A24 - Questions and Responses.pdf

PDF 72 KB Posted

Attached to
B. Everett Jordan Lake Picnic Shelter
Solicitation number
W912PM25QA028
Issued by

About this file

This document is a Questions and Answers (Q&A) file for Solicitation Number W912PM25QA028 P00001, dated 11-Sep-25. The Q&A addresses two key points regarding a procurement opportunity: (1) delivery lead time and (2) scope of procurement. Specifically, the responses clarify that the contractor must deliver supplies no later than 60 calendar days after receiving the Notice of Award, and the quote covers only procurement and delivery of a structure, not its installation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question # Question Response

1 Can the lead time for delivery be more than 60 days from the award?

No, In accordance with paragraph 1.3 of the SOW “The contractor shall deliver the supplies no later than 60 calendar days after receipt of Notice of Award.”

Is the quote for procurement and delivery of the structure, but not for installation?

Yes, the quote is just for procurement and delivery.