This solicitation is for a construction project to build a toe protection system along bluffs in Norco, Riverside County, California. The project involves placing an earth fill embankment along approximately 7,330 feet of bluffs, with a 2H:1V slope revetted with 42-inch thick riprap. A launchable stone toe blanket will be installed to provide scour protection from the 100-year flow water surface elevation. The estimated construction cost range is $25-100 million. The period of performance is 720 calendar days. This is a 100% total small business set-aside solicitation conducted under FAR Part 14 sealed bidding. The NAICS code is 237990 and size standard is $36.5 million. A mandatory site visit is scheduled for May 17, 2021 at the provided location. Plans and specifications are available on SAM.gov under solicitation number W912PL21B0005.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Abstract Attachment W912PL21B0005 - sam.gov.pdf | ||
| SF 30 W912PL21B0005 - Amendment 0004- Final.pdf | ||
| SF 30 W912PL21B0005 - Amendment 0003- Final.pdf | ||
| W912PL21B0005_Amendment0002-Final.pdf | ||
| W912PL21B0005_Amendment0001-Final.pdf | ||
| For Information Only - Norco Bluffs - Pre-Bid-W912PL21B0005 Site Walk Sign In Sheet.pdf | ||
| W912PL21B0005_Solicitation_Specifications_VolumeII.pdf | ||
| W912PL21B0005_Solicitation_Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB No: W912PL21B0005
Lower Norco Bluffs Bluff Toe Protection
Santa Ana River - Prado Dam Riverside County, California
100% Total Small Business Set-Aside
Construction Solicitation and Specifications
VOLUME I
7 May 2021 Solicitation
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
PAGE OF PAGES
IMPORTANT - The "offer" section on the reverse must be fully completed by the offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE
9. FOR INFORMATION CALL
B. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12B. CALENDAR DAYS
YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour)
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212
Designed using Perform Pro, WHS/DIOR, Oct 96
1442-103 STANDARD FORM 1442 (REV. 4-85) (EG)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
W912PL21B0005 x
3. DATE ISSUED
7 May 2021 1 OF 1171
U.S.Army Corps of Engineers, Los Angeles Dist Attn:Contracting Division CESPL-CT-W 915 Wilshire Boulevard, Suite 930 Los Angeles, California 90017-3401
A. NAME
Michael G Robinson 213-452-3311
10 see 00 73 00
X X *Section 00 73 00
X 10
1 Digital 1:00 PM
7 June 2021 If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
X
8. ADDRESS OFFER TO
Bids are to be submitted electronically, DoD Secure Access File Exchange (DoD Safe) at https://safe.apps.mil/ in accordance with Section 00 21 13, Instructions Pertaining to Submission of Electronic Bids (APR 2020).
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date):
Lower Norco Bluffs Toe Protection, Riverside County, CA
The project consists of an earth fill placed against the existing bluffs, approximately 7,330 feet in length, revetted with riprap slope protection and a launchable stone toe blanket. The project will tie into existing high ground at the upstream and downstream project extents. The embankment fill will raise the grade between 12 and 25 feet above existing grade to provide protection up to a 100-year flow event water surface elevation (WSE).
Period of Performance is 720 Calendar Days. The Estimate cost range for this procurement is $25,000,000 - $100,000,000
This procurement is a 100% total Small Business Set Aside. The NAICS Code is 237990 "Other Heavy and Civil Engineering Construction. The size Standard is $39,500,000.00.
Be advised this project may delayed, postponed, canceled or revised at any time prior to award.
OFFER (Must be fully completed by offeror)
STANDARD FORM 1442 BACK (REV. 4-85)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal or greater than the minimum requirement stated in 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24.SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BYCODE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to the issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and
(c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD. (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN
(Type or print)
30B. SIGNATURE 30C. DATE
31A. NAME OF CONTRACTING OFFICER (Type or print)
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
DUNS NO.: TAX ID NO.:
CAGE CODE NO.:
( ) - ; FAX ( ) -
See Section 00 10 00 Solicitation Contract Line Item Number (CLIN) Schedule
Santa Ana Dams Resident Office 2493 Pomona Riccon Rd.
Corona, CA 92880
USACE, Finance Center
ATTN: CEFCO-AO-D
5722 Integrity Drive Millington, TN 38054-5005
00 01 05 Certification Page
CERTIFICATE OF OFFEROR’S PRINCIPAL
1) IF THE OFFEROR IS PARTNERSHIP OR JOINT VENTURE, LIST FULL NAME OF ALL PARTNERS/ JOINT VENTURERS (Add addendum as necessary):
(Company Name) (Signature) (Title)
(Company Name) (Signature) (Title)
(Company Name) (Signature) (Title)
2) IF THE OFFEROR IS A CORPORATION, THE FOLLOWING CERTIFICATION SHOULD BE COMPLETED:
CERTIFICATION AS TO CORPORATE PRINCIPAL
I, ______________________________, certify that I am the Secretary of the corporation named as principal in the within SF 1442; that ________________________________, who signed the SF 1442 at Block 20B on behalf of the principal, was the _________________________________________of the corporation; that I know the individual’s signature and that his/her signature is genuine; and that said Offer was duly signed, sealed and attested for on behalf of said corporation by authority of its governing body.
CORPORATE SEAL ______________________________________________
CORPORATE PRINCIPAL
SECRETARY
3) IF THE OFFEROR IS A LIMITED LIABILITY COMPANY/PARTNERSHIP, LIST FULL NAME OF ALL MANAGERS BELOW (Add addendum as necessary). SIGNATURES BY ALL MANAGERS HERE SIGNIFY THAT THAT THE INDIVIDUAL WHO SIGNED THE OFFER IN BLOCK 20B OF THE SF 1442 HAS THE AUTHORITY TO
BIND THE LIMITED LIABILITY COMPANY/PARTNERSHIP.
(Officer’s Name) (Signature) (Title)
(Officer’s Name) (Signature) (Title)
(Officer’s Name) (Signature) (Title)
Lower Norco Bluffs Toe Protection Riverside County, CA W912PL21B0005
7 May 2021
Section 00 01 05 Page 1 of 1 Solicitation
Riverside County, CA
W912PL21B0005
SF-1442 - SOLICITATION AND AWARD
00 01 05 CERTIFICATION PAGE
00 01 10 00 10 00
00 21 00 INSTRUCTIONS
00 21 13 INSTRUCTIONS TO BIDDERS
00 45 00 REPRESENTATION AND CERTIFICATIONS
00 70 00 CONDITIONS OF THE CONTRACT
00 73 00 SUPPLEMENTARY CONDITIONS
00 73 46 WAGE RATES
01 11 00 01 22 00 01 32 01 01 33 00 01 35 26 01 42 00 01 45 00 01 45 01 01 50 00
01 57 19
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00
03 30 53
03 36 00 GROUTING STONE PROTECTION
05 50 15
31 00 00
31 05 22 GEOTEXTILES USED AS FILTERS
31 09 13 31 11 00
31 23 19 DIVERSION AND CONTROL OF WATER
32 11 23 32 12 16 32 31 13
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
TEMPORARY ENVIRONMENTAL CONTROLS
CLOSEOUT SUBMITTALS
DIVISION 03 - CONCRETE
MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
CIVIL WORKS FABRICATIONS
DIVISION 31 - EARTHWORK
EARTHWORK
GEOTECHNICAL INSTRUMENTATION AND MONITORING
CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
AGGREGATE BASE COURSE
DIVISION 01 - GENERAL REQUIREMENTS
SUMMARY OF WORK
PRICE AND PAYMENT PROCEDURES
PROJECT SCHEDULE
RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
SUBMITTAL PROCEDURES
GOVERNMENTAL SAFETY REQUIREMENTS
SOURCES FOR REFERENCE PUBLICATIONS
QUALITY CONTROL
SECTION 00 01 10
TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
TABLE OF CONTENTS
HOT-MIX ASPHALT (HMA) FOR ROADS
CHAIN LINK FENCES AND GATES
7 May 2021
TABLE OF CONTENTS PAGE 1
W912PL21B0005
32 92 19 32 93 00
33 40 00
35 31 19
-- End of Project Table of Contents --
DIVISION 33 - UTILITIES
DIVISION 35 - STONE PROTECTION
STONE PROTECTION
SEEDING
EXTERIOR PLANTING
STORM DRAINAGE UTILITIES
7 May 2021
TABLE OF CONTENTS PAGE 2
W912PL21B0005
Item Description Estimated Quantity
Unit Unit Price
Amount
0001 Clear Site and Remove Obstructions 1 JOB JA $
0002 Diversion and Control of Water 1 JOB JA $
0003 Well Abandonment 6 EA $ $
0004 Sound Wall 9,700 LF $ $
0005 Excavation - General 87,000 CY $ $
0006 Weathered Rock Excavation 350 CY $ $
0007 Geotextile Stabilizer 65,000 SY $ $
0008 Geotextile Filter 41,750 SY $ $
0009 Miscellaneous Unsorted Rock 8,000 TON $ $
00010 Crushed Rock
00010A First 35,000 TON 35,000 TON $ $
00010B Over 35,000 TON 15,000 TON $ $
0011 Embankment Fill 220,000 CY $ $
0012 Engineered Fill 350 CY $ $
0013 Structural Fill 320 CY $ $
0014 42-inch Riprap 107,600 TON $ $
0015 15-inch Riprap 36,000 TON $ $
0016 Grouting 15-inch Grouted Stone 780 CY $ $
SECTION 00 10 00
SOLICITATION CONTRACT LINE ITEM (CLIN) SCHEDULE
Bidding Schedule
7 May 2021 1 Solicitation
W912PL21B0005
0017 Bedding 22,000 TON $ $
Item Description Estimated Quantity
Unit Unit Price
Amount
0018 Stone Infill 15,000 TON $ $
0019 Toe Backfill 86,800 TON $ $
0020 Asphaltic Concrete 3,300 TON $ $
0021 Aggregate Base Course 4,680 TON $ $
0022 Decomposed Granite 150 TON $ $
0023 4-foot Wide Concrete V-Ditch 6,520 LF $ $
0024 3-foot Wide Concrete V-Ditch 730 LF $ $
0025 3-foot Wide Concrete Swale 35 LF $ $
0026 2-foot Wide Concrete Swale 60 LF $ $
0027 6-inch Concrete Curb and Gutter 350 LF $ $
0028 6-inch Concrete Curb 170 LF $ $
0029 8-inch Concrete Curb 110 LF $ $
0030 Concrete Mow Curb 1,530 LF $ $
0031 Concrete Ramp 1 JOB JA $
0032 Weep Hole Pipes 1 JOB JA $
0033 Side Drain 1, Catch Basin 1 1 JOB JA $
0034 Side Drain 2, Catch Basin 2 1 JOB JA $
0035 Side Drain 3, Catch Basin 3 1 JOB JA $
0036 Side Drain 4, Catch Basin 4 1 JOB JA $
0037 Culvert 1 1 JOB JA $
7 May 2021 2 Solicitation
W912PL21B0005
0038 Stairs and Ramp At Culvert 1 1 JOB JA $
Item Description Estimated Quantity
Unit Unit Price
Amount
0039 Culvert 2 1 JOB JA $
0040 Stairs and Ramp At Culvert 2 1 JOB JA $
0041 Culvert 3 1 JOB JA $
0042 Stairs and Ramp At Culvert 3 1 JOB JA $
0043 20-foot Wide Pipe Swing Gate 2 EA $ $
0044 15-foot Wide Pipe Swing Gate 2 EA $ $
0045 Chain Link Fence 780 LF $ $
0046 Cable Fence 220 LF $ $
0047 Geotechnical Instrumentation and Monitoring
1 JOB JA $
0048 Landscape Planting and Hydroseeding 39 AC $ $
0049 Temporary Irrigation 39 AC $ $
0050 Landscape Establishment 39 AC $ $
0051 Borrow Area Restoration 1 Job JA $
0052 Reconstruction of Parking Lot Area 1 Job JA $
0053 Removable Metal Bollard 1 Job JA $
0054 City of Norco Utility Retrofit Work 1 Job JA $
$TOTAL ESTIMATED AMOUNT:
(Line Items 0001 through 0054)
7 May 2021 3 Solicitation
Section 00 21 00 Instructions
Table of Contents
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
52.204-16 Commercial and Government Entity Code Reporting (AUG 2020) 52.204-22 Alternative Line Item Proposal (JAN 2017)
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
52.214-5 SUBMISSION OF BIDS (DEC 2016)
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
52.216-1 TYPE OF CONTRACT (APR 1984)
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
52.228-1 BID GUARANTEE (SEP 1996)
52.232-13 NOTICE OF PROGRESS PAYMENTS (APR 1984)
52.232-38 SUBMISSION OF ELECTRONIC FUNDS TRANSFER INFORMATION WITH OFFER (JULY
2013)
52.233-2 SERVICE OF PROTEST (SEP 2006)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
252.204-7008 Compliance With Safeguarding Covered Defense Information Controls (OCT 2016)
252.211-7002 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS, STANDARDS, PLANS,
DRAWINGS, DATA ITEM DESCRIPTIONS, AND OTHER PERTINENT DOCUMENTS (DEC. 1991)
252.215-7008 ONLY ONE OFFER (JUL 2019)
Section 00 21 00 Page 1 of 13
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
(a) Definitions. As used in this provision--
Electronic Funds Transfer (EFT) indicator means a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for Award Management records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.
Registered in the System for Award Management (SAM) means that--
(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14) into SAM;
(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in SAM;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and
(4) The Government has marked the record ``Active''.
Unique entity identifier means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.
(b)(1) An Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ``Unique Entity Identifier'' followed by the unique entity identifier that identifies the Offeror's name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in SAM.
(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:
(1) Company legal business name.
(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(3) Company physical street address, city, state, and Zip Code.
(4) Company mailing address, city, state and Zip Code (if separate from physical).
(5) Company telephone number.
(6) Date the company was started.
Section 00 21 00 Page 2 of 13 Solicitation http://www.sam.gov/ http://www.sam.gov/
(7) Number of employees at your location.
(8) Chief executive officer/key manager.
(9) Line of business (industry).
(10) Company headquarters name and address (reporting relationship within your entity).
(d) Processing time should be taken into consideration when registering. Offerors who are not registered in SAM should consider applying for registration immediately upon receipt of this solicitation. See https://www.sam.gov for information on registration.
(End of Provision)
52.204-16 Commercial and Government Entity Code Reporting (AUG 2020)
(a) Definition. As used in this provision--
Commercial and Government Entity (CAGE) code means—
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity by unique location; or
(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.
(b) The Offeror shall provide its CAGE code with its offer with its name and location address or otherwise include it prominently in its proposal. The CAGE code must be for that name and location address. Insert the word "CAGE" before the number. The CAGE code is required prior to award.
(c) CAGE codes may be obtained via--
(1) Registration in the System for Award Management (SAM) at www.sam.gov. If the Offeror is located in the United States or its outlying areas and does not already have a CAGE code assigned, the DLA Commercial and Government Entity (CAGE) Branch will assign a CAGE code as a part of the SAM registration process. SAM registrants located outside the United States and its outlying areas shall obtain a NCAGE code prior to registration in SAM (see paragraph (c)(3) of this provision).
(2) The DLA Commercial and Government Entity (CAGE) Branch. If registration in SAM is not required for the subject procurement, and the Offeror does not otherwise register in SAM, an Offeror located in the United States or its outlying areas may request that a CAGE code be assigned by submitting a request at https://cage.dla.mil.
(3) The appropriate country codification bureau. Entities located outside the United States and its outlying areas may obtain an NCAGE code by contacting the Codification Bureau in the foreign entity's country if that country is a member of NATO or a sponsored nation. NCAGE codes may be obtained from the NSPA at https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx if the foreign entity's country is not a member of
Section 00 21 00 Page 3 of 13 Solicitation https://www.sam.gov/ http://www.sam.gov/ https://cage.dla.mil/ https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx
NATO or a sponsored nation. Points of contact for codification bureaus, as well as additional information on obtaining NCAGE codes, are available at http://www.nato.int/structur/AC/135/main/links/contacts.htm.
(d) Additional guidance for establishing and maintaining CAGE codes is available at https://cage.dla.mil.
(e) When a CAGE code is required for the immediate owner and/or the highest-level owner by Federal Acquisition Regulation (FAR) 52.204-17 or 52.212-3(p), the Offeror shall obtain the respective CAGE code from that entity to supply the CAGE code to the Government.
(f) Do not delay submission of the offer pending receipt of a CAGE code.
(g) If the solicitation includes FAR clause 52.204-2, Security Requirements, a subcontractor requiring access to classified information under a contract shall be identified with a CAGE code on the DD Form 254. The Contractor shall require a subcontractor requiring access to classified information to provide its CAGE code with its name and location address or otherwise include it prominently in the proposal. Each location of subcontractor performance listed on the DD Form 254 is required to reflect a corresponding unique CAGE code for each listed location unless the work is being performed at a Government facility, in which case the agency location code shall be used. The CAGE code must be for that name and location address. Insert the word "CAGE" before the number. The CAGE code is required prior to award.
(End of Provision)
52.204-22 Alternative Line Item Proposal (JAN 2017)
(a) The Government recognizes that the line items established in this solicitation may not conform to the Offeror's practices. Failure to correct these issues can result in difficulties in acceptance of deliverables and processing payments. Therefore, the Offeror is invited to propose alternative line items for which bids, proposals, or quotes are requested in this solicitation to ensure that the resulting contract is economically and administratively advantageous to the Government and the Offeror.
(b) The Offeror may submit one or more additional proposals with alternative line items, provided that alternative line items are consistent with subpart 4.10 of the Federal Acquisition Regulation. However, acceptance of an alternative proposal is a unilateral decision made solely at the discretion of the Government. Offers that do not comply with the line items specified in this solicitation may be determined to be nonresponsive or unacceptable.
(End of provision)
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b) (1) Bidders shall acknowledge receipt of any amendment to this solicitation--
(i) By signing and returning the amendment;
Section 00 21 00 Page 4 of 13 Solicitation http://www.nato.int/structur/AC/135/main/links/contacts.htm https://cage.dla.mil/
(ii) By identifying the amendment number and date in space provided for this purpose on the form for submitting a bid;
(iii) By letter;
(iv) By facsimile, if facsimile bids are authorized in the solicitation; or
(v) By email, if email bids are authorized in the solicitation.
(2) The Government must receive the acknowledgement by the time and at the place specified for receipt of bids.
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments.
The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it
Section 00 21 00 Page 5 of 13 would be prejudicial to other prospective bidders.
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV
1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.
Section 00 21 00 Page 6 of 13
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
(a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation.
(b) The Government may reject any or all bids, and waive informalities or minor irregularities in bids received.
(c) The Government may accept any item or combination of items, unless doing so is precluded by a restrictive limitation in the solicitation or the bid.
(d) The Government may reject a bid as nonresponsive if the prices bid are materially unbalanced between line items or subline items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount to allowing an advance payment.
(End of provison)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
(End of provision)
Section 00 21 00 Page 7 of 13
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY
SITE OF THE WORK (MAY 2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
19% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts
Section 00 21 00 Page 8 of 13 to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is City of Norco, Riverside County, California
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20% percent of the bid price or $3,000,000 whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
Section 00 21 00 Page 9 of 13
52.232-13 NOTICE OF PROGRESS PAYMENTS (APR 1984)
The need for customary progress payments conforming to the regulations in Subpart 32.5 of the Federal Acquisition Regulation (FAR) will not be considered as a handicap or adverse factor in the award of the contract. The Progress Payments clause included in this solicitation will be included in any resulting contract, modified or altered if necessary in accordance with subsection 52.232-16 and its Alternate I of the FAR. Even though the clause is included in the contract, the clause shall be inoperative during any time the contractor's accounting system and controls are determined by the Government to be inadequate for segregation and accumulation of contract costs.
(End of clause)
52.232-38 SUBMISSION OF ELECTRONIC FUNDS TRANSFER INFORMATION WITH
OFFER (JULY 2013)
The offeror shall provide, with its offer, the following information that is required to make payment by electronic funds transfer (EFT) under any contract that results from this solicitation. This submission satisfies the requirement to provide EFT information under paragraphs (b)(1) and (j) of the clause at 52.232-34, Payment by Electronic Funds Transfer--Other than System for Award Management.
(1) The solicitation number (or other procurement identification number).
(2) The offeror's name and remittance address, as stated in the offer.
(3) The signature (manual or electronic, as appropriate), title, and telephone number of the offeror's official authorized to provide this information.
(4) The name, address, and 9-digit Routing Transit Number of the offeror's financial agent.
(5) The offeror's account number and the type of account (checking, savings, or lockbox).
(6) If applicable, the Fedwire Transfer System telegraphic abbreviation of the offeror's financial agent.
(7) If applicable, the offeror shall also provide the name, address, telegraphic abbreviation, and 9-digit Routing Transit Number of the correspondent financial institution receiving the wire transfer payment if the offeror's financial agent is not directly on-line to the Fedwire and, therefore, not the receiver of the wire transfer payment.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
Contracting Office 915 Wilshire Blvd Suite 930 Los Angeles, CA 90017
Section 00 21 00 Page 10 of 13
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/content/regulations
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
N/A
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any DFARS (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
252.204-7008 Compliance With Safeguarding Covered Defense Information Controls
(OCT 2016)
Section 00 21 00 Page 11 of 13
Controlled technical information, covered contractor information system, covered defense information, cyber incident, information system, and technical information are defined in clause 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting.
(b) The security requirements required by contract clause 252.204-7012 shall be implemented for all covered defense information on all covered contractor information systems that support the performance of this contract.
(c) For covered contractor information systems that are not part of an information technology service or system operated on behalf of the Government (see 252.204-7012(b)(2))--
(1) By submission of this offer, the Offeror represents that it will implement the security requirements specified by National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171, ``Protecting Controlled Unclassified Information in Nonfederal Information Systems and Organizations'' (see http://dx.doi.org/10.6028/NIST.SP.800-171) that are in effect at the time the solicitation is issued or as authorized by the contracting officer not later than December 31, 2017.
(2)(i) If the Offeror proposes to vary from any of the security requirements specified by NIST SP 800-171 that are in effect at the time the solicitation is issued or as authorized by the Contracting Officer, the Offeror shall submit to the Contracting Officer, for consideration by the DoD Chief Information Officer (CIO), a written explanation of—
(A) Why a particular security requirement is not applicable; or
(B) How an alternative but equally effective, security measure is used to compensate for the inability to satisfy a particular requirement and achieve equivalent protection.
(ii) An authorized representative of the DoD CIO will adjudicate offeror requests to vary from NIST SP 800-171 requirements in writing prior to contract award. Any accepted variance from NIST SP 800-171 shall be incorporated into the resulting contract.
252.211-7002 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS, STANDARDS,
PLANS, DRAWINGS, DATA ITEM DESCRIPTIONS, AND OTHER PERTINENT DOCUMENTS
(DEC. 1991)
The specifications, standards, plans, drawings, data item descriptions, and other pertinent documents cited in this solicitation are not available for distribution but may be examined at the following location:
beta.sam.gov
252.215-7008 ONLY ONE OFFER (JUL 2019)
(a) Cost or pricing data requirements. After initial submission of offers, if the Contracting Officer notifies the Offeror that only one offer was received, the Offeror agrees to--
Section 00 21 00 Page 12 of 13 http://dx.doi.org/10.6028/NIST.SP.800-171
(1) Submit any additional cost or pricing data that is required in order to determine whether the price is fair and reasonable or to comply with the statutory requirement for certified cost or pricing data (10 U.S.C. 2306a and FAR 15.403-3); and
(2) Except as provided in paragraph (b) of this provision, if the acquisition exceeds the certified cost or pricing data threshold and an exception to the requirement for certified cost or pricing data at FAR 15.403-1(b)(2) through (5) does not apply, certify all cost or pricing data in accordance with paragraph (c) of DFARS provision 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, of this solicitation.
(b) Canadian Commercial Corporation. If the Offeror is the Canadian Commercial Corporation, certified cost or pricing data are not required. If the Contracting Officer notifies the Canadian Commercial Corporation that additional data other than certified cost or pricing data are required in accordance with DFARS 225.870-4(c), the Canadian Commercial Corporation shall obtain and provide the following:
(1) Profit rate or fee (as applicable).
(2) Analysis provided by Public Works and Government Services Canada to the Canadian Commercial Corporation to determine a fair and reasonable price (comparable to the analysis required at FAR 15.404-1).
(3) Data other than certified cost or pricing data necessary to permit a determination by the U.S. Contracting Officer that the proposed price is fair and reasonable [U.S. Contracting Officer to provide description of the data required in accordance with FAR 15.403-3(a)(1) with the notification].
(4) As specified in FAR 15.403-3(a)(4), an offeror who does not comply with a requirement to submit data that the U.S. Contracting Officer has deemed necessary to determine price reasonableness or cost realism is ineligible for award unless the head of the contracting activity determines that it is in the best interest of the Government to make the award to that offeror.
(c) Subcontracts. Unless the Offeror is the Canadian Commercial Corporation, the Offeror shall insert the substance of this provision, including this paragraph (c), in all subcontracts exceeding the simplified acquisition threshold defined in FAR part 2.
-END OF SECTION-
Section 00 21 00 Page 13 of 13
Section 00 21 13 Instructions to Bidders
Table of Contents
INQUIRIES
SPECIAL INSTRUCTIONS PERTAINING TO SUBMISSION OF ELECTRONIC BIDS (APR 2020)
INSTRUCTIONS FOR SUBMITTING ELECTRONIC BIDS:
INSTRUCTIONS TO FOLLOW ON THE SAFE WEBSITE:
RECEIPT OF SUBMISSIONS:
VIRTUAL BID OPENING PROCEDURES AND INSTRUCTIONS FOR BIDDER’S PARTICIPATON
CONTRACTOR RESPONSIBILITY, PRE-AWARD SURVEY INFORMATION TO BE SUBMITTED WITH
BID
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
OFFEROR'S CHECKLIST
Lower Norco Bluffs Toe Protection Riverside County, CA W912PL21B0005
7 May 2021 Section 00 21 13 Page 1 of 7
INQUIRIES
Any prospective offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders/offerors before submission of their bids/offers. Oral explanations or instructions given before award of a contract are not binding. Any information given to a prospective offeror concerning a solicitation will be furnished promptly to all other prospective offerors as an amendment to the solicitation, if that information is necessary in submitting offers or if lack of it would be prejudicial to other prospective bidders/offerors.
1. All inquiries relating to this solicitation are to be submitted via Bidder Inquiry in
ProjNet at https://www.projnet.org/projnet/
A. To submit and review bid inquiry items, offerors will need to be a current registered user, self-register into the ProjNet system.
To access the Bid Inquiry system, go to the ProjNet web page and fill in:
- Managing Agency – USACE
- Email address
- Key Access (this is the Bidder Inquiry Key – see below for key)
- Click on “Sign In”
- You will be prompted for the answer to your secret question on the next screen
If this is your first time accessing ProjNet, you will be directed to a screen titled, “User account not found. Please create one using the form below.” Fill in the requested information (name, company, city, phone #, etc.).
B. From this page, you may view all bidder inquiries or add an inquiry. Please note:
Offerors shall only submit one question per inquiry. All inquiries containing multiple questions may be rejected.
C. Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is:W912PL21B0005 The Bidder Inquiry Key is: SZ86UJ-AAP356
2. The Bidder Inquiry System will be unavailable for new inquires up to 5 business days prior to bid/proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary.
3. Offerors are requested to review the specifications in its entirety, review the Bidder
Inquiry System for answers to questions prior to submission of a new inquiry.
4. The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone
(Chicago). The telephone number for the ProjNet Call Center is 800-428-HELP.
Lower Norco Bluffs Toe Protection Riverside County, CA W912PL21B0005
7 May 2021 Section 00 21 13 Page 2 of 7
Solicitation https://www.projnet.org/projnet/ http://www.projnet.org/projnet/
5. Responses on the Bidder Inquiry System do not revise, change, amend or supersede the provisions of the solicitation. Changes to the solicitation must be by written amendment thereto. Any Bidder Inquiry System response that can be interpreted to be in conflict with the solicitation or amendment, shall be subordinate to the conflicting provision, term, and/or note, wherever it appears in the solicitation, until revised or altered by a written amendment to the solicitation.
6. Additionally, offerors may not anticipate a change to the solicitation until the change, revision, alteration of the solicitation is actually made, in writing and published as an amendment to the solicitation.
(End of Statement)
SPECIAL INSTRUCTIONS PERTAINING TO SUBMISSION OF ELECTRONIC BIDS (APR 2020)
The Bidder’s bid shall be submitted electronically, as described below. The IFB will provide the Government address and receipt date for bid submittal. The Bidder’s bid shall not contain classified data. The use of hyperlinks in bids is prohibited.
NOTE: The only authorized transmission method for bids in response to this solicitation is electronically via SAFE online submission. NO OTHER TRANSMISSION METHODS
(EMAIL, FACSIMILE, REGULAR MAIL, HAND CARRIED, ETC.) WILL BE ACCEPTED.
The Bidder’s bid must be received by the Government by the date/time specified in the solicitation.
Bidders shall email their bid using the following link: https://safe.apps.mil/ Please send bids using the link above to Contract Specialist Michael.g.robinson@usace.army.mil AND to Contracting Officer Suntok.Mcguinness@usace.army.mil.
INSTRUCTIONS FOR SUBMITTING ELECTRONIC BIDS:
In an effort to reduce paperwork and cost, all bids shall be submitted electronically through the SAFEsite. Submission shall be in Adobe PDF format. You are limited to twenty five (25) maximum files per upload (total size cannot exceed 8GB).
REQUEST FOR UPLOAD CODE: Bidders must email Contract Specialist Michael.G.Robinson@usace.army.mil and to Contracting Officer Suntok.Mcguinness@usace.army.mil no later than five (5) working days prior to the bid due date to receive a request code which will allow for file uploads via the SAFE site. Bidders who
Lower Norco Bluffs Toe Protection Riverside County, CA W912PL21B0005
7 May 2021 Section 00 21 13 Page 3 of 7
Solicitation mailto:Michael.g.robinson@usace.army.mil mailto:Suntok.Mcguinness@usace.army.mil mailto:Michael.G.Robinson@usace.army.mil mailto:Suntok.Mcguinness@usace.army.mil fail to email for request a code five (5) working days before bid submission date may not be able to receive a request code in time to upload their submission.
FILE DESCRIPTION: Include a “File Description” for each file(s) you upload.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .