AMENDMENT_0002_W912P617B0007_CAL_HARBOR_BLDG.pdf

PDF 2 MB Posted

Attached to
CALUMET HARBOR BOAT AND STORAGE BUILDING -AMENDMENT 0001
Solicitation number
W912P617B0007
Issued by

About this file

AMENDMENT NO. 0002 IS CONTAINED IN THIS FILE

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W81G6671658271

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

1. CONTRACT ID CODE PAGE OF PAGES

1 43

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Aug-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P617B0007

X 9B. DATED (SEE ITEM 11)

31-Jul-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Aug-2017

CODE

U.S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

W912P6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

PROJECT TITLE: CALUMET HARBOR AND RIVER STORAGE BUILDING, CHICAGO, IL

A. The government mistakenly added an Indiana Wage Determination under its recently issued Amendment No. 0001 for this Solicitation. In that regard, by this Amendment 0002, the government is hereby incorporating and attaching the correct Wage Determination, which is “IL170009 08/25/2017 IL9.” Note, this is the most current w age determination issued by the Department of Labor.

B. BID DUE DATE: The Bid Opening Date is NOT EXTENDED by this Amendment. Therefore, Contractor’s shall submit Bid packages PRIOR to 2:00pm (Central Time) on August 31, 2017. Detailed instructions regarding the submittal of Bids is provided at Section 00100 of the Solicitation document - SEE "IMPORTANT ACQUISITION NOTES."

-- THIS AMENDMENT CONTINUES ON THE FOLLOWING PAGES

W912P617B0007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

AMENDMENT PARTICULARS

B. Per the above Paragraph A, the correct copy and most current wage rates are hereby incorporated AND enclosed hereunder. In this regard, at SECTION 00010 - SOLICITATION CONTRACT FORM, the following and relevant portion is changed to read as follows:

Wage Rates: General Decision Number: “IL170009 08/25/2017 IL9 is attached”

C. REVISIONS TO THE SOLICITATION SECTION 00010 FOLLOW – A REVISED BID SCHEDULE IS

ENCLOSED HEREUNDER; THEREFORE, BIDDERS SHALL REMOVE THE PREVIOUSLY ISSUED

BIDDING SCHEDULE AND REPLACE IT WITH THE SCHEDULE PROVIDED HEREUNDER.

(1) CLIN 0012:

This CLIN has been renumbered to CLIN 0013.

(2) CLIN 0012 is now a Government Price Allowance for Coordination of Electric Services.

D. AMENDED SECTIONS – PROJECT SPECIFICATIONS:

(1) Section 01 45 00.10, QUALITY CONTROL SYSTEM (QCS) -Section 01 45 00.1, QUALITY CONTROL SYSTEM (QCS) was replaced with Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) per direction of the Contracting Officer's Representative (COR) for the project.

(2) Section 01 11 00, SCOPE OF WORK - Changes were made in conjunction with contractor question numbers 1, 7, 9, 11, 12, 20, 24, 25, 34, and 37.

(3) Section 01 22 00, MEASUREMENT AND PAYMENT - Changes were made in conjunction with contractor question numbers 1, 12, 24, and 37.

(4) Section 01 33 00, SUBMITTAL PROCEDURES - References to Section 01

45 00.1 were changed to Section 01 45 00.15 10.

(5) Section 01 35 26, GOVERNMENT SAFETY REQUIREMENTS - Was replaced with the most recent version.

(6) Section 13 34 19, METAL BUILDING SYSTEM - Warranty language was revised.

E. AMENDED PLAN SHEETS:

Sheets E-101 and E-104 - Changes were made in conjunction with contractor question numbers 2, 3, 4, 5, and 23.

F. USACE RESPONSE TO QUESTIONS: By this Amendment the USACE responds to Contractors Questions, which follows:

QUESTION 1

Specification 26 00 01; 1.3 COORDINATION The contractor is asked to include “all coordination and construction fees” to obtain a new electrical service from

COMED.

Does the GOV’T have a cost from COMED for this, or will the GOV’T provide an allowance to include in the bid for these costs?

Typically, COMED will not provide this information to a bidding contractor, especially with only a 2 week notice.

USACE Response 1 (23-Aug-17): A Cost Reimbursable Line Item for coordination with ComEd costs will be added and have a Government price allowance of a NTE $80,000 price. The following will text about what is involved with the ComEd service coordination effort will be added to paragraph 1.1.1, Project Description, of Specification Section 01 11 00 SOW, Paragraph 1.1.1. “The Contractor shall coordinate with the COR and ComEd for the provision of overhead electrical service 200Amp Main, 480Y/277V 3 Phase 4 Wire to the Storage Facility located at 9169 US-41 for the U.S. Army Corps of Engineers Chicago District. The Contractor shall provide ComEd with (1) a Service Entrance Location (SEL) sketch, (2) a complete plan layout of new electrical service to Storage Facility located at 9169 US-41, (3) Fault Current (fault duty) at customer secondary side of transformer and estimated X/R ratio, and (4) Electrical one-line diagram of utility distribution to Storage Facility located at 9169 US- 41, as noted in the Submittals paragraph Site Electric Services.” The Bid Schedule has been revised to reflect the new CLIN (0012), “Site Electric Service” with a LOT unit with cost reimbursable – NTE $80,000, and Section 01 22 00, Measurement and Payment, has been revised to sync with the revised bid schedule. The original CLIN 0012, Performance and Payment Bonds, is now CLIN 0013. The following text has been added to Section 01 22 00, Measurement and Payment, “This is a Government Price Allowance at the ceiling price of Not to Exceed (NTE) $80,000. Costs may be reimbursed up to this ceiling price as follows: Payment will be made for site electrical utilities for the site development operation costs associated with coordination efforts with the electric company (Commonwealth Edison), which involve providing service to the new building. This effort is fully described in Specification Section 01 11 00, SCOPE OF WORK. The Contractor shall inform the Contracting Officer's Representative (COR) of all planned coordination efforts prior to them being undertaken such that compliance with the ceiling price of this item and the tasks performed, the associated level of effort, and scheduling can be verified.

(1) The Contractor shall NOT incur any additional costs or perform any additional services outside of the ceiling price established hereunder. Should the Contractor determine that the allocated amount is insufficient because additional related services are deemed necessary, the government may negotiate a fair and reasonable price with the contractor to make price adjustments to the Contract. (2) The COR is responsible for processing payments. The contractor shall provide the COR with paid invoices and all other supporting cost information (Labor, travel, per Diem, subcontractor costs, etc.). For the verification of the Contractor's expenditures for this line item. ANY UNUSED BALANCE WILL BE DEOBLIGATED AT THE END OF THE CONTRACT PERIOD. Unit of Measure. LOT. “

QUESTION 2

Specification 26 00 01; 1.3 COORDINATION and Drawing SHEET ID E-104; PANEL SCHEDULES Please provide the available KAIC Available Fault Current from COMED or provide the desired KAIC rating for panels MDP and LP shown on E-104.

USACE Response 2: Provide panels rated for 42KAIC. See revised Sheet E-104.

QUESTION 3

Drawing SHEET ID E-104; RISER DIAGRAM and PANEL SCHEDULES PANELS MDP and LP: The maximum 1 pole breaker spaces in a 200 amp panelboard is 42. Both panel schedules show 60 circuits.

Please confirm 42 circuits is adequate, or if we should provide a sub-panel for MDP spare circuits and a sub-panel for LP spare circuits.

USACE Response 3: Due to possible future load requirements, a 60ckt panel-board is required and 42ckt may be insufficient. Provide 60ckt panel-board. See revised Sheet E-104.

QUESTION 4

Welding outlets are commonly fed from 480 volt, 3 pole, 60 amp rated circuits.

Please confirm the welding station is to be fed from panel LP (208 volt) and provide a frame/trip rating for the feeder breaker.

USACE Response 4: Please provide 480V, 3P, 60A as per contractor recommendation. See revised sheet E-104.

QUESTION 5

PANEL MDP; The panel schedule shows (9) 125 amp frame breakers. This is very unusual for a 200 amp rated panel. If possible, please provide actual desired frame/trip ratings of spare breakers.

Please confirm breakers feeding the HVAC equipment (AHU-1 @ 70 AMPS, ACCU-1 @

30 AMPS).

Please provide breaker trip rating for the water heater.

Please allow normal sizing of breaker frame ratings so that all breakers will physically fit in a single panelboard (unless a sub-panel is desired, per question 3 above).

USACE Response 5 (22-Aug-17): Breakers should be sized based on final selection of equipment. Breaker specifics have been revised on Sheet E-104.

QUESTION 6

Will the Government provide a list of approved manufacturers for the prefabricated building?

USACE Response 6: No

QUESTION 7

The bid documents indicate that the Contractor is responsible for the design of the building structure. To what extent is the Contractor responsible for MEP components as they integrate with the building?

USACE Response 7 (21-Aug-17): The Corps completed the design and remaining work to be done by the contractor is the building integration and commissioning. The contractor is responsible for integrating the provided MEP design into the building structure including ensuring that the structure is designed appropriately to accept all penetrations and loads as well as final building commissioning of the MEP. The Contractor will have to ensure that the security measures are integrated for the building and commissioning of the building (i.e., ensure that all the mechanical and electrical components are fully functional and work together). Specification section 01 11 00 paragraph 1.1.1, states, "The Contractor shall design and construct a 4000 square foot (SF) prefabricated building..."

… "The Contractor is responsible to provide all equipment, piping, wiring, controls, and appurtenances required to complete the Work." … "The contractor shall acquire all applicable water, sewer, and utility permits to ensure fully functional facility." Lastly, specification section 01 11 00 paragraph 1.2, Prefabricated Building Designs states "Design narrative and analysis including code analysis by all disciplines (e.g., civil, structural, electrical, plumbing, security)."

QUESTION 8

Upon review of the solicitation package/bid requirements, I noticed that the documents required include the Representations and Certification and all pricing sheets, bid bond.

Are any other Past performance/employee/subcontractor documents required with the submittal of the bid? Or will this be discussed at the pre-bid meeting?

USACE Response 8 (21-Aug-17): In order for a contract to be awarded, the contracting officer must deem the lowest, responsive bidder, a responsible contractor (re: Part 9 of the FAR). In doing so, the contractor’s past performance record must be concluded as satisfactory. In the bid notes (paragraph 1b), the USACE states: “The Government intends to award all Base Bid Items to the responsive, responsible bidder submitting the lowest aggregate fair and reasonable price for all items in the bid schedule.” Contractors are allowed to contact the Contracting Officer Representative at the Calumet Area Office for a site visit meeting in lieu of a pre-bid meeting.

Question 9

Please provide a size, insulation specifications, booster pump requirements on the Insulated, Domestic Water Supply Tank with Heater.

USACE Response 9 (21-Aug-17): The Contractor is responsible for determining a size, insulation specifications, booster pump requirements on the Insulated, Domestic Water Supply Tank with Heater, etcetera to complete the Work in conjunction with the phase design as specified in specification section 01 11 00 paragraph 1.1.1, "The Contractor shall design and construct a 4000 square foot (SF) prefabricated building..." … "The Contractor is responsible to provide all equipment, piping, wiring, controls, and appurtenances required to complete the Work."

… "The contractor shall acquire all applicable water, sewer, and utility permits to ensure fully functional facility.”

and in specification section 01 11 00 paragraph 1.2, Prefabricated Building Designs states "Design narrative and analysis including code analysis by all disciplines (e.g., civil, structural, electrical, plumbing, security)."

Question 10

Going over the approved manufacturers section of the specs, it calls for the building to be provided by Butler or A&S. We have access to Ceco, Alliance Building Systems, or Kirby (A Nucor company) as well. Would any of those be okay to bid with for the building?

USACE Response 10 (22-Aug-17): Specification Section 13 34 19 METAL BUILDING SYSTEM paragraph 2.1 METAL BUILDING SYSTEM MANUFACTURER allows for “Acceptable metal building system manufacturers include: Butler…or Government-approved technical equivalent.” The three companies listed in the question are acceptable as long as their product meets all the other requirements outlined in the project plans and specifications.

Please note that there is no Alliance Building System company that builds manufactured buildings. There is an Alliance Steel company that does build manufactured buildings and this would be the acceptable company.

Question 11

With regards to the approved manufacturers, A&S has indicated they do not intend to bid. Butler tells me the following:

“There is a provision in the metal building specifications under Warranty that calls for a no dollar limit roof weather tightness warranty. Butler does not have that provision in their warranty. They limit the warranty to $0.80/SF.

Unless that is waived we would not be able to quote this project.”

Please advise?

USACE Response 11 (22-Aug-17): Butler's standard warranty is acceptable. The phrase "no dollar limit" was removed from paragraph 1.8 of Section 13 34 19, Metal Building System.

Question 12

General note #1 on drawing E-101 shows a continuation symbol but I could not locate the pad or pole mounted transformer that we need to run our conduit to for the Com-Ed service drop?

USACE Response 12 (23-Aug-17): These details shall be determined as result of the Contractor's coordination with ComEd.

Received on 8-17

Question 13 There does not appear to be any work related to fire protection (sprinklers, alarms, coatings, etc.) in the scope.

Please confirm.

USACE Response 13: Correct, there will not be any work related to fire protection (sprinklers, alarms, coatings, etc.) in the scope.

Question 14

Note 4 on Sheet C-501 states “The existing concrete foundations and asphalt and gravel pavements at the project site shall be removed and disposed of as an option to this contract…”

Please advise if this cost should be included in a specific Line Item as part of the base bad, or if it will be a change order following award, should the USACE decide to include it.

USACE Response 14: The Corps of Engineers Field Crew will be removing the existing concrete foundations and asphalt/gravel pavement and dispose of all construction waste by 31-Aug-17.

Question 15

Are room finish schedules available for the mechanical room, electrical room, and bathroom inside the storage building?

USACE Response 15: No. Per specification Section 01 11 00 SCOPE OF WORK (SOW) paragraph 1.1.1 the rooms are stud wall construction laid out and designed per the applicable building codes for each rooms intended use. As part of this design the contractor shall choose the appropriate finish for the walls and submit per paragraph

1.2 SUBMITTALS a “Narrative describing… interior wall type… finish colors…”. Also the contractor is required to submit color boards for approval.

Question 16

Drawing P-101 calls for an “above-ground insulated container to house potable water tank and small heater.” What size tank is required for this facility and is there a government required water service pressure at each fixture?

USACE Response 16: Section 01 11 00 paragraph 1.1.1 states “potable water tank has to be sized in accordance with UFC 3-240-01”. Determine fixture capacity in accordance with UFC 3-240-01 and UFC 3-420-01.

Question 17

Will the selected contractor be required to generate specifications for design-build features of the project i.e. doors, interior framing, finishes, painting, etc. that are not included in the current specification?

USACE Response 17: No

Question 18

As a government facility, what level of Anti-Terrorism Force Protection is required for this facility and related site work?

USACE Response 18: In reference to the Contractors Antiterrorism question. If this is in reference to what the facility requires once the USACE begins operating from it, see the SOW. If this is in reference to with what the contractor must comply while operating on the site, nothing is needed.

USACE Response 18 (22-Aug-17): Anti-Terrorism Force Protection (AT-FP) requirements are inherent with the installation of the physical security measures prescribed in Section 01 11 00, paragraph 2.3. No additional AT-FP contract clauses pertain to this contract. In the event, the Site is impacted by a change to the force protection condition, the Contractor will be notified.

Question 19

Will AutoCAD .dwg files be acceptable in place of Microstation .dgn files for the CADD submittals?

USACE Response 19: No. If Contractor prepares in AutoCAD he will need to convert to Microstation and confirm that the design symbology (levels, colors, line weights, line styles, patterns, etc) converted correctly.

Question 20

Spec Section 01 11 00 lists due dates for each design phase (65% at 75 calendar days after NTP, 95% at 125 calendar days after NTP, and Final at 150 calendar days after NTP) but does not list a government review period.

What is the government review period for the each of the required design phases?

USACE Response 20 (21-Aug-17): A 14 calendar day review period for the Government has been added to respective submittal subparagraphs of paragraph 1.2 of Section 01 11 00, SOW.

Question 21 Are there any utility easements or controlled access easements on the property that would limit the contractor from securing and locking the double gate into the property? Access specific to ComEd utility service and NOAA facility.

USACE Response 21: Currently ComEd and NOAA have locks daisy-chained on the gates and the USACE would like those locks to be maintained. The Contractor can add their lock on the gate but the other locks will need to be maintained to ensure other utilities have access.

Question 22

The trench drains in the shop area are not connected to any of the waste piping or waste tank. Please confirm the trenches are not to be connected.

USACE Response 22 (21-Aug-17): The trenches and all other waste fixtures are to be connected to a fully functional waste disposal system as stated in Note 2 on sheet C-105 – “All plumbing (e.g., bathroom fixtures, trench drains, light-duty floor drains, water lines) shall be incorporated into a unified design.”

Question 23

General Note 7 on E-101 asks us to include the cost for internet to be brought in to the site. Please advise who the internet service provider is. Does the USACE already have service at a facility near the proposed building?

USACE Response 23 (21-Aug-17): This note will be deleted since per paragraph 1.1.1 of Section SOW, “The Government shall provide telecommunication capability…” Question 24

General Note 8 on E-101 asks us to include the cost for the electrical service upgrade to be included in the bid.

Determining this cost with ComEd can take months and will be difficult to estimate before the bid due date. Would the USACE consider adding an allowance for this line item?

USACE Response 24: Yes. The Contractor shall make an allowance and the USACE will make it cost reimbursable line item. Refer to the response to question 1.

Question 25

Sheet C101 appears to show the existing site elevations. Where are the final grading and site elevations shown?

USACE Response 25 (21-Aug-17): The Corps of Engineers Field Crew is in the process of demolishing the building and the existing site elevations will change based upon the demolition work. The Government's site preparation work will be completed prior to NTP. A site survey will not be performed by the Government prior to the work. The Contractor is to survey the site and use the existing grade as their base reference while designing level building foundation and is to grade the gravel pavement around the building with a 1% slope proceeding from the base of the foundation slab outward. The access road will have a 1% crown. The following text has been added paragraph 1.1.2 of Section 01 11 00. “The Contractor shall perform site surveys to ensure the building foundation is level and the facility is graded as noted on the Plans.”

Question 26

If there is spoil haul off for this project, who is providing the analytical testing and the required EPA 663 certification form?

USACE Response 26: In Section 01 57 20.01 03 (Environmental Protection for Illinois) of the project specifications, Paragraph 3.5.1, Solid Wastes explains the following:

"Soil material needs to be reused on the Calumet storage building Government property if possible. However, if some excess soil material requires transport off the Government property, this material must be taken to a permitted landfill that will accept the excess soil material for disposal in compliance with Federal, State, and local requirements. The Contractor shall be responsible for the identification and coordination with appropriate landfills and any and all requirements that may be necessary to ensure the excess soil material is disposed of properly at a permitted landfill in accordance with all applicable Federal, State, and local regulations and requirements. Documentation, including manifests, pertaining to solid waste and/or excess soil disposal shall be submitted along with the updates to the Environmental Protection Plan."

Form LPC-663 is for "uncontaminated" soil certification. As indicated by Section 00 31 24.13 (Soil Contamination Report) of the project specifications, it was presumed that none of the soil would qualify as "uncontaminated" soil, so this form would not be applicable. In accordance with the paragraph above, if there is soil that needs to be removed from the site for disposal, the Contractor will need to coordinate with and perform any testing required by the permitted landfill.

Question 27

What is the building finish slab elevation?

USACE Response 27: Per Specification Section 01 11 00 SCOPE OF WORK (SOW) paragraph 1.3.1 b and Note 15 on Sheet C-102 the finish elevation of the slab shall be 4” above the final grade.

Question 28

Is there a building foundation plan available?

USACE Response 28: No. The contactor is required to design the foundation. The nominal dimensions of the foundation can be found on sheet C-105. Also a description of the foundation requirements is in Specification Section 01 11 00 SCOPE OF WORK (SOW) paragraph 1.3.1 b.

Question 29

It appears that there is some water and sewer that will be coming out of the building. Is a site utility plan available?

USACE Response 29: No, the contractor is required to install a fully functional waste disposal system and a fully functional water supply system, both in accordance with the plans and specifications. There are no utilities on site to and from the city to convey in and out proper sewage and supply water.

Question 30

Does this Army Corp job require DOD certification? Or, are state certifications sufficient?

USACE Response 30 (21-Aug-17): The question is not clear. Please clarify the context of the “certification”.

Question 31

Regarding the Insulated, Domestic Water Supply Tank with Heater; what are the insulation requirements, is there back up power for the water heater, what is the source of the water, please verify the size of the tank, it this tank for drinking water along with other potable use?

USACE Response 31 (22-Aug-17): Section 01 11 00, paragraph 1.1.1 states, “Plumbing Systems and potable water tank and appurtenant features in accordance with UFC 3-240-01, Wastewater Collection.” Water heater sizing, backup power and insulation requirements are to be designed by the contractor to be in accordance with UFC 3-240-

01. The water is for potable use, not drinking water. Source of water is being trucked-in on a periodic to as need basis.

Question 32

What are the booster pump requirements to get the toilets to flush?

USACE Response 32 (22-Aug-17): Section 01 11 00, paragraph 1.1.1 states, “Plumbing Systems and potable water tank and appurtenant features in accordance with UFC 3-240-01, Wastewater Collection.” Booster pump requirements are to be designed by the contractor to provide a fully functional system and will be evaluated during the phased-reviews (65%, 95% and 100%) noted in Section 01 11 00, paragraph 1.2, SD-01 Preconstruction Submittals, Prefabricated Building Designs.

Question 33

Is the City of Chicago code to be used instead of the International Building Code ( for example the City of Chicago requires for buildings located next to a river to have roof drains run a separate line to the river)?

USACE Response 32 (22-Aug-17): Per Specification Section 01 11 00 SCOPE OF WORK (SOW) paragraph 1.1.1 “The contractor shall design the building to meet local building codes…”. The project is located in the City of Chicago therefore the City of Chicago building code would be the primary code to use. In the case that something is not covered by the City of Chicago building code then the International Building Code shall be applied. Please note that there are no roof drains in the structure so the requirement for roof drains to run in a separate line to the river is not applicable.

Question 34

What are the site drainage requirements?

USACE Response 34 (21-Aug-17): See Note 16 on Phase sheet C-102, “Gravel pavement around the building shall be graded with a 1% slope proceeding from the base of the foundation slab outward. The access road will have a 1% crown.” The land around the facility will be graded by the Government.

Question 35

Is a triple basin required?

USACE Response 35 (21-Aug-17): No triple basin is required. Per paragraph 2.2 f. of Section 01 11 00, trench drains are to be connected to the waste water system.

Question 36 Are trench drains required?

USACE Response 36 (21-Aug-17): Yes. The trenches and all other waste fixtures are to be connected to a fully functional waste disposal system as stated in Note 2 on sheet C-105 – “All plumbing (e.g., bathroom fixtures, trench drains, light-duty floor drains, water lines) shall be incorporated into a unified design.”

Question 37

Where are the ties in for sewer, electrical, water, gas and data?

USACE Response 37 (21-Aug-17): There are no ties to existing sewer, water, or gas. The Contractor is responsible for coordinating the electric service tie-in with ComEd.

Question 38

Is data part of this work or will this be done under another contract?

USACE Response 38 (21-Aug-17): The question is not clear. Please clarify what “data” is being referred to in the question.

Question 39

Wages: Are prevailing wage rates for Chicago to be used for this project?

USACE Response 39: See Amendment No. 0002, wherein correcting the Wage Rates to General Decision Number: IL170009, dated 08/25/2017, which were attached therein. The prevailing wages for this project are for Cook County, state of IL.

Question 40

Will the project require a building permit from the City of Chicago?

USACE Response: 40 (21-Aug-17): Paragraph 1.9 of Section 01 57 20.01 03 states: “The Contractor shall comply with 40 USC 3312 and cooperate with State and Local officials but shall not be required to pay any amount for any action a State or a political subdivision of a State takes to carry out this statute. If there is written correspondence between the City of Chicago and the Contractor regarding applicable building or construction permits, and/or if any permits are acquired by the Contractor or inspections are conducted by the City of Chicago, the documentation needs to be included in the permit appendix of the environmental protection plan.”

The following are additional questions following the release of USACE RESPONSES to questions posted to FBO on 25 August 2017. These are provided in sequential order.

Question 41

The specification states that the QCM cannot be the SSHO. Can the Site Superintendent also perform either QCM or SSHO duties?

USACE Response 41: Refer to the updated Section 01 35 26, GOVERNMENT SAFETY REQUIREMENTS. The QCM cannot be the SSHO; however, the Site Superintendent can be the SSHO.

Question 42

Can the Government provide a typical foundation / slab sketch for estimating purposes?

USACE Response 42: No Question 43

There appears to be a designated location for spoil generated on this project. Please confirm if any special preparation of the stockpile location needs to made prior to stockpile: permit, visquine barrier, erosion barrier, etc..

USACE Response 43: As specified in Section 01 57 20.01 03, ENVIRONMENTAL PROTECTION FOR ILLINOIS, paragraph 3.2.1, the Contractor shall be responsible for providing erosion and sediment control measures. The type and location of the erosion and sediment control measures shall be identified in the Storm Water Pollution Prevention Plan (SWPPP) of the Environmental Protection Plan as described in Section 01 57 20.01 03, paragraph 1.7.2. See Section 01 57 20.01 03, paragraph 1.7.2 subparagraph f for more information about the SWPPP and consult the Illinois Urban Manual for further guidance on planning principles and best management practices (BMPs).

Question 44

The project site is adjacent to Lake Michigan. Will a safety boat be required?

USACE Response 44: EM 385-1-1, Section K.5, requires that a safety skiff be immediately available for rescues when work activities are taking place over or adjacent to water.

Question 45

The project site is adjacent to Lake Michigan. Will turbidity curtain be required, or silt fence be sufficient?

USACE Response 45: Section 01 57 20.01 03, ENVIRONMENTAL PROTECTION FOR ILLINOIS, paragraph 3.2.1 states how the Contractor shall be responsible for providing erosion and sediment controls measures. A turbidity curtain is not required since no work is to be performed in the water. A silt fence will be sufficient. Refer to the response to question 43 as it pertains to the SWPPP.

Question 46

CCTV System: Specifications do not agree with the drawings. Specifications reference card access but not video or intrusion. Drawings reference video and intrusion, but no card access, yet there is electrified hardware with no way to control them. Please advise.

USACE Response 46: See Sheet G-002 for the symbol used for access control (electro-mechanical door lock/strike (EDL)). Locations for the EDLs are shown on Sheets C-104 and C-

105. CCTV (i.e., video) specifications are located in the following paragraphs of Section 01 11 00, SCOPE OF WORK: 1.2 subparagraph e; 1.3.1 subparagraph j; 2.3; 2.3.2 subparagraphs (b),

(c) and (k); 2.3.3; 2.3.4; 2.3.5.1; 2.3.5.3; 2.3.6; 2.3.6.2; 2.3.6.3; and 2.3.9. Intrusion Detection System (IDS) (i.e., intrusion) specifications are located in the following paragraphs of Section 01 11 00, SCOPE OF WORK: 1.2 subparagraph e; 1.3.1 subparagraph j, 2.3, 2.3.2, 2.3.5.1, and 2.3.5.3.

Question 47

Please provide a structural plan drawing for the storage building.

USACE Response 47: "No structural plan shall be provided. Per Section 01 11 00, SCOPE OF WORK, the contractor shall design the building. See RFI Question 7."

Question 48

We respectfully request a bid extension to address the above concerns.

USACE Response 48: No bid extension will be provided.

Question 49

On page CS503 Detail D1 the fence foundation is close to the Calumet River. Will that require sheet metal pilings to dam the water. If so, is that the preferred method for install the footing.

USACE Response 49: The fence outrigger section shown on Sheet CS503 is conceptual. The Contractor shall field-verify fence-post footing locations (i.e., final placement) with the Contracting Officer’s Representative.

Question 50

Can specifications be provided for the overhead doors?

USACE Response 50: No. The contactor is required to complete the building design per design criteria provided in Section 01 11 00, SCOPE OF WORK, paragraph 1.3.1 subparagraph d and related specification sections.

------------------------------------END OF QUESTIONS AND RESPONSES-----------------------------------------------

G. POINT OF CONTACT: For questions regarding this Amendment, bidders/contractors may contact either Thomas Russell at 312-846-5376 or Regina Blair at 312-846-5371.

H. In accordance with paragraph C above, below is the revised Bid Schedule, Section 00010 - Solicitation Contract Form, that shall be used when bidding this project. In this regard, the bidder shall replace the previously issued Schedule/Form with the following:

REVISED BID SCHEDULE

(AMENDMENT 0002)

00010 – SOLICITATION CONTRACT FORM

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

MOBILIZATION

FFP

Under this CLIN, the contractor is required to perform mobilization activities. The contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.

Payment Provision:

The Government will pay all costs for the mobilization of all of the Contractor's plant and equipment at the unit price for this item. The Contracting Officer or its Representative may require the Contractor to furnish cost data to justify its proposal price for this item if the Contracting Officer deems there's no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment determined by the Contracting Officer of the actual costs, which is not subject to appeal.

MILSTRIP: W81G6671658271

PURCHASE REQUEST NUMBER: W81G6671658271

NET AMT

0002 1 Job

DEMOBILIZATION

FFP

Under this CLIN, the Contractor is required to perform demobilization activities.

The Contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force to the project site.

Payment Provisions:

The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the unit price for this item. The Contracting Officer or its Representative may require the Contractor to furnish cost data to justify its proposal price for this item if the Contracting Officer deems there's no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment determined by the Contracting Officer of the actual costs, which is not subject to appeal.

0003 1 Job

PREFABRICATED BUILDING

FFP

0004 1 Job

ELECTRICAL SERVICE UPGRADE

ELECTRICAL POWER AND LIGHTING

FFP

This is a Parent Line identifying the work that relates directly to its Sub-line Items 0005AA through 0005AB; the Sub-line Items themselves identify the quantities required to perform said work. Therefore, the Contractor shall provide its pricing separately at Sub-items 0005AA through 0005AB.

0005AA 1 Job

INTERIOR POWER AND LIGHTING

0005AB 1 Job

EXTERIOR POWER AND LIGHTING

PLUMBING

FFP

This is a Parent Line identifying the work that relates directly to its Sub-line Items 0006AA through 0006AF; the Sub-line Items themselves identify the quantities separately at Sub-items 0006AA through 0006AF.

0006AA 1 Job

SANITARY PIPING LAYOUT

0006AB 1 Job

INSTALLATION SANITARY PIPING, CONNECTION

INSTALLATION SANITARY PIPING, CONNECTIONS AND FIXTURES

0006AC 1 Job

INSTALLATION WASTE WATER HOLDING TANK

0006AD 1 Job

POTABLE WATER TANK AND PIPING LAYOUT

0006AE 1 Job

INSTALLATION OF POTABLE WATER PIPING

FFP

INSTALLATION OF POTABLE WATER PIPING, CONNECTIONS AND

FIXTURES

0006AF 1 Job

INSTALLATION OF POTABLE HOLDING TANK

INSTALLATION OF POTABLE WATER HOLDING TANK

0007 1 Job

HVAC AND MECHANICAL INSTALLATION

HVAC AND MECHANICAL INSTALLATION AND COORDINATION

SECURITY MEASURES

FFP

This is a Parent Line identifying the work that relates directly to its Sub-line Items 0008AA through 0008AG; the Sub-line Items themselves identify the quantities separately at Sub-items 0008AA through 0008AG.

0008AA 1 Job

ACCESS CONTROL SYSTEM (ACS)

0008AB 1 Job

INTRUSION DETECTION SYSTEM (IDS)

0008AC 1 Job

CLOSED-CIRCUIT TELEVSION (CCTV) SYSTEM

0008AD 3 Each

UPGRADE OF EXISTING EXTERIOR LIGHT POLE

0008AE 11 Each

MULTI-HEAD MOTION DETECTION LIGHTS

0008AF 2 Each

METAL POLES FOR LIGHTING AND CAMERAS

0008AG 22 Each

BOLLARDS

FENCING

FFP

This is a Parent Line identifying the work that relates directly to its Sub-line Items 0009AA through 0009AB; the Sub-line Items themselves identify the quantities separately at Sub-items 0009AA through 0009AB.

0009AA 88 Linear

Foot

MODULAR FENCING (10.5 FEET HIGH)

0009AB 693 Linear

STANDARD FENCING (9 FEET HIGH)

0010 12,205 Square

GRAVEL PAVEMENT

LIGHTNING PROTECTION SYSTEM

FFP

This is a Parent Line identifying the work that relates directly to its Sub-line Items 0011AA through 0011AB; the Sub-line Items themselves identify the quantities separately at Sub-items 0011AA through 0011AB.

0011AA 1 Job

MATERIAL AND INSTALLATION

0011AB 1 Job

UL MASTER LABEL LIGHTNING PROTECTION CER

UL MASTER LABEL LIGHTNING PROTECTION CERTIFICATE

0012 1 Lot

GOVERNMENT PRICE ALLOWANCE

FFP

GOVERNMENT PRICE ALLOWANCE FOR COORDINATION EFFORTS

ASSOCIATED WITH ELECTRIC SERVICES (COMMON WEALTH EDISON –

COMED)

This is a Government Price Allowance at the ceiling price of Not to Exceed (NTE) $80,000.

Costs may be reimbursed up to this ceiling price as follows: Payment will be made for site electrical utilities for the site development operation costs associated with coordination efforts with the electric company (Commonwealth Edison), which involve providing service to the new building. This effort is fully described in Specification Section 01 11 00, SCOPE OF WORK.

The Contractor shall inform the Contracting Officer's Representative (COR) of all planned coordination efforts prior to them being undertaken such that compliance with the ceiling price of this item and the tasks performed, the associated level of effort, and scheduling can be verified.

(1) The Contractor shall NOT incur any additional costs or perform any additional services outside of the ceiling price established hereunder. Should the Contractor determine that the allocated amount is insufficient because additional related services are deemed necessary, the government may negotiate a fair and reasonable price with the contractor to make price adjustments to the Contract.

(2) The COR is responsible for processing payments. The contractor shall provide the COR with paid invoices and all other supporting cost information (Labor, travel, per Diem, subcontractor costs, etc.). For the verification of the Contractor's expenditures for this line item.

ANY UNUSED BALANCE WILL BE DEOBLIGATED AT THE END OF THE

CONTRACT PERIOD

0013 1 Lot

PERFORMANCE AND PAYMENT BONDS

FFP

BONDS FOR LINE ITEMS 0001 THROUGH 0012 (INCLUDES

GOVERNMENT PRICE ALLOWANCE)

The Government will reimburse the Contractor for the actual cost of acceptable bonds, upon receiving evidence of payment (i.e. paid invoice) from the bonding company or agency, not to exceed the total amount of this contract line item. The Government will not pay more than the amount bid for this line item. If the actual bond costs are less than the line item amount, the contract will be modified to adjust the line item accordingly.

Adjustment(s) to the line item will also be made for any revisions associated with contract changes.

TOTAL BID PRICE:

TOTAL OVERALL BID PRICE LINE ITEMS 0001 THROUGH 0013, inclusive of Sub- Items & GOVERNMENT PRICE ALLOWANCE): $________________________

I. Per the above Paragraph B, the CORRECT copy and most current wage rates are incorporated into the Solicitation and are provided as follows:

General Decision Number: IL170009 08/25/2017 IL9

Superseded General Decision Number: IL20160009

State: Illinois

Construction Types: Building, Heavy, Highway and Residential

County: Cook County in Illinois.

BUILDING, RESIDENTIAL, HEAVY, AND HIGHWAY PROJECTS (does not include landscape projects).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.

The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017 1 01/13/2017 2 01/27/2017 3 02/24/2017 4 04/07/2017 5 04/28/2017 6 05/05/2017 7 06/02/2017 8 06/09/2017 9 06/23/2017 10 06/30/2017 11 07/07/2017 12 07/21/2017 13 07/28/2017 14 08/04/2017 15 08/25/2017

ASBE0017-001 06/01/2015

Rates Fringes

ASBESTOS WORKER/INSULATOR

Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems..........$ 48.45 24.35 Fire Stop Technician.............$ 38.76 23.15

HAZARDOUS MATERIAL HANDLER

includes preparation, wetting, stripping removal scrapping, vacuuming, bagging and disposal of all insulation materials, whether they contain asbestos or not, from mechanical systems..........$ 36.34 23.15

BOIL0001-001 05/01/2017

Rates Fringes

BOILERMAKER......................$ 46.18 29.58

BRIL0021-001 06/01/2016

Rates Fringes

BRICKLAYER.......................$ 44.88 26.62

BRIL0021-004 06/01/2017

Rates Fringes

Marble Mason.....................$ 44.63 26.83

BRIL0021-006 06/01/2017

Rates Fringes

TERRAZZO WORKER/SETTER...........$ 44.38 25.14

TILE FINISHER....................$ 38.56 22.10

TILE SETTER......................$ 45.49 24.91

BRIL0021-009 06/01/2017

Rates Fringes

MARBLE FINISHER..................$ 33.95 26.03

BRIL0021-012 06/01/2017

Rates Fringes

Pointer, cleaner and caulker.....$ 45.42 24.06

CARP0555-001 06/01/2017

BUILDING, HEAVY, AND HIGHWAY

Rates Fringes

CARPENTER

Carpenter, Lather, Millwright, Piledriver, and Soft Floor Layer Building...................$ 46.35 31.29 Heavy & Highway............$ 46.35 31.31

CARP0555-002 10/01/2016

RESIDENTIAL CONSTRUCTION

Rates Fringes

CARPENTER........................$ 36.11 30.02

ELEC0009-003 06/04/2017

Rates Fringes

Line Construction Groundman...................$ 39.39 61.37% Lineman and Equipment Operator....................$ 50.50 61.37%

ELEC0134-001 06/05/2017

Rates Fringes

ELECTRICIAN......................$ 47.40 32.21

ELEC0134-003 06/05/2017

Rates Fringes

ELECTRICIAN

ELECTRICAL TECHNICIAN.......$ 43.10 23.95

The work shall consist of the installation, operation, inspection, maintenance, repair and service of radio, television, recording, voice sound vision production and reproduction, telephone and telephone interconnect, facsimile, data appatatus, coaxial, fibre optic and wireless equipment, appliances and systems used for the transmission and reception of signals of any nature, business, domestic, commercial, education, entertainment and residential purposes, including but not limited to communication and telephone, electronic and sound equipment, fibre optic and data communication systems, and the performance of any task directly related to such installation or service whether at new or existing sites, such tasks to include the placing of wire and cable and electrical power conduit or other raceway work within the equipment room and pulling wire and/or cable through conduit and the installation of any incidential conduit.

ELEV0002-001 01/01/2017

Rates Fringes

ELEVATOR MECHANIC................$ 53.18 31.585+a+b

FOOTNOTES:

a) PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; Day after Thanksgiving Day; Veterans' Day and Christmas Day.

b) Employer contributes 8% of regular hourly rate as vacation pay credit for employee with more than 5 years of service, and 6% for employee with less than 5 years service

* ENGI0150-006 06/01/2017

Building and Residential Construction

Rates Fringes

OPERATOR: Power Equipment

GROUP 1....................$ 50.10 36.45

GROUP 2....................$ 48.80 36.45

GROUP 3....................$ 46.25 36.45

GROUP 4....................$ 44.50 36.45

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1: Mechanic; Asphalt Plant*; Asphalt Spreader;

Autograde*; Backhoes with Caisson attachment*:Batch Plant*;

Benoto(Requires two Engineers); Boiler and Throttle Valve;

Caisson Rigs*; Central Redi-Mix Plant*; Combination Backhoe Front Endloader Machine; Compressor and Throttle Valve;

Concrete Breaker (Truck Mounted)*; Concrete Conveyor;

Concrete Conveyor, Truck Mounted; Concrete Paver over 27E

cu. ft.*; Concrete Paver 27E cu ft and Under*; Concrete Placer*; Concrete Placing Boom; Concrete Pump (Truck Mounted); Concrete Tower; Cranes*; Cranes, Hammerhead*;

Cranes, (GCI and similar type Requires two operators only);

Creter Crane; Crusher, Stone, etc; Derricks; Derricks, Traveling*; Formless Curb and Gutter Machine*; Grader, Elevating; Grouting Machines; Highlift Shovels or Front Endloader 2 1/4 yd. and over; Hoists, Elevators, Outside Type Rack and pinion and similar Machines; Hoists, One, Two, and Three Drum; Hoists, Two Tugger One Floor;

Hydraulic Backhoes*; Hydraulic Boom Trucks; Hydraulic Vac (and similar equipment);Locomotives; Motor Patrol*; Pile Drivers amd Skid Rig*; Post Hole Digger; Pre- Stress Machine; Pump Cretes Dual Ram(Requiring frequent Lubrication and Water); Pump Cretes; Squeeze Cretes-Screw

Type Pumps Gypsum Bulker and Pump; Raised and Blind Hole Drill*; Roto Mill Grinder (36" and Over)*; Roto Mill Grinder (Less Than 36")*; Scoops-Tractor Drawn; Slip-Form Paver*; Straddle Buggies; Tournapull; Tractor with Boom, and Side Boom; and Trenching Machines*.

GROUP 2: Bobcat (over 3/4 cu yd); Boilers; Broom, Power Propelled; Bulldozers; Concrete Mixer (Two Bag and over);

Conveyor, Portable; Forklift Trucks; Greaser Engineer;

Highlift Shovels or Front End loaders under 2 1/4 cu yd;

Aotomatic Hoists, Hoists, Inside Elevators; Hoists, Sewer Dragging Machine; Hoists, Tugger Single Drum; Laser Screed;

Rock Drill (Self-Propelled); Rock Drill (Truck Mounted)*;

Rollers; Steam Generators; Tractors; Tractor Drawn Vibratory Roller (Receives an additional $.50 per hour);

Winch Trucks with "A" Frame.

GROUP 3: Air Compressor-Small 250 and Under (1 to 5 not to exceed a total of 300 ft); Air Compressor-Large over 250;

Combination-Small Equipment Operator; Generator- Small 50 kw and under; Generator-Large over 50 kw; Heaters, Mechanical; Hoists, Inside Elevators (Remodeling or Renovatin work); Hydrualic Power Units (Pile Driving, Extracting, and Drilling); Low Boys; Pumps Over 3" (1 To 3 not to exceed a total of 300 ft); Pumps, Well Points;

Welding Machines (2 through 5); Winches, 4 Small Electric Drill Winches; Bobcat (up to and including 3/4 cu yd)

GROUP 4 - Bobcats and/or other Skid Steer Loaders; Brick Forklifts; Oilers

*-Requires Oiler

* ENGI0150-025 06/01/2017

Heavy and Highway Construction

Rates Fringes

OPERATOR: Power Equipment

GROUP 1.....................$ 48.30 36.45

GROUP 2.....................$ 47.75 36.45

GROUP 3.....................$ 45.70 36.45

GROUP 4.....................$ 44.30 36.45

GROUP 5.....................$ 43.10 36.45

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt Plant*; Asphalt Heater and Planer combination; Asphalt Heater Scarfire*, Asphalt…