BaseContract Item Description Estimate Quantity Comment
0003 Video and Photographic Documentation 1 JOB No QTY is available
0004 Temporary Retaining Structure 1 JOB N/A - Contractor's Design Item
0005 Work Platform 1 JOB N/A - Contractor's Design Item
| 0006 | Traffic Control and Coordination | 1 JOB |
| Drums = 60 ea. | |
| Lane Closed Sign = 7 ea. | |
| Road Work Ahead = 5 ea. | |
| Road Closed = 1ea. | |
| Flashing Arrow Panel = 1ea. | |
| Merge lane Traffic = 1 ea. | |
| Type III Barricade W/light = 9ea | |
| 0009 | Selective Demolition | 1 JOB |
| PZ = 34,490 SF | |
| 2-4" Dia. Steel Conduits = 100 lf | |
| Concrete Sack Protection = 1,100 SF | |
| 12" Dia RCP = 40lf | |
| 15" Dia. RCP = 40lf | |
| 20" Dia. D.I pipe water = 103 lf | |
| Timber Bulkhead = 725 lf | |
| 36" RCP = 85 lf | |
| 42" Dia. RCP = 35 lf | |
| 30" Dia. CMP = 50 lf | |
| 42" Dia. CMP = 35 lf | |
| 6- 12" Timber piles = 360 lf | |
| 3 - Manhole Brick (5' Dia x 8') = 18 CY | |
| Headwall = 2.5 CY | |
| Concrete wall cutting = 108 lf x 5" cut | |
| Concrete Removal = 2.5 CY | |
| 2-12"x12"x 10' - Concrete Cap | |
| 6" x 8" - Concrete curb = 80lf | |
| 0012 | Geotechnical Instrumentation | 1 JOB |
| Inclinometer = 4 ea. | |
| Probe pipe = 2 ea. | |
| 0013 | Clearing and Grubbing | 1 JOB |
| Area = 4 AC | |
| 0022 | Fertilizing, Seeding and Mulching | 1 JOB |
| Area = 4 AC | |
Opt 1 Item Description Estimate Quantity Comment
0003 Video and Photographic Documentation 1 JOB No QTY is available
0004 Temporary Retaining Structure 1 JOB N/A - Contractor's Design Item
0005 Work Platform 1 JOB N/A - Contractor's Design Item
| 0006 | Traffic Control and Coordination | 1 JOB |
| Drums = 58 ea. | |
| Lane Closed Sign = 2 ea. | |
| Road Work Ahead = 4 ea. | |
| Road Closed = 2ea. | |
| Flashing Arrow Panel = 1ea. | |
| Merge lane Traffic = 1 ea. | |
| Type III Barricade W/light = 5ea | |
| 0009 | Selective Demolition | 1 JOB |
| PZ = 17,250 SF | |
| 4-4" Dia. Steel Conduits = 65lf | |
| Concrete Sack Protection = 800 SF | |
| 15" Dia. RCP =15 lf | |
| 18" Dia. CMP = 90 lf | |
| 18" Dia. RCP = 45 lf | |
| 36" Dia. RCP = 105 lf | |
| 36" Dia. CMP = 40 lf | |
| 42" Dia. RCP = 65 lf | |
| 122"x78" RCPA = 20lf | |
| Concrete Drainage Structure Headwall = 17 CY | |
| Timber Head = 160 lf | |
| Concrete Wall Cutting = 55 lf x 5" cut | |
| Concrete Removal use= 1.5 CY | |
| 0012 | Geotechnical Instrumentation | 1 JOB |
| Inclinometer = 2 ea. | |
| Probe pipe = 1 ea. | |
| 0013 | Clearing and Grubbing | 1 JOB |
| Area = 3 AC | |
| 0022 | Fertilizing, Seeding and Mulching | 1 JOB |
| Area = 3 AC | |
Opt 2 Item Description Estimate Quantity Comment
0003 Video and Photographic Documentation 1 JOB No QTY is available
0004 Temporary Retaining Structure 1 JOB N/A - Contractor's Design Item
0005 Work Platform 1 JOB N/A - Contractor's Design Item
| 0006 | Traffic Control and Coordination | 1 JOB |
| Drums = 60 ea. | |
| Lane Closed Sign = 2 ea. | |
| Road Work Ahead = 4 ea. | |
| Road Closed = 2ea. | |
| Flashing Arrow Panel = 1ea. | |
| Merge lane Traffic = 1 ea. | |
| Type III Barricade W/light = 4ea | |
| 0009 | Selective Demolition | 1 JOB |
| PZ = 17,300 SF | |
| Concrete Sack Protection = 880 SF | |
| 15" Dia. RCP = 130 lf | |
| 18" Dia. CMP = 145 lf | |
| 18" Dia. RCP = 150 lf | |
| 36" Dia. RCP = 30 lf | |
| Concrete Drainage Structure Headwall = 10 CY | |
| Timber Head = 200 lf | |
| Riprap = 1 CY | |
| Concrete wall cutting = 55 lf x 0.5" thick | |
| Concrete Removal use = 1.5 CY | |
| 0012 | Geotechnical Instrumentation | 1 JOB |
| Inclinometer = 4 ea. | |
| Probe pipe = 2 ea. | |
| 0013 | Clearing and Grubbing | 1 JOB |
| Area = 5.0 AC | |
| 0022 | Fertilizing, Seeding and Mulching | 1 JOB |
| Area = 5.0 AC | |
Opt 3 Item Description Estimate Quantity Comment
0003 Video and Photographic Documentation 1 JOB No QTY is available
0004 Temporary Retaining Structure 1 JOB N/A - Contractor's Design Item
0005 Work Platform 1 JOB N/A - Contractor's Design Item
| 0006 | Traffic Control and Coordination | 1 JOB |
| Drums = 40 ea. | |
| Lane Closed Sign = 2 ea. | |
| Road Work Ahead = 4 ea. | |
| Road Closed = 2ea. | |
| Flashing Arrow Panel = 1ea. | |
| Merge lane Traffic = 1 ea. | |
| Type III Barricade W/light = 4ea | |
| 0009 | Selective Demolition | 1 JOB |
| PZ = 28,050 SF | |
| Concrete Sack Protection = 1,130 SF | |
| 15" Dia. RCP = 20 lf | |
| 18" Dia. CMP = 65 lf | |
| 18" Dia. RCP = 25 lf | |
| 36" Dia. RCP = 20 lf | |
| 22"x36" RCPA = 80lf | |
| 31"x51" RCPA = 12lf | |
| Concrete Drainage Structure Headwall = 3.0 CY | |
| Timber Head = 0 lf | |
| Riprap = 5.0 CY | |
| Concrete wall Cutting = 55lf x 0.5" | |
| Concret removal = 1.50 CY | |
| 0012 | Geotechnical Instrumentation | 1 JOB |
| Inclinometer = 4 ea. | |
| Probe pipe = 2 ea. | |
| 0013 | Clearing and Grubbing | 1 JOB |
| Area = 2.0 AC | |
| 0022 | Fertilizing, Seeding and Mulching | 1 JOB |
| Area = 2.0 AC | |