AMENDMENT_0001_LOCKPORT_PRAIRE_ECOSYSTEM_RESTORATION_WO_PLANSDWGS.pdf
PDF 593 KB Posted
- Solicitation number
- W912P6-18-B-0001
About this file
This File contains Amendment 0001 which includes all Attachments, with the exception of the Revised Specification Sections and Revised Drawing Sheets of which are attached herein this Notice under the following associated folders.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81G6671528129
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
RE: LOCKPORT PRAIRIE ECOSYSTEM RESTORATION, SECTION 219 PROJECT
A. This Amendment extends the Bid Opening Date and changes the Bid Opening time. Accordingly, all bid packages shall be submitted PRIOR to 1:00pm (Central Time) on December 20, 2017. Detailed instructions regarding the submittal of Bids is provided at Section 00 22 13 of the Solicitation document - SEE "IMPORTANT BID NOTES".
THE DESCRIPTION OF THIS AMENDMENTFOLLOWS ON THE FOLLOWING PAGE
1. CONTRACT ID CODE PAGE OF PAGES
1 57
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Dec-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P618B0001
X 9B. DATED (SEE ITEM 11)
17-Nov-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Dec-2017
CODE
U.S. ARMY ENGINEER DISTRICT, CHICAGO
231 SOUTH LASALLE STREET SUITE 1500
CHICAGO IL 60604-1437
W912P6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P618B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
B. REVISIONS to SECTION 00 10 00 – SOLICITATION:
The required response date/time has changed from 19-Dec-2017 02:00 PM to 20-Dec-2017 01:00 PM.
C. REVISIONS to SECTION 00 10 00 – SOLICITATION (CONTRACT FORM/BID SCHEDULE): The following are changes to the Bid Schedule, resulting in a revised, conformed Bid Schedule. Therefore, Bidders shall replace the previously issued Bid Schedule with the form provided hereunder and apply their bid prices accordingly.
CLIN 0007
The pricing detail quantity has decreased by 247.00 from 248.00 to 1.00.
The unit of issue has changed from Acre to Job.
CLIN 0009
The pricing detail quantity has increased by 22.00 from 74.00 to 96.00.
CLIN 0010
The pricing detail quantity has increased by 1.00 from 4.00 to 5.00.
SUBCLIN 0013AE
The pricing detail quantity has decreased by 83.00 from 84.00 to 1.00.
SUBCLIN 0013AF
The pricing detail quantity has decreased by 83.00 from 84.00 to 1.00.
SUBCLIN 0014AF
The pricing detail quantity has decreased by 68.00 from 69.00 to 1.00.
SUBCLIN 0014AG
The pricing detail quantity has increased by 5.00 from 64.00 to 69.00.
SUBCLIN 0015AE
The pricing detail quantity has decreased by 84.00 from 85.00 to 1.00.
SUBCLIN 0016AD
The pricing detail quantity has decreased by 112.00 from 113.00 to 1.00.
SUBCLIN 0017AD
The pricing detail quantity has decreased by 59.00 from 60.00 to 1.00.
SUBCLIN 0018AA
The pricing detail quantity has increased by 1.00 from 21.00 to 22.00.
SUBCLIN 0018AC
The pricing detail quantity has decreased by 20.00 from 21.00 to 1.00.
SUBCLIN 0018AD
The pricing detail quantity has increased by 3.00 from 12.00 to 15.00.
SUBCLIN 0018AF
The pricing detail quantity has decreased by 11.00 from 12.00 to 1.00.
D. REVISIONS to SECTION 00 22 13 - SUPPLEMENTARY INSTRUCTIONS TO BIDDERS: The following Bid Notes have been amended to include: 1) a new subparagraph under Paragraph 1 (Bid Conditions) and, 2) to inform of a change to the location of the Bid Opening Room (Paragraph 5, (1) ).
- IMPORTANT BID NOTES
1. BID CONDITIONS:
(5) With respect to Amendment No. 0001, as relating to CLINs 0018AB and 00018AE, quantity adjustments will be subject to the FAR Changes Clause giving the contractor an opportunity to submit a request for equitable adjustment. By no means would the quantity adjustment/increase exceed a volume requiring a new contract; however, if deemed appropriate, the government may proceed with a Competition in Contracting Act modification.
5. BID OPENING ROOM:
(1) The designated Bid Opening Room is located on the 15th floor at 231 South LaSalle Street, Suite
1500, Chicago, Illinois 60604.
E. USACE RESPONSE TO QUESTIONS: By way of this Amendment, the USACE responds to Contractors Questions as follows:
Question 1. Specifications mention that options may be awarded within 1,460 calendar days (4 years). With some of the options having 5 years of invasive species control, does this mean the project could potentially be 9 years?
Response: No, the project’s period of performance is 1825 calendar days (5 years). By way of this Amendment, Specification Section 01 22 00.00 10, Para 1.1.5.1, was clarified to state that Option CLINs 0018AB and 0018AE assumes 5 years of invasive species control and may be adjusted after the options are exercised to account for the remainder of years left in the contract. Any quantity adjustments will be subject to the FAR Changes Clause giving the contractor an opportunity to submit a request for equitable adjustment.
By no means would the quantity adjustment/increase exceed a volume requiring a new contract; however, if deemed appropriate, the government may proceed with a Competition in Contracting Act modification.
Question 2. Drain Tile Disablement is part of the base bid but will be happening throughout Prairie Bluff which is broken out into options. How will this work out if some of the Prairie Bluff options are not awarded?
What would be the requirements for restoration of these areas?
Response: The base contract CLINs as shown on Section 00 10 00 of the Solicitation includes drain tile disablement. The contractor will be required to disable the drain tiles at Prairie Bluff under the base contract to restore the site hydrology as described in the Specification Section 33 46 17.10, paragraph 1.1. Other restoration activities at each area of the prairie bluff will be completed upon award of the Option CLINS related to the bluff.
Question 3. There appears to be a possible mistake for item 0013AE. Is that supposed to be a bid quantity of 1 Job like the other Invasive Species Control Years 1-4 quantities?
Response: The unit of measure for Option CLIN 0013AE should be “Job”. By way of this Amendment, the Bid Schedule is corrected to change the unit of measure to Job. – see the enclosed revised Bid Schedule.
Question 4. There appears to be a mistake for item 0014AG. Is that supposed to be 69 acres to match the quantities given on plan sheet CE103 and to match the bid quantity for prescribed burning for that unit?
Response: The quantity for Option CLIN 0014AG is corrected by way of this Amendment to “69.” - see the enclosed revised Bid Schedule.
Question 5. Can you please clarify what Item 0004-Protection of Listed Species is supposed to include?
Response: This line item should include any labor necessary for maintaining flagging of endangered species protection areas as well as any costs incurred from special precautions to avoid impacting listed species on site as stated in paragraph 3.8 of Specification Section 01 57 20.01 03.
Question 6. The wage rates sheets provided in the specs are for Cook County, IL although project is in Will County, IL.
Response: By this Amendment, the government hereby replaces the Wage Determination included in the Solicitation package with the appropriate Wage Determination. Accordingly, General Decision Number IL170020, dated 09/22/2017 is hereby incorporated into the Solicitation and is attached hereto, wherein providing Cook County wages.
Question 7. Dry Mesic Prairie and Wet Prairie have oak species listed in the plugs/acre. Are these intended to be bare roots? Please clarify.
Response: By this Amendment, a paragraph was added to Specification Section 32 92 19.10 03, paragraph
2.4.1 to clarify the tree size requirements for the project. The revised Section is enclosed herewith this Amendment.
Question 8. Prescribed burning specifications mention that approximately 50% of Lockport Prairie Preserve will be burned each year of the contract. Item 0007 has a bid quantity of 248 acres which appears to be the whole base bid area for Lockport Prairie. Burning 50% for each year of the contract (5 years) would go over that bid quantity. Please clarify.
Response: Since the project areas will be burned multiple times throughout the contract duration, the unit of measure for the Prescription Burning CLINs have been revised by this Amendment from “AC” to “Job”. The project areas in acreage that will be burned are provided in para 1.9 of Specification Section 31 31 19.16.03.
- See enclosed Revised Bid Schedule
Question 9. Are the Priority 1-5 Additional plugs intended to be propagated plugs?
Response: Priority 1-4 Additional plugs (Option Items CLIN 0012AE – 0012AH) are not propagated plugs.
They are additional plugs to be purchased and installed in accordance with Specification Section 32 92 19.10
03 NATIVE PLANTS.
Question 10. Notes on plan sheets GC002 and GC003 state that work limits are approximately 50 feet inside property lines however the selective clearing specifications Objective # 3 says to remove all trees within 50 feet of Division Street east of the railroad tracks. Please clarify.
Response: The drawings have been revised by this Amendment to extend the work limits to the property line at Lockport Prairie Nature Preserve. - See the enclosed revised relevant drawing sheets
Question 11. If any or all of the option items for Native Planting are exercised, can the USACE provide a rough timeline for the overall planting schedule? Would the plantings be spread out evenly or would all of the plantings need to be completed in year two for example?
Response: In accordance to Section 32 92 19.10 03, paragraph 1.5, the Contractor is required to submit a yearly planting plan. The plan will include the timing of planting for approval. If and when the government awards the option items for Native Planting, we expect the seeds/plugs installed at the next growing season.
Question 12. For the Selective Clearing items, it was mentioned at the pre-bid meeting that all cut material would need to be hauled offsite, and burn piles would only be considered if there was a way to utilize them without impacting vegetation. It would appear at the time of the site visit that much of the area to be selectively cleared was poorly vegetated with invasive grasses. Would the USACE provide a firm answer on whether burn piles will be allowed in these areas? The amount of labor to haul offsite versus burning onsite will likely be vastly different.
Response: Refer to Specification Section 31 11 00, paragraph 1.5.2. Upon written approval from the COR, we will allow for onsite burn in such a way as to protect nearby woody and herbaceous species from heat damage. A statement will be added to paragraph 1.5.2 of the above Section to allow for Platform Style burn with locations approved by the COR for onsite burning and resulting ashes removed offsite.
Question 13. There are several questions regarding the CLINS for Invasive Species Control:
QUESTION 13A: Item Number 0005 – Which area(s) does this item refer to?
Response to 13A: CLIN 0005 includes invasive species control for the entire project area under the base contract except for project areas 2 north and south. CLIN 0006 includes invasive species control for project areas 2 north and south. This statement is added by this Amendment to Specification Section 01 22 00.00 10, para. 1.1.5.1 for clarification. – See the enclosed revised relevant Specification Section
QUESTION 13B: Item Number 0013AE – The unit price is in acres for this item, while the previous 4 years unit price is “job.” Is this correct?
Response to 13B: The unit of measure for Option CLIN 0013AE should be “Job” and is corrected by this Amendment – see the enclosed Revised Bid Schedule.
QUESTION 13C: Item Number 0018AB - The unit price for this is “job”, but there are no years associated with the line. Is this item for 1 year, 3 years, or 5 years?
Response to 13 C: By this Amendment, Specification Section 01 22 00.00 10, Para 1.1.5.1, was REVISED to state that OPTION CLINs 0018AB and 0018AE assumes 5 years of invasive species control and may be adjusted after the options are exercised to account for the remainder of years left in the contract. Any quantity adjustments will be subject to the FAR Changes Clause giving the contractor an opportunity to submit a request for equitable adjustment. By no means would the quantity adjustment/increase exceed a volume requiring a new contract; however, if deemed appropriate, the government may proceed with a Competition in Contracting Act modification.
QUESTION 13D: Item Number 0018AE- The unit price for this is “job”, but there are no years associated with the line. Is this item for 1 year, 3 years, or 5 years?
Response to 13D: By this Amendment, Specification Section 01 22 00.00 10, Para 1.1.5.1, was REVISED to state that OPTION CLINs 0018AB and 0018AE assumes 5 years of invasive species control and may be adjusted after the options are exercised to account for the remainder of years left in the contract. Any quantity adjustments will be subject to the FAR Changes Clause giving the contractor an opportunity to submit a request for equitable adjustment. By no means would the quantity adjustment/increase exceed a volume requiring a new contract; however, if deemed appropriate, the government may proceed with a Competition in Contracting Act modification.
Question 14. Under the Price and Payment Procedures, section 1.1.5.1 Payment says “….Under the base contract and optional contract line item numbers (CLINS) 001BAA and 0019AE, the Contractor will be paid 20 percent of the job price for years 1,2,3,4, and 5. It doesn’t appear that either of those numbers are CLINS for this project; which CLINS are they referring to?
Response: These CLINs are shown in error and are corrected via this Amendment – see the enclosed Revised Bid Schedule.
Question 15. Site Access - Will ATVs or trucks be allowed to access the site along the existing two-track path on the south side of Division Street?
Response: Trucks and other vehicles are only allowed on Division Street at Lockport Prairie. ATVs/UTVs are allowed only on access routes shown on plan sheets GC002 and GC003 at Lockport Prairie. Trucks, tractors, ATVs, and other equipment is allowed on site at Prairie Bluff Preserve throughout the project area, provided that rutting and other damage to the site is avoided.
Question 16. The legend on sheet CE104 outlines the planting area as 4 acres while Bid Item 0010 is only for 2 acres. Which acreage should we use?
Response: The CLIN 0010 of the bid schedule and Sheet CE104 both shows 4 Acres. However, both areas will be revised to 5 AC due to the changes in the work limits. By way of this amendment CLIN 0010 quantity will be changed to 5 AC and planting area on CE104 will be changed to 5 AC.
Question 17. What CLIN would any PRE-seeding/ planting work fall under?
Response: Pre-planting work will be cover under Native Planting CLINs as specified in Specification Section 01 22 00.00 10, paragraph 1.2.2. Payment for native plants include appropriate component to complete the work as described in Specification Section 01 22 00.00 10, which covers work for pre-planting.
Question 18. How many acres is CLIN 0005 and 0006?
Response: By way of this amendment, the acres for CLINs 0005 and 0006 will be provided in Specification Section 01 22 00.00 10, Para 1.1.5.1.
Question 19. What is the duration of invasive species control for CLIN 0005 and 0006?
Response: Specification Section 31 31 19.13, paragraph 1.1 states that invasive species control will be completed over the span of the contract to satisfy the yearly performance criteria contained in paragraph 3.10.
Question 20. Section 01 57 20.01 Paragraph 3.8.3 states “any herbicide application occurring within a 65 foot buffer of HED larval habitat shall be applied via hand wicking and using a USFWS aquatic approved herbicide and surfactant.” Are ALL of the HED larval habitat areas outlined on Sheets GC002 and GC0003?
Response: Yes, the HED habitat areas are shown on sheets GC002 and GC0003. As stated on note 2 of these sheets, the HED areas will be updated by others prior to construction.
Question 21. For initial tree clearing are we following the spec section 31 11 00 1.1.2 objectives 1-6 to guide the removal of large trees to be cut and removed and then during establishment treating/girdling any other species encountered that are on table 1 section 31 31 19.13? The alternative would be to remove any tree of any size on table 1 in section 31 31 19.13 during the initial clearing. What is the intent?
Example: black cherry is not mentioned in the tree clearing section but it is on the table. If we find a 10 inch cherry should it be removed from site during the initial clearing?
Response: The contract requires all targeted trees to be treated initially to meet the performance criteria stated in Specification Section 31 11 00, paragraph 3.2. Follow-up treatments will be made of resprouts over the course of the contract to meet the performance criteria in Section 31 31 19.13 paragraph 3.10.
Black cherry (Prunus serotina) is mentioned in Specification Section 31 11 00, paragraph 1.1.2 and Table 1 of Specification Section 31 31 19.13.
Question 22. In the option for plugs, is it on the contractor to collect the seed for the “Propogated Plugs”?
Also, for the “Additional Plugs”, are these plugs to be from the same seed source as the “Propogated Plugs” or will any seed source of local genotype (200 mi radius of project site) be acceptable?
Response: Refer to section 32 93 01.00 03, paragraph 1. The project scopes states that propagated plugs will be collected from onsite sources. The paragraph was revised by this Amendment to clarify that the contractor will collect these seeds, grow them into plugs, and installation of the plugs at the project site. – see the enclosed revised relevant Specification Section
Additional plugs will be readily available plugs purchased through commercial source and similar type of plugs listed in Specification Section 32 92 19.10 03. Additional clarification has been provided via this Amendment in Specification Section 01 22 00.00 10. – see the enclosed revised relevant Specification Section Question 23. Our question refers to Section 32 92 19.10 03 - Native Plants and Section 32 93 01.00 03 - Propagated Plug Production & Planting.
The native plants specification contains a table with various species of plant plugs with a number / acre to be planted in the various locations throughout the project. Is it the owners intention that the contractor obtain these various species commercially? In other words, the only plant material that will be propagated from on-site sources will be for the CLINs that specifically call out propagated material and these species will be determined by the owner and contractor during the course of the project, correct?
Response: Plant material for installation for this project may be procured from commercial sources provided that the appropriate plant origin specifications are met as referenced in Specification Section 32 92 19.10 03, paragraph
2.4.2. Plant material from within the prescribed ranges will be accepted, and any commercially sourced plant material from outside the prescribed ranges will be considered on a case by case basis. Seed collected from on site or other very local sources is required for any plants provided under section 32 93 01.00 03.
Question 24. We have a question about the plug species listed in the native restoration specification. Some of the species listed are trees but we don’t see a specification for tree planting or even a specified size for the plant material. Please clarify.
Response: By this Amendment, a paragraph was added to Specification Section 32 92 19.10 03, paragraph 2.4.1 to clarify the tree size requirements for the project. The revised Section is enclosed herewith this Amendment. Refer to Specification Section 32 92 19.10 03 for additional information for tree planting.
F. CHANGES TO SPECIFICATIONS SECTIONS: The REVISED Specification Sections follow and are hereby incorporated into the Solicitation. The Revised Pages are enclosed herewith.
a. SECTION 01 22 00.00 10, PRICE AND PAYMENT PROCEDURES, para.
1.1.5.1 - 0ptional CLINs 0018AB and 0018AE are shown in error and were corrected. A statement was added to the paragraph to clarify that the CLINs assumes invasive species control for 5 years and may be adjusted at the time of award to account for the remainder of years left in the contract. A statement was also added to this paragraph to clarify the difference between CLINs 0005 and 0006.
b. SECTION 01 22 00.00 10, PRICE AND PAYMENT PROCEDURES, para. 1.1.7 & para. 1.2.5 -Due to the change in the unit of measure for Prescribed Burning, para 1.2.5 was removed under the unit price section and para 1.1.7 was added describing the lump sum payment procedure.
c. SECTION O l 22 00.00 10, PRICE AND PAYMENT PROCEDURES, para.
1.2.4 -A statement was added to clarify that additional plugs will be derived from the plant list provided in Section 32 92 19.10.
d. SECTION 31 11 00, SELECTIVE CLEARING, para 1.5.2- A note was added to this paragraph to state that Platform Style Burn will be acceptable and resulting ashes from burn activities must be disposed offsite.
e. SECTION 31 31 19.16 03, PRESCRIBED BURNING, para. 1.9 -The CLINs unit of measure for the Prescription Burns will be revised from "acre" to "Job". For the contractor's reference, the project areas in acreage to be burned are provided in para
1.9 of this section.
f. SECTION 32 92 19.10 03, NATIVE PLANTS, para 2.4.1 -A paragraph was added to clarify the tree size requirements for the project.
g. SECTION 32 93 01.00 03, PROPAGATED PLUG PRODUCTION AND PLANTING, para. 1 -A statement was added to clarify that the contractor will be responsible to collect seeds to grow as plugs and installation of the plugs at the project site.
G. CHANGES TO DRAWING SHEETS: The following REVISED Drawing Sheets are hereby incorporated into the Solicitation and are enclosed herewith.
Sheets GC002, GC003, GC005, GC006, CElOl, CE102, & CE104: the work limits were revised on these sheets to show the work limits extension to the property lines.
H. WAGE DETERMINATION: As described in the aforementioned USACE’s Response to Question 6., the USACE is providing the correct Wage Determination herein this Amendment;
thereby incorporated into the Solicitation.
I. PREAWARD SURVEY FORM: Attached is a Pre-Award Survey Form that will aid in the USACE’s process of conducting a preaward survey of the winning Bidder. Please fully complete and submit said form with your Bid.
J. PRE-BID MEETING ATTENDANCE SHEET: The pre-bid meeting attendance sheet is attached herein at the end of this amendment.
(END OF SUMMARY OF CHANGES – THE REVISED BID SCHEDULE, NEW WAGE RATES,
PREAWARD SURVEY FORM, ATTENDANCE SHEET (PREBID MEETING), AND REVISED
SPECIFICATIONS AND PLAN SHEETS FOLLOW)
REVISED BID SCHEDULE - AMENDMENT 0001
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
MOBILIZATION
FFP
Under this CLIN, the Contractor is required to perform mobilization activities. The Contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.
Payment Provisions The Government will pay costs for the mobilization of all of the Contractor's plant and equipment at the unit price for this item. The Contracting Officer or a Representative may require the Contractor to furnish data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment determined by the Contracting Officer of the actual costs, which is not subject to appeal.
MILSTRIP: W81G6671528129
PURCHASE REQUEST NUMBER: W81G6671528129
NET AMT
0002 1 Job
DEMOBILIZATION
FFP
Under this CLIN, the Contractor is required to perform demobilization activities.
The Contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force to the project site.
Payment Provisions The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the unit price for this item. The Contracting Officer or a Representative may require the Contractor to furnish cost data to justify the bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment determined by the Contracting Officer of the actual costs, which is not subject to appeal.
0003 1 Job
PROJECT & SAFETY SIGNS
0004 1 Job
PROTECTION OF LISTED SPECIES
0005 1 Job
INVASIVE SPECIES CONTROL
0006 1 Job
INVASIVE SPECIES CONTROL
INVASIVE SPECIES CONTROL - AREA 2 NORTH AND SOUTH
0007 1 Job
PRESCRIPTION BURN
0008 1 Job
DRAIN TILE DISABLEMENT
0009 96 Acre
SELECTIVE CLEARING
0010 5 Acre
NATIVE PLANTING - AREA 2 SOUTH
0011 1 Lot
PERFORMANCE AND PAYMENT BOND (BASE WORK)
FFP
PERFORMANCE AND PAYMENT BONDS ASSOCIATED WITH LINE ITEMs 0001 through 0010
THIS IS A COST-REIMBURSABLE LINE ITEM - The Government will reimburse the Contractor for the actual cost of acceptable performance and payments bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly.
Adjustment(s) to the line item will also be made for any revisions to the actual bond costs associated with contract changes.
OPTION OPTION - PLUGS
FFP
This Line Item identifies the work description that relates directly to Sub-line Items 0012AA THROUGH 0012AJ. The Sub-line Items themselves identify the quantities required to execute the work associated with the respective Station.
Therefore, the Contractor shall provide its pricing separately at Sub-line Items
0012AA THROUGH 0012AJ.
0012AA 10,000 Each
OPTION PRIORITY 1 - PROPAGATED PLUGS
0012AB 10,000 Each
OPTION PRIORITY 2 - PROPAGATED PLUGS
0012AC 10,000 Each
OPTION PRIORITY 3 - PROPAGATED PLUGS
0012AD 10,000 Each
OPTION PRIORITY 4 - PROPAGATED PLUGS
0012AE 10,000 Each
OPTION PRIORITY 1 - ADDITIONAL PLUGS
0012AF 10,000 Each
OPTION PRIORITY 2 - ADDITIONAL PLUGS
0012AG 10,000 Each
OPTION PRIORITY 3 - ADDITIONAL PLUGS
0012AH 10,000 Each
OPTION PRIORITY 4- ADDITIONAL PLUGS
0012AJ 1 Lot
OPTION PERFORMANCE AND PAYMENT BOND (PLUGS)
FFP
PERFORMANCE AND PAYMENT BONDS ASSOCIATED WITH LINE ITEMs 0012AA through 0012AH
THIS IS A COST-REIMBURSABLE LINE ITEM - The Government will reimburse the Contractor for the actual cost of acceptable performance and payments bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly.
OPTION PRAIRIE BLUFF NW
FFP
This Line Item identifies the work description that relates directly to Sub-line Items 0013AA THROUGH 0013AH. The Sub-line Items themselves identify the quantities required to execute the work associated with the respective Station.
0013AA THROUGH 0013AH.
0013AA 1 Job
OPTION INVASIVE SPECIES CONTROL, YEAR 1
0013AB 1 Job
OPTION INVASIVE SPECIES CONTROL, YEAR 2
0013AC 1 Job
OPTION INVASIVE SPECIES CONTROL, YEAR 3
0013AD 1 Job
OPTION INVASIVE SPECIES CONTROL, YEAR 4
0013AE 1 Job
OPTION INVASIVE SPECIES CONTROL, YEAR 5
0013AF 1 Job
OPTION PRESCRIPTION BURN
0013AG 84 Acre
OPTION NATIVE PLANTING
0013AH 1 Lot
OPTION PERFORMANCE AND PAYMENT BOND (BLUFF NW)
FFP
PERFORMANCE AND PAYMENT BONDS ASSOCIATED WITH LINE ITEMs 0013AA through 0013AG
THIS IS A COST-REIMBURSABLE LINE ITEM - The Government will reimburse the Contractor for the actual cost of acceptable performance and payments bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly.
OPTION PRAIRIE BLUFF W
FFP
This Line Item identifies the work description that relates directly to Sub-line Items 0014A THROUGH 0014AH. The Sub-line Items themselves identify the quantities required to execute the work associated with the respective Station. Therefore, the Contractor shall provide its pricing separately at Sub-line Items 0014AA
THROUGH 0014AH.
0014AA 1 Job
0014AB 1 Job
0014AC 1 Job
0014AD 1 Job
0014AE 1 Job
OPTION INVASIVE SPECIES CONTROL, YEAR 5
0014AF 1 Job
0014AG 69 Acre
0014AH 1 Lot
OPTION PERFORMANCE AND PAYMENT BOND (BLUFF W)
FFP
PERFORMANCE AND PAYMENT BONDS ASSOCIATED WITH LINE ITEMs
0014AA THROUGH 0014AG.
--THIS IS A COST-REIMBURSABLE LINE ITEM - The Government will reimburse the Contractor for the actual cost of acceptable performance and payments bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly.
OPTION PRAIRIE BLUFF SW
FFP
This Line Item identifies the work description that relates directly to Sub-line Items 0015AA THROUGH 0015AG. The Sub-line Items themselves identify the quantities required to execute the work associated with the respective Station.
0015AA THROUGH 0015AG.
0015AA 1 Job
0015AB 1 Job
0015AC 1 Job
0015AD 1 Job
0015AE 1 Job
0015AF 85 Acre
0015AG 1 Lot
OPTION PERFORMANCE AND PAYMENT BOND (BLUFF SW)
FFP
PERFORMANCE AND PAYMENT BONDS ASSOCIATED WITH LINE ITEMs
0015AA THROUGH 0015AF.
THIS IS A COST-REIMBURSABLE LINE ITEM - The Government will reimburse the Contractor for the actual cost of acceptable performance and payments bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly.
OPTION PRAIRIE BLUFF SE
FFP
This Line Item identifies the work description that relates directly to Sub-line Items 0016AA THROUGH 0016AF. The Sub-line Items themselves identify the quantities required to execute the work associated with the respective Station.
0016AA THROUGH 0016AF.
0016AA 1 Job
0016AB 1 Job
0016AC 1 Job
0016AD 1 Job
0016AE 113 Acre
0016AF 1 Lot
OPTION PERFORMANCE AND PAYMENT BOND (BLUFF SE)
FFP
PERFORMANCE AND PAYMENT BONDS ASSOCIATED WITH LINE ITEMs 0016AA through 0016AE.
THIS IS A COST-REIMBURSABLE LINE ITEM - The Government will reimburse the Contractor for the actual cost of acceptable performance and payments bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly.
OPTION PRAIRIE BLUFF NE
FFP
This Line Item identifies the work description that relates directly to Sub-line Items 0017AA THROUGH 0017AF. The Sub-line Items themselves identify the quantities required to execute the work associated with the respective Station.
0017AA THROUGH 0017AF.
0017AA 1 Job
0017AB 1 Job
0017AC 1 Job
0017AD 1 Job
0017AE 60 Acre
0017AF 1 Lot
OPTION PERFORMANCE AND PAYMENT BOND (BLUFF NE)
FFP
PERFORMANCE AND PAYMENT BONDS ASSOCIATED WITH LINE ITEMs 0017AA through 0017AE.
THIS IS A COST-REIMBURSABLE LINE ITEM - The Government will reimburse the Contractor for the actual cost of acceptable performance and payments bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly.
OPTION OPTION AREA 1 (COMED)
FFP
This Line Item identifies the work description that relates directly to Sub-line Items 0018AA THROUGH 0018AG. The Sub-line Items themselves identify the quantities required to execute the work associated with the respective Station.
0018AA THROUGH 0018AG
0018AA 22 Acre
OPTION SELECTIVE CLEARING - AREA 1 NORTH
0018AB 1 Job
OPTION INVASIVE SPECIES CONTROL - AREA 1 NORTH
0018AC 1 Job
OPTION PRESCRIPTION BURN - AREA 1 NORTH
0018AD 15 Acre
OPTION SELECTIVE CLEARING - AREA 1 SOUTH
0018AE 1 Job
OPTION INVASIVE SPECIES CONTROL AREA 1 SOUTH
0018AF 1 Job
OPTION PRESCRIPTION BURN - AREA 1 SOUTH
0018AG 1 Lot
OPTION PERFORMANCE AND PAYMENT BOND (COMED)
FFP
PERFORMANCE AND PAYMENT BONDS ASSOCIATED WITH LINE ITEMs 0018AA through 0018AF
THIS IS A COST-REIMBURSABLE LINE ITEM - The Government will reimburse the Contractor for the actual cost of acceptable performance and payments bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly.
SUMMATION OF BID PRICES:
Bid Amount for Base Items 0001 through 0011:$______________
Bid Amount for Option Items 0012AA through 0012AJ: $_______________
Bid Amount for Option Items 0013AA through 0013AH: $______________
Bid Amount for Option Items 0014AA through 0014AH:$_______________
Bid Amount for Option Items 0015AA through 0015AG:$_______________
Bid Amount for Option Items 0016AA through 0016AF:$_______________
Bid Amount for Option Items 0017AA through 0017AF:$_______________
Bid Amount for Option Items 0018AA through 0018AG:$______________
TOTAL OVERALL BID AMOUNT FOR ITEMS 0001 THROUGH 0018AG (includes all Options and Sub-Items for the respective CLINs): $______________________________
END OF REVISED BID SCHEDULE
NEW WAGE RATES
General Decision Number: IL170020 09/22/2017 IL20
Superseded General Decision Number: IL20160020
State: Illinois
Construction Types: Building Landscape, Heavy Landscape, Highway Landscape and Residential Landscape
Counties: Boone, Cook, De Kalb, Du Page, Grundy, Henry, Kane, Kankakee, Kendall, Lake, McHenry, McLean, Ogle, Peoria, Rock Island, Tazewell, Will, Winnebago and Woodford Counties in Illinois.
LANDSCAPING WORK ON BUILDING, RESIDENTIAL, HEAVY AND HIGHWAY
CONSTRUCTION PROJECTS.
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.
The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/06/2017 1 07/21/2017 2 08/04/2017 3 09/22/2017
ENGI0150-013 06/01/2017
BUILDING AND HIGHWAY CONSTRUCTION (LANDSCAPE WORK): The landscape work for the Landscape Equipment Operator excludes the preparation of sub-grade prior to application of finish landscape materials and the utilization of any equipment over one cubic yard.
BOONE, COOK, DUPAGE, GRUNDY, KANE, KENDALL, LAKE, MCHENRY, AND
WILL COUNTIES
Rates Fringes
Operators:.......................$ 31.10 $6.00+A+B
Includes Angle Dozer, Small; Bobcat and other similar type machines, 1 cu yd or less; Chipping Machine; Combination Backhoe and Front End Loader 1 cu yd or less; Fork Lift Truck;
Hi-Reach and High-Ranger;Hydraulic Boom with Clam;Log Skidder;
Sttraw Blower and Seeder; Stump Machine;Tractors, Crawlers, Rubber Tire Tractors, Highlift Shovels or Front End Loaders 1 cu yd or less; Tree Spades, all; Utility Tractor and attachments, and Rubber Tire Front End loader or similar machine of 1 to 1.5 cu yd solely used for placement of large decorative boulders, trees with balled soil, and other decorative landscape material too large to be accommodated in a 1 cu yd bucket. All other equipment utilized for performing landscape work, tree trimming or removal of stees, and to install plants; transport trees; excavate plant pits; place soil and other landscape materials; and apply finish landscape material on subgrade prepared by others
FOOTNOTE:
A. Health and Welfare contribution is $1,240.00 per month.
B. Paid Holidays: New Year's Day; Memorial Day; Fourth of July; Labor Day; Thanksgiving Day; and Christmas Day provided that all such employees shall have in fact worked their regularly scheduled work day immediately preceding and the regularly scheduled work day immediately succeeding the occurrence of such holiday.
ENGI0150-023 06/01/2017
HIGHWAY CONSTRUCTION (LANDSCAPE WORK): The landscape work for the Landscape Equipment Operator excludes the preparation of sub-grade prior to application of finish landscape materials and the utilization of any equipment over one cubic yard.
HENRY, MCLEAN, OGLE, PEORIA, ROCK ISLAND, TAZEWELL, WINNEBAGO,
and WOODFORD COUNTIES
Operators:.......................$ 31.10 $6.00+A+B Includes the following: Angle Dozer, Small; Bobcat and other similar type machines, 1 cu yd or less; Chipping Machine;
Combination Backhoe and Front End Loader 1 cu yd or less; Fork Lift Truck; Hi-Reach and High-Ranger;Hydraulic Boom with Clam;Log Skidder; Sttraw Blower and Seeder; Stump Machine;Tractors, Crawlers, Rubber Tire Tractors, Highlift Shovels or Front End Loaders 1 cu yd or less; Tree Spades, all; Utility Tractor and attachments, and Rubber Tire Front End loader or similar machine of 1 to 1.5 cu yd solely used for placement of large decorative boulders, trees with balled soil, and other decorative landscape material too large to be accommodated in a 1 cu yd bucket. All other equipment utilized for performing landscape work, tree trimming or removal of stees, and to install plants; transport trees; excavate plant pits; place soil and other landscape materials; and apply finish landscape material on subgrade prepared by others
FOOTNOTE:
A. Health and Welfare contribution is $1,240.00 per month.
B. Paid Holidays: New Year's Day; Memorial Day; Fourth of July; Labor Day; Thanksgiving Day; and Christmas Day provided that all such employees shall have in fact worked their regularly scheduled work day immediately preceding and the regularly scheduled work day immediately succeeding the occurrence of such holiday.
LABO0032-004 05/01/2009
HIGHWAY CONSTRUCTION
WINNEBAGO COUNTY
Rates Fringes
Landscape Laborer................$ 27.66 18.50
LABO0362-003 05/01/2013
HIGHWAY CONSTRUCTION
MCLEAN COUNTY
Rates Fringes
Landscape Laborer................$ 31.08 17.79
LABO0751-004 05/01/2012
HIGHWAY CONSTRUCTION
KANKAKEE COUNTY
Rates Fringes
Landscape Laborer................$ 33.16 20.66
LABO0852-004 05/01/2006
HIGHWAY CONSTRUCTION
ROCK ISLAND AND HENRY COUNTIES
Landscape Laborer................$ 21.94 12.79
LABO0996-004 05/01/2014
HIGHWAY CONSTRUCTION
PEORIA, TAZEWELL, AND WOODFORD COUNTIES
Rates Fringes
Landscape Laborer................$ 31.61 18.76
TEAM0026-005 05/01/2017
MCLEAN (South of a straight line from where Route 24 intersects the Woodford County line in a Southeast direction to the South Southwest corner of Livingston County) COUNTY
TRUCK DRIVER
Group 1.....................$ 36.15 18.30 Group 2.....................$ 36.67 18.30 Group 3.....................$ 36.91 18.30 Group 4.....................$ 37.25 18.30 Group 5.....................$ 38.23 18.30
CLASSIFICATIONS:
GROUP 1: Drivers on 2 axles hauling less than 9 tons; air compressor & welding machines and brooms, including those pulled by separate units; Truck Driver Helper, warehouse employees; Mechanic Helpers; greasers and tiremen; pick-up trucks when hauling material, tools, or workers to and from and on the job site; and forklifts up to 6,000 lb capacity.
GROUP 2: 2 or 3 axles hualing more than 9 tons but hauling less than 16 tons; A-frame winch trucks; hydrolift trucks;
Vactor Trucks or similar equipment when used for transportation purposes; Forklift over 6,000 lb.capacity;
winch trucks; and four axle combiation units.
GROUP 3: 2, 3 or 4 Axles hauling 16 tons or more; 5-Axles or more combination units; drivers on water pulls; articulated dump trucks; mechanics and working forepersons.
GROUP 4: Low Boy and Oil Distributors.
GROUP 5: Drivers who require special protective clothing while employed on hazardous waste work.
* TEAM0179-004 06/01/2017
GRUNDY, KENDALL, MCLEAN (North of a straight line starting at the intersection of McLean-Woodford Counties line & Route 24 in a Southeastern direction to the South Southwest corner of Livingston County), WILL, and WOODFORD (Northeast corner east of Route 51/251 & North of Route 24) COUNTIES
2-3 AXLES...................$ 37.68 0.15+a 4 AXLES.....................$ 37.83 0.15+a 5 AXLES.....................$ 38.03 0.15+a 6 AXLES.....................$ 38.23 0.15+a
FOOTNOTES:
a. $733.20 per week.
b. Lowboy rate based on number of axles
An additional $.20 per axle shall be paid for all vehicles with more than six (6) axles.
CLASSIFICATIONS:
Group 1 - Frame Truck when used for transportation purposes;
Air Compressor and Welding Machines, including those pulled by cars, pick-up trucks and tractors; Ambulances;
Articulated Dumps; Batch Gate Lockers; Batch Hopperman; Car and Truck Washers; Carry Alls; Forl Lifts and Hoisters;
Helpers; Mechanics Helpers and Greasers; Oil Distributors, two-man operation; Pavement Breakers; Pole Trailer, up to 40 feet; Pothole Repair Trucks; Power Mower Tractors; Quick Change Barrier; Self-Propelled Chip Spreader; Shipping and Receiving Clerks and Checkers; Skipman; Slurry Trucks, two-man operation; Slurry Trucks, Conveyor Operated - 2 or 3 man operation; Teamsters; Unskilled Dumpmen; Warehousemen and Dockmen; Truck Drivers hauling warning lights, barricades, and portable toilets on the job site
Group 2 - Dispatcher; Dump Crets and Adgetators under 7 yards; Dumpsters, Track Trucks, Euclids, Hug Bottom Dump Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment under 16 cubic yards; Mixer Trucks under 7 yards; Ready-Mix Plant Hopper Operator; Winch Trucks, 2 Axles
Group 3 - Dump Crets and Adgetators, 7 yards and over;
Dumpsters, Track Trucks, Euclids, Hug Bottom Dump Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment over 16 cubic yards; Explosives and/or Fission Material Trucks; Mixer Trucks 7 yards or over; Mobile Cranes while in transit; Oil Distributors, one-man operation; Pole Trailer, over 40 feet; Pole and Expandable Trailers hauling material over 50 feet long;
Slurry Trucks, one-man operation; Winch Trucks, 3 axles or more; Mechanic - *Truck Welder and *Truck Painter*These classifications shall only apply in areas where and when it has been a past area practice; Asphalt Plant Operators in areas where it has been past practice
Group 4 - Dual-purpose vehicels, such as mounted crane tucks with hoist and accessories; Foreman; Master Mechanic;
Self-loading equipment like P.B. and trucks with scoops on the front
* TEAM0179-008 06/01/2016
KANKAKEE COUNTY
Rates Fringes
TRUCK DRIVER
2 or 3 axles................$ 37.68 0.15+a 4 axles.....................$ 37.83 0.15+a 5 axles.....................$ 38.03 0.15+a 6 axles.....................$ 38.23 0.15+a
FOOTNOTES:
a. $733.20 per week.
b. Lowboy rate based on number of axles
An additional $.20 per axle shall be paid for all vehicles with more than six (6) axles.
CLASSIFICATIONS:
Group 1 - Frame Truck when used for transportation purposes;
Air Compressor and Welding Machines, including those pulled by cars, pick-up trucks and tractors; Ambulances;
Articulated Dumps; Batch Gate Lockers; Batch Hopperman; Car and Truck Washers; Carry Alls; Forl Lifts and Hoisters;
Helpers; Mechanics Helpers and Greasers; Oil Distributors, two-man operation; Pavement Breakers; Pole Trailer, up to 40 feet; Pothole Repair Trucks; Power Mower Tractors; Quick Change Barrier; Self-Propelled Chip Spreader; Shipping and Receiving Clerks and Checkers; Skipman; Slurry Trucks, two-man operation; Slurry Trucks, Conveyor Operated - 2 or 3 man operation; Teamsters; Unskilled Dumpmen; Warehousemen and Dockmen; Truck Drivers hauling warning lights, barricades, and portable toilets on the job site
Group 2 - Dispatcher; Dump Crets and Adgetators under 7 yards; Dumpsters, Track Trucks, Euclids, Hug Bottom Dump Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment under 16 cubic yards; Mixer Trucks under 7 yards; Ready-Mix Plant Hopper Operator; Winch Trucks, 2 Axles
Group 3 - Dump Crets and Adgetators, 7 yards and over;
Dumpsters, Track Trucks, Euclids, Hug Bottom Dump
Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment over 16 cubic yards; Explosives and/or Fission Material Trucks; Mixer Trucks 7 yards or over; Mobile Cranes while in transit; Oil Distributors, one-man operation; Pole Trailer, over 40 feet; Pole and Expandable Trailers hauling material over 50 feet long;
Slurry Trucks, one-man operation; Winch Trucks, 3 axles or more; Mechanic - *Truck Welder and *Truck Painter*These classifications shall only apply in areas where and when it has been a past area practice; Asphalt Plant Operators in areas where it has been past practice
Group 4 - Dual-purpose vehicels, such as mounted crane tucks with hoist and accessories; Foreman; Master Mechanic;
Self-loading equipment like P.B. and trucks with scoops on the front
* TEAM0301-001 06/01/2017
LAKE AND MCHENRY COUNTIES
Rates Fringes
TRUCK DRIVER
2-3 AXLES...................$ 37.69 10.15+a 4 AXLES.....................$ 37.84 10.15+a 5 AXLES.....................$ 38.04 10.15+a 6 AXLES.....................$ 38.24 10.15+a
FOOTNOTES:
a. 325.20 per week.
b. Lowboy rate based on number of axles
An additional $.20 per axle shall be paid for all vehicles with more than six (6) axles.
Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day.
900 straight time hours or more in 1 calendar year for the same employer shall receive 1 week paid vacation; 3 years - 2 weeks paid vacation; 10 years - 3 weeks paid vacation; 20 years - 4 weeks paid vacation.
CLASSIFICATIONS:
Group 1 - Frame Truck when used for transportation purposes;
Air Compressor and Welding Machines, including those pulled by cars, pick-up trucks and tractors; Ambulances;
Articulated Dumps; Batch Gate Lockers; Batch Hopperman; Car and Truck Washers; Carry Alls; Forl Lifts and Hoisters;
Helpers; Mechanics Helpers and Greasers; Oil Distributors, two-man operation; Pavement Breakers; Pole Trailer, up to 40 feet; Pothole Repair…