About this file

Amendment 0002

View the file

Other files

File Type Posted
B05_-_Bid_Abstract-b.pdf PDF
B05_-_Bid_Abstract-a.pdf PDF
B05_-_Bid_Abstract.pdf PDF
W912P816B0049BIDABSTRACT.pdf PDF
Am-0001.pdf PDF
A22_-_Solicitation_No._W912P8-16-B-0049.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

W912P8

The above numbered solicitation for Calcasieu River and Pass, LA, Dredge Material Management Plan (DMMP) Disposal Area "E" Retention Dike Construction, Cameron Parish, LA is hereby amended as follows:

1. See the attached changes.

2. Questions and Answers are included.

3. Bid Opening Date remains the same Tuesday, 13 September 2016 at 2:00 P.M. CST.

USACE, CONTRACTING DIVISION

ATTN: CEMVN-CT-W, ROOM 172/184

7400 LEAKE AVENUE

NEW ORLEANS, LA 70118-3651

SEE ITEM 6

J

W912P8-16-B-0049

09/06/2016

08/11/2016

SECTION 31 24 00.00

1. Page 5. Add the following new paragraph after paragraph 1.3.3:

“1.3.4 Existing Spill Box Installation

No separate measurement will be made for installation of the existing spill box.”

2. Page 5, paragraph 1.4.1. Delete this paragraph in its entirety and substitute the following therefore:

“1.4.1 Embankment

Payment for all fill material placed and compacted as required in embankments, including additional material placed by reason of foundation settlement during construction, will be made at the contract unit price per cubic yard for "Dike Construction". Price and payment shall constitute full compensation for furnishing all plant, labor, testing, employ of professional engineering services, equipment and material (except earth material), and performing all operations necessary for excavation, installation of the existing spill box, all testing, hauling, foundation preparation, material processing for moisture control, placing and compacting the material, surveys, and other incidental work required to complete the embankment or fill.”

3. Page 8, paragraph 3.1.1. Delete this paragraph in its entirety and substitute the following therefore:

“3.1.1 Dike Alignments

The horizontal dike centerline alignment controls and details are shown in the contract drawings. The Contractor shall field verify and ensure the exterior dike toe of the proposed dike is a minimum of 100-ft from the top of bank along the eastern lake side. In addition, the Contractor shall field verify and ensure the exterior dike toe of the proposed dike is a minimum of 100 feet from the interior toe of the existing foreshore stone dike. In the event the exterior dike toe is less than 100 feet from the lake side top of bank or the river side interior stone dike, the Contractor shall immediately bring this to the attention of the Government in writing. The Government will examine the information presented and inform the Contractor for an appropriate resolution in writing.

The dike alignment from the dike centerline station 60+00 to station 80+00 may require an alignment shift east based on actual field conditions by the Contractor. This reach of the alignment shall be field verified by the Contractor and coordinated with the Contracting Officer's Representative to determine if a new alignment for this reach is required.”

4. Page 12. Add the following new paragraph after paragraph 3.7:

“3.8 Spill Box Installation

The Contractor shall reinstall one (1) spill box at the location and elevation determined by the Contracting Officer Representative during the pre-construction meeting with the Government. The spill box to be installed shall be the existing spill box located on site at CDF "E". The Cost for the installation of the existing spill box shall be included in the unit price, Dike Construction.”

DRAWINGS

1. SHEET IDENTIFICATION No. G-03. Delete this drawing in its entirety and substitute the attached revised SHEET IDENTIFICATION No. G-03 therefore.

2. Add the attached new drawings identified as SHEET IDENTIFICATION Nos.

C-02A and C-03A.

Questions and Answers

Question 1. – Upon reviewing the prints and specifications we do not see where this solicitation calls out for fertilizing and seeding the berm after completion.

Answer – No. The P&S for this solicitation do not require fertilizing and seeding.

Question 2. - Has any material from virgin cuts been placed in the DMMA since the geotechnical data was collected? If so, can the government provide the volume of the virgin material?

Answer - The borings of Disposal Area "E" were performed between 2000 and 2003. Since that time frame, there has NOT been any specified dredging of virgin material through, say, enlargement of the Calcasieu River Ship Channel, or any other project in the area, which would have entailed placement of virgin material into Disposal Area "E". The only virgin material that would might been placed within Disposal Area "E" would have been simply incidental virgin material as a result of excessive dredging in the side slopes or over depth.

Question 3. - Is there a required compaction specification for the Dike’s?

Answer - See Section 31 24 00.00, Embankment, paragraph 3.5.2 Placement, Spreading, and Compaction. Compaction to the typical 90 or 95 percent maximum dry density is not required for this contract.