RFI #2
1. Are there any requirements on the pipe?
36” Watertight/Bell End ASTM 48” Watertight/Bell End ASTM
OR do you need AASHTO (virgin) pipe
They need to know if you have any requirements of the pipe to quote it correctly.
Meeting provided ASTM will suffice. Pipe will need to sustain moderate vehicle traffic with appropriate installed soil cover.
2. The trucking company has asked us to clarify the distance from the entrance to McEntire to the stockpile locations?
No more than 3 miles