicals, etc. A backflow prevention device must be installed at each location potable water enters a facility. This includes fire suppression.
1.8.9 Waste Water: Absolutely no chemical products will be allowed to be dumped in any drainage system, storm drain, wash rack, septic system or sanitary sewer. All remaining and residual chemicals will be taken away by the contractor.
1.8.10 NOT USED
1.8.11 Erosion Prevention and Sediment Control: Soil disturbance during this project, including equipment staging areas, will require erosion control measures. For projects that disturb more than an acre, a Notice of Intent (NOI) must be approved by the applicable State EPA, DOW or DEQ prior to any soil being disturbed as well as a storm water pollution prevention plan (SWPPP) reviewed and accepted by the government. For projects that disturb less than an acre of soil, an erosion control plan is required prior to soil disturbance.
1.9 NOT USED
1.10 NOT USED
1.11 NOT USED
1.12 NOT USED
1.13 NOT USED
2.0 NOT USED
3.0 GENERAL CONSTRUCTION REQUIREMENTS
3.1 SUMMARY
3.1.1 The requirements include:
a. Construction considerations and use of the premises.
b. Protection of personnel and Government property.
c. Construction facilities and job site standards.
d. The requirements of this section apply to the entire project including all amendments or modifications that may be issued to modify the contract documents.
3.2 GENERAL INFORMATION
3.2.1 Contractor shall have shared use of all spaces for execution of the construction work as defined in the requirements of this RFP; all areas are currently occupied. Entrance into and interface with the surrounding facilities shall be coordinated in advance with the Contracting Officer. The project site is within the fenced boundaries of a United States Department of Defense Military
Installation. Access will require advanced notice and security passes at all times. The contractor is responsible for obtaining all security passes.
3.2.2 The superintendent in charge of this work shall personally contact the Contracting Officer’s Representative a minimum of 72 hours before starting work on the contract, before restarting work after a lengthy delay, and prior to moving workers and equipment from one site of work to another.
3.2.3 Coordinate all construction activities with:
a. Contracting Officer’s Representative
b. Base Fire Department
c. Base Security/Police
d. Base Civil Engineer
e. Building Occupants
3.2.4 Prior to the start of any construction operations whatsoever, a schedule of work or operations in proper sequence shall be submitted by the contractor for approval by the Contracting Officer’s Representative so as to cause a minimum amount of disruption to the normal flow of traffic on streets, pedestrian travel, installation security, and facility operations.
3.2.5 Coordinate all Construction and Use of Premises Activities with the
Contracting Officer’s Representative.
3.2.6 Coordinate with Contracting Officer’s Representative the scheduling and routing of work, personnel access and material deliveries for the work.
3.2.7 The Contractor shall coordinate with Installation security regulations and personnel regarding worker and vehicle identification, badging, and permits.
3.2.8 High-ranking officers, foreign dignitaries, or DOD employees may approach you. Only the Contracting Officer can make changes to the contract.
3.3 DOCUMENTATION
3.3.1 Construction Plan:
3.3.1.1 Prior to the start of any onsite construction activities, the
Contractor shall submit a detailed construction plan. The plan shall include a detailed schedule of the major construction activities. Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area
(onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
3.3.1.2 Once the schedule is approved, do not deviate from the sequence, without prior written approval.
3.3.2 Waste Disposal:
3.3.2.1 Prior to the start of any onsite construction activities, the Contractor shall submit a written plan for disposing of waste materials resulting from work under this contract as described in this specification section.
3.4 CONSTRUCTION CONSIDERATIONS
3.4.1 Use of the Premises:
3.4.1.1 The Contractor’s use of the site, utility availability, and temporary facilities are described below.
3.4.1.2 WORK SCHEDULE: The Contractor shall schedule the work between the hours of 7:00 a.m. and 5:00 p.m. Monday through Friday except Federal Holidays.
a. Permission to perform any work outside of these hours, including weekends, must be in writing and submitted five (5) calendar days in advance for approval by the Contracting Officer.
b. The Government may or may not grant such permission at its discretion.
3.4.1.3 Work is anticipated to be performed during normal business hours. Work may be required to be performed on weekends if it is determined by the
Contracting Officer that work will be disruptive to any installation operations.
The Government will occupy areas adjacent to the work site during construction.
Contractor shall schedule and perform the work so as not to interfere with the
Government’s operations. The Contractor shall cooperate fully with the
Government during construction operations to minimize conflicts and to facilitate Government usage.
3.4.1.4 The Contractor will not be permitted to use existing toilet and wash facilities. The contractor shall provide his own toilet and wash facilities if desired.
3.4.1.5 Water, gas, and electricity will be furnished to the Contractor by the Government from the Government’s existing system outlets. Utilities will be furnished at no cost to the Contractor, except for telephone. The contractor is responsible for all coordination and the payment of all temporary telephone costs (setup and monthly charges).
3.4.1.6 UTILITY OUTAGES:
a. Any utility outages (gas, steam, electricity, and water) requested by the Contractor shall be submitted in writing no less than fourteen
(14) calendar days prior to proposed outage.
b. The Government reserves the right to reschedule the Contractor’s proposed outage if deemed necessary.
c. In the event utility outages cannot be performed on any facility due to critical operation impact, the utility outages and any related work shall be performed on non-duty hours.
d. Contractor shall notify the installation Fire Department prior to emergency utilities shutdown of the facilities.
3.4.1.7 Contractor Personal Vehicle Parking: The contractor may use a limited number of parking spaces in the existing lots for the contractor’s employee parking of personal vehicles. The Contractor shall coordinate with the Government on the exact number of available spaces, and shall make provisions to transport employees to the site should inadequate parking spaces be available on site. Parking in these areas is available on a first-come first served basis.
3.4.2 Project Site:
3.4.2.1 Contractor shall maintain a neat and orderly workplace with clear paths of emergency egress within the construction area.
3.4.2.2 Protection and Maintenance of Traffic: Prior to commencement of demolition and construction, the Contractor shall coordinate daily access and egress from the area of construction with the Contracting Officer, both vehicle and pedestrian. The Contractor shall confine construction personnel and equipment travel and operations to the area of work. The Contractor shall request approval for the limits of construction from the Government. The contractor shall coordinate access ways for personnel and equipment with the contracting officer.
a. The Contractor shall maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. The Contractor shall prepare a traffic plan
(vehicle and pedestrian) for the project area and submit it to the
Contracting Officer for review and approval.
b. The Contractor shall maintain and protect pedestrian traffic inside and outside of project area. The Contractor shall not cause traffic interference on any interior corridors without approval from the
Contracting Officer.
c. The traveling public shall be protected from damage to person and property.
3.4.2.3 Dust control. For interior work, the Contractor shall construct a dust partition wall around the interior perimeter of the space as necessary to prevent dust from travelling into the corridor space. For exterior work the contractor shall control all fugitive dust.
3.4.3 Storage of Materials:
3.4.3.1 The Contractor shall be responsible for the storage and safekeeping of all material to be incorporated into the work. The Contractor shall be responsible for all aspects of safety and security within the storage area.
3.4.3.2 Outside space is extremely limited on the installation for the storage of materials, the Contractor shall limit storage of materials to areas within project area. The Contractor shall indicate if the use of a supplemental or other staging area is desired.
a. Upon the Contractor’s request, the Contracting Officer will consider another or supplemental area for the Contractor’s use and storage of equipment, trailers, and materials; however, this will be solely at the discretion of the garrison and may not be approved. This area may not be in close proximity of the construction site but will be within the installation boundaries.
b. Fencing of materials or equipment will be required at storage locations; plastic strip inserts, colored green, must be used on the fence to screen the storage compound from the installation; fence posts must be embedded into grade as recommended by the manufacturer. The Contractor shall be responsible for cleanliness and orderliness of the area used and shall restore the area to its original condition upon completion of the project.
c. The Government will not provide utilities to the storage area.
3.4.3.3 Provide adequate storage facilitates for protection of materials and equipment. Materials and equipment shall be stored so as to ensure preservation of their quality of fitness for Work. Perishable items and items adversely affected by weather, rain, wind, dust, heat, or cold shall be stored within the designated area of construction, temporary waterproof sheds, or mobile facilities with raised floors, and heated if necessary. Other materials and equipment shall be stored on wooden platforms and not on the ground.
3.4.3.4 Storage facilities shall be clean, in good condition, undamaged and free of rust or surface deterioration. Rental trailers shall be of a neutral color. Unsightly material storage or office trailers will not be permitted.
3.4.3.5 The Contractor shall be responsible to maintain the condition of storage facilities, as defined above, and the entire construction site in a neat, orderly, professional and uncluttered manner at all times throughout the length of the contract.
3.4.4 Security:
3.4.4.1 Security requirements shall be observed at all times. The Contractor shall be responsible for maintaining satisfactory standards of employee competency, conduct, appearance, and integrity. Personnel working on or involved with security alarms, secure areas or security infrastructure shall be US
Citizens.
3.4.4.2 Construction operations shall be strictly confined to the designated area of Work.
3.4.4.3 The Contractor shall be responsible for the security of his own equipment.
3.4.5 Protection of Personnel and Government Property:
3.4.5.1 Contractor shall comply with all applicable Federal, State, and
Local safety codes, regulations, and requirements.
3.4.5.2 The Installation Safety Officer or his representative will attend preconstruction conferences to brief contractors on pertinent safety regulations and to provide guidance for safe operations during contract performance. Local safety guidance will be furnished to the Contractor for briefing his personnel.
3.4.5.3 The Contractor shall provide, no later than ten days after receiving
Notice of Award, four (4) copies of their written safety program to the
Contracting Officer for review. No construction shall commence until the
Contractor’s Safety Program has been reviewed and accepted by the Contracting
Officer.
3.4.5.4 It is the Contractor’s responsibility to maintain a secure construction site to prevent access to the work area by unauthorized personnel.
3.4.5.5 Safety posters, “hard hat area” posters, “authorized personnel only” posters, and any other notifications required by law shall be posted and maintained in sufficient quantity to be conspicuous on the job site.
3.4.5.6 The contractor shall protect all government property in adjacent areas from damages during the construction project; especially furniture and finishes.
In the event of damages of any nature caused by this work due to improper protection, precaution, or safety measures, such damages shall be repaired by the Contractor at no cost to the Government. In the event the Contractor does not satisfactorily repair or replace such damage caused by the work of this contract, the Government will make the necessary corrections and the Contractor shall reimburse the Government for inconveniences, labor, and materials, involved.
3.4.5.7 The Contractor shall erect and maintain temporary barricades to limit public access to hazardous areas.
a. Such barricades shall be required whenever safe public access is prevented by construction activities or as otherwise necessary to ensure safety of both pedestrian and vehicular traffic.
b. Barricades shall be securely placed, clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
3.4.6 Site Fire Protection:
3.4.6.1 Site fire protection shall conform to NFPA 241 and EM 385-1-1.
3.4.6.2 Fire extinguisher equipment shall be provided in storage areas according to the hazard present.
3.4.6.3 Fire extinguishers listed or approved by a nationally recognized testing laboratory shall be used.
3.4.6.4 Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.
3.4.7 Waste Disposal:
3.4.7.1 The Contractor is required to maintain a clean project site free of accumulating debris. Demolition debris and other construction waste shall be promptly disposed of at the end of each workday in proper waste containers maintained on the project site by the Contractor.
3.4.7.2 Environmentally hazardous or other construction debris with special disposal requirements shall be stored on the site and disposed of offsite in a proper lawful manner.
3.4.7.3 All debris shall be removed from the site on a regular basis. Waste shall not be allowed to accumulate.
3.4.7.4 Construction waste and debris maintained on-site prior to off-site disposal shall be controlled in a manner to eliminate any potential health or safety hazards.
3.4.7.5 Burning of waste or any other material on-site is strictly prohibited.
3.4.7.6 The project job site shall be “broom cleaned” at the end of each work day. The Contractor shall remove debris from the job site as it is generated and dispose of it in proper containers as outlined herein.
3.4.7.7 The Contractor shall coordinate dumpster location with the contracting officer.
3.5 CONTRACTOR DAMAGED FINISHES
Damage to any existing finishes or equipment, such as floors, ceilings, HVAC equipment, doors, paint, by the contractor shall be repaired or replaced by the contractor at the contractor’s expense to the satisfaction of the government.
4.0 NOT USED
5.0 NOT USED
6.0 NOT USED
7.0 ARCHITECTURAL
Upon completion of this project, the areas used by the contractor shall be returned to their condition prior to beginning the work. Items damaged by the contractor will be repaired, trash removed, and areas cleaned.
8.0 NOT USED
9.0 NOT USED
10.0 MECHANICAL AND ELECTRICAL
The contractor shall perform the following work to replace Chilled and Hot
Water Pumps and associated Motors at DFAS Building 21A, DSCC, Columbus, OH.
The replacement pumps are centrifugal pumps with the following details:
2x
Size: 6x8x13½A
HP: 125
RPM: 1800
Power: 230-460/60/3
Rating: 1680 gpm @ 165’ TDH
Motor: ODP, VFD Rated, Premium Efficient
2x
Size: 5x6x13½B
HP: 75
RPM: 1800
Power: 230-460/60/3
Rating: 1046 gpm @ 165’ TDH
Motor: ODPEE, VFD Rated, Premium Efficient
1x
Size: 12x14x17½A
HP: 150
RPM: 1200
Power: 230-460/60/3
Rating: 6030 gpm @ 80’ TDH
Motor: ODP, VFD Rated, Premium Efficient
2x
Size: 10x12x13½A
HP: 40
RPM: 1200
Power: 230-460/60/3
Rating: 3216 gpm @ 36’ TDH
Motor: ODPEE, VFD Rated, Premium Efficient
a. All demolition required to construct the project is included as part of the work of this Contract. The contractor shall take possession of the existing pumps(s) to be replaced and is responsible for its disposal.
b. Replacement pumps shall meet or exceed existing pumps’ capacity.
Contractor shall test baseline chiller and hot water flowrates leaving the plant. Fulling heating and cooling is required from the plant in order to take the reading. Coordination with the customer is required to ensure max flow is occurring when readings are taken. Contractor shall also test baseline flowrates after pump replacements to demonstrate adequate capacity.
c. Testing and installation of pumps may affect building occupants. If potential disruptions are expected, contractor shall coordinate with customer to minimize effects.
d. Pumps must be integrated into the existing Johnson Controls Metasys building management system which is a closed system configured with
Johnson Controls software and equipment.
11.0 NOT USED
12.0 NOT USED
13.0 NOT USED
14.0 NOT USED
Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers
(USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist
USACE contractors in their outreach efforts:
- U.S. Department of Labor Veterans’ Employment and Training Service (VETS):
https://www.dol.gov/vets/
- Federal Veteran Employment Information: https://www.fedshirevets.gov/
- Veterans Opportunity to Work (VOW) Program: https://www.benefits.va.gov/ vow/
- U.S. Army Warrior Transition Command Employment Index:
https://wct.army.mil/modules/employers/index.html
- Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes
(End of special contract requirement)
--End of Section –
SECTION 01 46 00.00 06
TOTAL BUILDING COMMISSIONING
PART 1 GENERAL
Conform to the commissioning procedures outlined in this specification.
1.1 SYSTEMS TO BE COMMISSIONED
Commission the following systems:
Heating, Ventilating, Air Conditioning, and Refrigeration Systems (HVAC)
Building Automation System
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 180 (2018) Standard Practice for Inspection and Maintenance of Commercial Building
HVAC Systems
ASHRAE 202 (2013; Addenda B 2018) Commissioning
Process for Buildings and System
ASSOCIATED AIR BALANCE COUNCIL (AABC)
ACG Commissioning Guideline (2005) Commissioning Guideline
US Army Corps of Engineers (USACE)
ER 25-345-1 Regulation No. 25-345-1Military
Publications SYSTEMS MANUAL
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
NEBB Commissioning Standard (2018) Whole Building Technical
Commissioning of New Construction
NATIONAL INSTITUTE OF BUILDING SCIENCES (NIBS)
NIBS Guideline 3 (2012) Exterior Enclosure Technical
Requirements for the Commissioning
Process
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA 1429 (1994) HVAC Systems Commissioning Manual, 1st Edition
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following to the COR for distribution:
SD-01 Preconstruction Submittals
Project Schedule; G, DO
Project construction schedule which includes commissioning milestone activities. Submit within 14 calendar days following the Construction Commissioning Coordination Meeting. Submit one hard copy and an electronic copy.
SD-06 Test Reports
PVT Procedures; G, DO
Submit no later than 14 calendar days prior to Performance
Verification Tests. Submit one hard copy and an electronic copy.
PVT Report; G, DO
Submit no later than 30 calendar days prior to Functional
Performance Tests. Submit one hard copy and an electronic copy.
Trend Log Report
Submit one electronic copy no later than 14 calendar days prior to
Functional Performance Tests.
Post-Construction Trend Log Report
Submit [one] hard copy and one electronic copy of the
Post-Construction Trend Log Reports, once for peak cooling season and once for peak heating season.
SD-07 Certificates
Certificate of Readiness; G, DO.
Submit no later than 14 calendar days prior to Functional
Performance Tests. Submit [one] hard copy and an electronic copy.
SD-10 Operation and Maintenance Data
Systems Training; G, DO
Submit two copies of the Systems Training recording no later than 14 calendar days following completing of the Systems
Training.
Training Plan; G, RO
Submit one hard copy and an electronic copy no later than 30 calendar days prior to the associated training.
Training Attendance Rosters; G, RO
Submit one hard copy and an electronic copy no later than
7]calendar days following the completion of the training for each system.
Systems Manual; G, DO
Submit Systems Manual no later than 30 calendar days following completion of Functional Performance Tests. Submit Three hard copies and an electronic copy.
Maintenance and Service Life Plans; G, DO
Submit the Maintenance Plan and Service Life Plan no later than 30 calendar days following the completion of Functional Performance tests. Submit three hard copies and an electronic copy.
1.4 COMMISSIONING SPECIALISTS
1.4.1 Government Commissioning Specialist (CxG)
The Government Commissioning Specialist will lead and oversee all commissioning work specified herein and be the primary point of contact regarding commissioning work.
1.5 Commissioning Standard
Comply with the requirements of the commissioning standard under which the Commissioning Specialists qualifications are approved. When the firm and specialists are certified by BCA or the University of
Wisconsin-Madison, comply with the requirements of one of the acceptable standards unless otherwise stated herein. The acceptable standards are ACG Commissioning Guideline, NEBB Commissioning
Standard, SMACNA 1429, or ASHRAE 202.
a. Implement all recommendations and suggested practices contained in the
Commissioning Standard and electrical test standards.
b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.
c. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.
d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract.
e. Use any new requirements, recommendations, and procedures published or adopted prior to contract solicitation by the body responsible for the
Commissioning Standard.
1.6 CERTIFICATE OF READINESS
Prior to scheduling Functional Performance Tests for each system, issue a
Certificate of Readiness certifying that the building system is ready for
Functional Performance Testing. The Certificate of Readiness must include, for each system to be commissioned, all equipment and system start-up reports; Performance Verification Test Reports; completed Pre-Functional
Checklists; Testing, Adjusting, and Balancing (TAB) Report; Trend Log
Review Report.
The Contractor; the Contractor's Quality Control Representative; and the
Mechanical, Electrical, Controls, and TAB subcontractor representatives must sign and date the Certificate of Readiness. Do not schedule and perform Functional Performance Tests prior to Government approval of the
Certificate of Readiness.
1.7 PROJECT SCHEDULE
Include the following tasks in the Project Schedule provided in accordance with section 01 32 01.00 06 PROJECT SCHEDULE. Ensure sufficient time is scheduled to accommodate the requirements of this specification section.
The order of items listed are not intended to imply a specified sequence:
a. Operational Tests of the plumbing systems (UFGS 22 00 00)
b. Disinfection of the plumbing systems (UFGS 22 00 00)
c. Manufacturer Equipment Start-Up for each system to be commissioned.
d. Testing, Adjusting, and Balancing (TAB)
e. TAB Verification / Field Acceptance Testing
f. Performance Verification Test
g. HVAC Trend Log Report
h. Pre-Functional Checklist Submittal
i. Functional Performance Testing
j. Demand Response Tests
k. Post-Test Deficiency Correction
l. Re-Testing
m. Training for each system to be commissioned
n. Systems Manual, Maintenance Plan, and Service Life Plan Submission
o. Seasonal Tests
p. Monitoring Based Commissioning Report Submission
q. Post-Construction Trend Log Reports
r. Post-Construction Building Site Visit
1.8 FUNCTIONAL PERFORMANCE TEST PREREQUISITES
Complete the following prior to starting Functional Performance Tests of the mechanical systems:
a. All equipment and systems have been completed, cleaned, flushed, disinfected, calibrated, tested, and operate in accordance with the contract documents and construction plans and specifications.
b. Testing, Adjusting, and Balancing has been completed and the Testing, Adjusting, and Balancing Report has been submitted and approved.
c. Performance Verification Tests of the controls systems have been completed and the Performance Verification Tests Report has been submitted and approved.
d. The Pre-Functional Checklists have been submitted and approved.
e. The Certificate of Readiness for the mechanical systems has been submitted and approved.
1.9 NOT USED
1.10 NOT USED
PART 2 NOT USED
3.0 NOT USED
3.1 CONSTRUCTION PHASE
3.1.1 Construction Commissioning Coordination Meeting
The Government Commissioning Specialist/CxG will lead a Construction
Commissioning Coordination Meeting no later than 30 calendar days after following construction notice to proceed to discuss the commissioning process including contract requirements, lines of communication, roles and responsibilities, schedules, documentation requirements, inspection and test procedures, and logistics as specified in this specification section.
The Contractor's Superintendent or Project Manager, the Contractor's
Quality Control Representative, the Commissioning Team, and the Government must attend this meeting. Invite the User to attend this meeting.
3.1.2 Commissioning Progress Meetings
The Government Commissioning Specialist/CxG must lead Commissioning
Progress Meetings to discuss the progress of commissioning process activities, upcoming commissioning activities, and any issues and deficiencies. The Contractor's Superintendent or Project Manager, the
Contractor's Quality Control Representative, and the Government must attend this meeting. A representative from each of the sub-contractors involved in the systems to be commissioned must attend this meeting. Invite the User to attend these meetings.
The Mechanical, Electrical, and Architectural designers of record must participate in the Commissioning Progress Meetings, at the request of the
Government Commissioning Specialist/CxG, to address any design issues or issues regarding technical adequacy.
Commissioning Progress Meetings must occur monthly following when installation of interior mechanical or electrical systems begins.
3.1.3 Construction Submittals
Provide all submittals associated with the systems to be commissioned, including shop drawings; equipment submittals; test plans, procedures, and reports; and resubmittals to the Commissioning Specialists. The
Commissioning Specialists must review the submittals to the extent necessary verify that the equipment and system installation will comply with the contract requirements and the requirements of the Basis of Design and the Owner's Project Requirements Document.
3.1.4 Inspection and Testing
Demonstrate that all system components have been installed, that each control device and item of equipment operates, and that the systems operate and perform in accordance with contract documents and the Owner's Project
Requirements. Requirements in related Sections are independent from the requirements of this Section and do not satisfy any of the requirements specified in this specification section. Provide all materials, services, and labor required to provide HVAC system trend logs, and to perform the
Functional Performance Tests.
3.2 NOT USED
3.2.1 NOT USED
3.2.2 NOT USED
3.2.3 NOT USED
3.2.4 NOT USED
3.2.5 NOT USED
3.2.6.1 Commissioning Team
Provide a commissioning representative for each sub-contractor associated with the systems to be commissioned. Each commissioning representative is responsible for coordination of their respective sub-contractor's execution of the commissioning activities and participation in the inspection and testing required by this specification section. The designers listed below must be the designer of record for the respective system. Substitutes must be approved by the Contracting Officer's Representative.
Designate team members to participate in the building envelope inspections, Pre-Functional checks, and the functional performance testing specified herein.
3.2.6.1.1 Mechanical Systems Team
The following team members must participate in Pre-Functional Checks and
Functional Performance Testing of mechanical systems. The CxG/QAR, CQC, MC, EC, and CC must participate in Demand Response Tests:
Designation Function
CxG Government Commissioning Specialist
QAR Contracting Officer's Quality Assurance Representative
CQC Contractor's Quality Control Personnel
MC Contractor's Mechanical Commissioning Representative
EC Contractor's Electrical Commissioning Representative
CC Contractor's Controls Commissioning Representative
TABC Contractor's TAB Commissioning Representative
PC Contractor's Plumbing Commissioning Representative
MD Mechanical Designer (Functional Performance Tests Only)
PD Plumbing Designer (Functional Performance Tests Only)
3.2.6.1.2. Testing, Adjusting, and Balancing (TAB) Verification
Following the testing, adjusting, and balancing of the systems and submission of a TAB Report and prior to scheduling Functional Performance
Tests, perform a TAB verification with the Contracting Officer's Quality
Assurance Representative/Government Commissioning Specialist.
Recheck a minimum of 10% of all readings listed in the TAB report during
TAB verification. The Contracting Officer's Quality Assurance
Representative/Government Commissioning Specialist will select the readings to be rechecked. If over 20% of the measurements rechecked fall outside of the specified tolerance from design requirements specified, recheck an additional 10% sample with selection of readings by the
Contracting Officer's Quality Assurance Representative/Government
Commissioning Specialist. If over 20% of the total rechecked readings fall outside of the required tolerance, the TAB Report will be considered invalid and all contract required testing, adjusting, and balancing work must be repeated.
Repair all insulation following completion of TAB Verification.
3.2.6.2 Performance Verification Test
Building Control System Performance Verification Tests The controls contractor must perform a Performance Verification Test (PVT) of the building control systems demonstrating that the control systems are in compliance with the requirements of the construction contract and accepted design. Show, step-by-step, the actions and results demonstrating that the systems perform in accordance with the sequences of operation. A one-point accuracy check will be performed for each sensor.
Prepare and submit PVT Procedures that list the step-by-step procedures to be performed during the tests and the expected results from each step that demonstrate contract and accepted design compliance. Start the
Performance Verification Tests only after approval of the PVT Procedures.
Provide a PVT Report documenting all tests performed during the PVT and the results. Document all failures and associated repairs in the PVT Report.
The Government Commissioning Specialist must review the PVT Procedures or
Test Plan and the PVT Report.
3.2.6.3 HVAC System Trend Logs
Following approval of the Performance Verification Test (PVT) Report and prior to Functional Performance Testing, the Government Commissioning
Specialist must review trend logs from the heating, ventilation, air-conditioning, and refrigeration control systems to ensure that the systems have stable operation and operate as required by construction contract, the accepted design, and the Owner's Project Requirements. Review trends for all items of equipment including sensor inputs; valve and damper positions
(command or feedback); equipment status, modes, and commands; and variable frequency drives, Provide a Trend Log Report that identifies any deficiencies noted in operation and includes a graphical representation of the trends.
3.2.6.4 Tests
3.2.6.4.1 Functional Performance Tests
Schedule personnel to attend the Functional Performance Tests for each system only after the Certificate of Readiness has been approved by the Government for the system and all deficiencies identified through any prior review, inspection, or test activity have been corrected. Functional Performance Tests must be performed with the Contracting Officer's Quality Assurance
Representative/Government Commissioning Specialist present. The Government
Commissioning Specialist will lead and document all Functional Performance Tests for the systems to be commissioned with the Contractor and appropriate subcontractors performing the Functional Performance Tests. The representatives listed in the paragraph Commissioning Team must attend the Functional Performance
Tests. Abort the Functional Performance Tests when any required commissioning team member is not present for the test. Abort Functional Performance Tests when any system deficiency prevents the successful completion of the test.
3.2.6.4.1.1 Checklists
Functional Performance Tests must be performed for each item of equipment and each…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .