This document provides details for a federal construction contract solicitation. The U.S. Army Corps of Engineers is seeking a firm-fixed price contract for channel clearing and excavation work along approximately 1.5 miles of channel in Middlesboro, Kentucky. The contractor will clear vegetation, excavate sediment, and dispose of materials at the specified Double Mountain Mining Site in accordance with the provided technical plans and specifications. The NAICS code for this opportunity is 237990 and it is set aside for small businesses below the $39.5 million size standard. The point of contact is Cierra Mendoza and the performance location is in Middlesboro, Kentucky. A mandatory pre-bid site visit will take place on July 27, 2021 to include an on-site safety training.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OF 1419 - Middlesboro Channel Clearing - page 1.pdf | ||
| OF 1419 - Middlesboro Channel Clearing - page 2.pdf | ||
| W912P521B0010 TSpecs Amendment 002.pdf | ||
| Updated Final MiddlesboroWQC_2020-040-1M2 .pdf | ||
| Middlesboro Channel Clearing RTA (Amendment 002) TPlans.pdf | ||
| Updated Final Yellow Creek Stream ConstructionPermit 29757.pdf | ||
| W912P521B0010 A0002 Middlesboro Channel Clearing.pdf | ||
| W912P521B0010 A0001 Middlesboro Channel Clearing.pdf | ||
| W912P521B0010 Middlesboro Channel Clearing.pdf | ||
| Middlesboro Channel Clearing RTA TPlans.pdf | ||
| MidChannelClearing_(RTA)_BidSchedule.xlsx | XLSX spreadsheet |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. W912P521B0010
US Army Corps Of Engineers Nashville District
MIDDLESBORO CHANNEL
CLEARING
Upper Cumberland River Basin Local Protection Project Middlesboro, Bell County, Kentucky
Technical Specifications Certified Final Documents - RTA
June 2021
THIS PAGE INTENTIONALLY LEFT BLANK
FOR DUPLEX PRINTING
Middlesboro Channel Clearing Middlesboro, Cumberland River W912P521B0010 Certified Final Documents - RTA Bell County, Kentucky
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 00 00 GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
01 95 00 FORMS AND ATTACHMENTS
DI VI SI ON 31 - EARTHWORK
31 11 00 CLEARING, GRUBBING, AND DISPOSAL
31 23 00 EXCAVATION AND FILL
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 92 19 SEEDING
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
35 31 19.20 ARTICULATING CONCRETE BLOCK REVETMENTS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
1.2 LOCATION AND ACCESS
1.2.1 Location
1.2.2 Access to Site
1.3 COORDINATION CONFERENCES
1.4 PARTNERING
1.5 REFERENCES
1.6 PROJECT SIGNS
1.6.1 General
1.6.2 Materials
1.6.3 Painting
1.6.4 Erection and Maintenance
1.7 CONTRACTOR'S STAGING AREA
1.8 DAILY CLEANUP AND DISPOSAL
1.9 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.10 EVALUATION OF CONTRACTOR PERFORMANCE
1.11 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.12 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Contractor Responsibilities
3.1.2 Interruptions of Utilities
-- End of Section Table of Contents --
SECTION 01 00 00 Page 1
SECTION 01 00 00 Page 2
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL
This section comprises an explanation of the general contract requirements needed to accomplish the work. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and drawings.
1.2 LOCATION AND ACCESS
1.2.1 Location
Middlesboro Kentucky
1.2.2 Access to Site
As specified in the project drawings.
1.3 COORDINATION CONFERENCES
Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this project. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to this construction. The Corps of Engineers and the Contractor will be represented at each of these meetings. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.
1.4 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Government Design and Construction team and Subject Matter Experts, and the Contractor and Subcontractors will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.5 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
SECTION 01 00 00 Page 3
U.S. ARMY CORPS OF ENGINEERS (USACE)
ECB 2020-1 (2020) USACE Construction Project Signs and Use of the Army Star
EP 310-1-6a (2006) Sign Standards Manual, VOL 1
EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices
1.6 PROJECT SIGNS
1.6.1 General
Furnish and erect, within 15 days after issuance of the Notice to Proceed, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN at the location directed by the Contracting Officer. Letter signs on one side only and conform to EP 310-1-6a (Section 16), EP 310-1-6b , ECB 2020-1 , and to the details and colors shown on the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. Name the project as follows:
MIDDLESBORO CHANNEL CLEARING
1.6.2 Materials
Construct the sign with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material.
Screws shall be commercial quality and of sizes shown.
1.6.3 Painting
Apply one prime coat and two finish coats of exterior oil paint to signs and post before lettering. Apply letters and trim to one side only using one coat of enamel of color, style, and size shown.
1.6.4 Erection and Maintenance
Erect signs at the locations designated by the Contracting Officer. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs throughout the life of the contract. Maintain signs in good condition until completion of the contract. Remove signs from the site upon final acceptance of the contract work.
1.7 CONTRACTOR'S STAGING AREA
The Contractor will be assigned an area within or near the project site for use as a staging area. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner. Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.
1.8 DAILY CLEANUP AND DISPOSAL
Work areas shall be kept reasonably neat on a daily basis. Debris
SECTION 01 00 00 Page 4 resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.
1.9 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.
1.10 EVALUATION OF CONTRACTOR PERFORMANCE
The Contractor's performance will be evaluated in accordance with FAR Part
42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum.
The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section
01 95 00 FORMS AND ATTACHMENTS.
The Contractor's review of the evaluation shall be completed electronically at the CPARS, http://www.cpars.gov . This website also includes guidance and the user's manual.
Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.
1.11 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13 EQUAL OPPORTUNITY FOR VETERANS, FAR Clause 52.222-35 EQUAL OPPORTUNITY FOR VETERANS, FAR Clause 52.222-37 EMPLOYMENT REPORTS ON VETERANS, DFARS
222.13 SPECIAL DISABLED AND VIETNAM ERA VETERANS, and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract.
While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
a. U.S. Department of Labor Veterans employment: www.vets.gov/
b. Federal veteran employment information: www.fedshirevets.gov/index.aspx
c. Veterans’ Employment and Training Service (VETS):
http://www.dol.gov/vets/
d. Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/
SECTION 01 00 00 Page 5
e. U.S. Army Warrior Transition Command Employment Index:
http://www.wct.army.mil/modules/employers/index.html
f. Hiring Our Heroes initiative:
www.uschamberfoundation.org/hiring-our-heroes
g. Guide to Hiring Veterans:
https:://obamawhitehouse.archives.gov/sites/default/files/docs/white_house_business_council
- guide_to_hiring_veterans_0.pdf
1.12 MEASUREMENT AND PAYMENT
No separate payment will be made for the work covered under this section.
The costs thereof shall be included in the item to which the work pertains.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Contractor Responsibilities
a. The Contractor shall be responsible for the availability of utilities for use on the project. The contractor shall supply any other utilities needed at his cost.
b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.
c. The Contractor is responsible for providing drinking water facilities for all personnel associated with this contract.
3.1.2 Interruptions of Utilities
a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.
b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) calendar days prior to date of proposed interruption. The request shall give the following information:
(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)
(2) Size of line and location of shutoff.
(3) Buildings and services affected.
(4) Hours and date of shutoff.
(5) Estimated length of time services will be interrupted.
c. Operation of valves on water mains will be by Government personnel.
Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations
SECTION 01 00 00 Page 6 and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event of emergency.
-- End of Section --
SECTION 01 00 00 Page 7
SECTION 01 00 00 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUBMITTALS
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Scope of Work
1.2.3 Location
1.3 EXISTING WORK
1.4 LOCATION OF UNDERGROUND UTILITIES
1.4.1 Notification Prior to Excavation
1.5 AVAILABILITY AND USE OF UTILITY SERVICES
1.5.1 Contractor Responsibilities
1.5.2 Alterations to Utilities
1.5.3 Interruptions of Utilities
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 LAYOUT OF WORK AND INITIAL SURVEYS
3.1.1 Layout of Work
3.1.2 Pre-Construction Survey
3.2 SEQUENCE OF WORK
3.2.1 General
3.3 CONTRACTOR SURVEYS
3.3.1 Post-Construction Quantity and Final Surveys
3.3.1.1 Quantity Surveys
3.3.1.1.1 Quantity Survey Method for Cubic Yard Items
3.3.1.1.2 Quantity Survey Method for Square Yard Items
3.3.1.2 Post-Construction Surveys
3.3.1.3 Surveys for Progress Payments
3.4 AVAILABILITY AND USE OF UTILITY SERVICES
3.4.1 Contractor Responsibilities
3.4.2 Alterations to Utilities
3.4.3 Interruptions of Utilities
SECTION 01 11 00 Page 1
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Resume and Proof of Professional Land Surveyor's License; G
Pre-Construction Survey; G
Emergency Action Plan for All Utilities; G
Post-Construction Surveys; G
Survey subittal requirements are detailed under paragraph 3.1 FIELD SURVEYS of this specification section
Area Use Plan; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
This section comprises an explanation of the general contract requirements associated with channel excavation along Yellow Creek. The scope of services for the items described is in the bidding schedule. This section is not intended to be all encompassing in the descriptions. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and contract drawings. The Contractor shall bid each type of work under the applicable bid item. Compensation for any item of work described in the contract documents, but not listed in the bid schedule shall be included in the price for the item of work to which it is made subsidiary.
The Contractor is required to commence work within ten (10) days of the issuance of the Notice to Proceed, unless otherwise directed by the Contracting Officer. All work shall be completed as specified, detailed and/or in strict accordance with all terms, conditions, general, specific and technical provisions, contained herein or incorporated by reference.
Incorporation by reference shall include any and all mandatory provisions required by the Federal Acquisition Regulation (FAR) whether it is referenced or not referenced, current at time of award.
1.2.2 Scope of Work
While the scope of work and services is further and extensively outlined
SECTION 01 11 00 Page 3 in the Bid Schedule, a synopsis of the scope of work for the project follows:
Due to excessive siltation and vegetation in Yellow Creek at Middlesboro, KY, approximately 1.5 miles of channel is to be cleared of vegetation and sediment is to be excavated from the channel. Sediment excavated from the channel is to be disposed of at the Double Mountain Mining Site. For the disposal area at the Double Mountain, LLC permit 807-9009 site, all drainage structures including ditches, culverts and ponds must be maintained thoughout course of disposal and restored to their pre-existing or better condition upon completion. This includes all haul roads within the designated work area shown on design sheet C-100. Organic material from clearing and grubbing work is to be hauled to the burn site designated in the plans, burned, and its residuals spread, covered and seeded. Channel Clearing is broken in to a Base Bid Item and an Option Bid Item. Furthermore there are multiple Option Bid Items for additional work to armor segments of the government owned levee, adjacent to the channel, with articulated concrete block revetments systems. Work shall also include, in addition to temporary erosion prevention and sediment control measures at all sites, construction, and deconstruction upon completion, of temporary access ramps on the levee to avoid injury to the levee while traversing for clearing and of temporary stream crossings to access all channel extents for the clearing to be accomplished. Upon completion of work and deconstruction of temporary measures, site shall be restored to condition equivalent or better than its pre-construction condition.
1.2.3 Location
The work is located at the Middlesboro Channel in Middlesboro KY, approximately as indicated. The exact location will be shown by the Contracting Officer and on the Contract Drawings.
1.3 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with requirements for locating and marking underground utilities. Contact local utility locating service a minimum of 14 calendar days prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations within area of work, to include utilities shown in the plan drawings along with any potential utilities not shown and/or not managed or located by the local utility companies, prior to construction and take necessary measures to ensure utilities remain undisturbed throughout construction duration. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to
SECTION 01 11 00 Page 4 be removed, that is indicated or discovered, in locations to be traversed.
Provide utility companies adequate time to coordinate the determination of the elevations of existing utilities. After coordination with local utilities to verify elevations of utilities within the Channel Clearing footprint, submit data to Government for approval prior to commencing excavation and follow additional guidance provided in SECTION 31 23 00 EXCAVATION AND FILL. Service interruptions shall be restored immediately.
Damages to existing utilities shall be repaired at the Contractor's expense and to the satisfaction of the Contracting Officer. Submit for approval an Emergency Action Plan with the contact information for all local emergency authorities and utilities in the event that a utility is damaged.
The Point of Contact for the Water Service Department of Kentucky is Stephen Vaughn (606-248-2306).
The Point of Contact for the Middlesboro Sewer Department is Travis Heck (606-248-4601).
The Point of Contact for Delta Natural Gas Company, Middlesboro is Frankie Gilbert (606-248-1845).
1.4.1 Notification Prior to Excavation
Notify the Contracting Officer at least 14 calendar days prior to starting excavation work.
1.5 AVAILABILITY AND USE OF UTILITY SERVICES
1.5.1 Contractor Responsibilities
a. The Contractor shall be responsible for the availability of utilities for use on the project. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to and paid for by the Contractor. The Contractor shall carefully conserve any utilities furnished without charge.
b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
1.5.2 Alterations to Utilities
a. Where changes and relocations of utility lines are noted to be performed by others, the Contractor shall give the Contracting Officer at least ten (10) days written notice in advance of the time that the change or relocation is required. In the event that, after the expiration of ten (10) days after the receipt of such notice by the Contracting Officer, such utility lines have not been changed or relocated and delay is occasioned to the completion of the work under contract, the Contractor will be entitled to a time extension equal to the period of time lost by the Contractor after the expiration of said ten (10) day period. Any modification to existing or relocated lines required as a result of the Contractor's method of operation shall be made wholly at the Contractor's expense and no additional time will be
SECTION 01 11 00 Page 5 allowed for delays incurred by such modifications.
b. Separate payment will not be made for alterations or relocations of utilities.
1.5.3 Interruptions of Utilities
a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.
b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) calendar days prior to date of proposed interruption. The request shall give the following information:
(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)
(2) Size of line and location of shutoff.
(3) Buildings and services affected.
c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.
d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 LAYOUT OF WORK AND INITIAL SURVEYS
All surveying, including layout of work and quantity surveys, shall be accomplished by a registered land surveyor licensed in the state in which the work is performed. Surveyor shall have no less than 5 years of experience in conducting topographic surveys. Surveyor shall submit Resume and Proof of Professional Land Surveyor's License for Government approval prior to being selected.
Surveys shall be conducted in the presence of the Contracting Officer or an authorized representative unless this requirement is waived by the Contracting Officer. The Contractor shall notify the Contracting Officer not less than five working days in advance of each survey. In the event of unavailability of the Contracting Officer or an authorized representative, the Contractor shall perform the survey and certify to the Contracting Officer that it complies with these specifications. Survey results certified by the registered surveyor shall be provided to the Contracting Officer in the form of raw data and also in legible scaled plots of the data no more than three (3) days after completion. Survey data shall be referenced horizontally to Kentucky State Plane Coordinate System, South Zone, NAD83, using U.S. Survey feet and vertically to NAVD88. Horizontal and Vertical accuracies shall meet or exceed Third Order surveying accuracy standards, GPS data shall be derived at the 95% confidence level, all of which as described in EM 1110-1-1005, "Control and Topographic
SECTION 01 11 00 Page 6
Surveying", dated 1 January, 2007. Yellow Creek channel cross-section surveys shall be performed during lower flow periods when sediment bars to be excavated are generally in the dry. Regarding hydrographic survey data, horizontal data shall be to the nearest foot with an accuracy of 0.5 feet, and elevation data shall be to the nearest tenth of a foot with an accuracy of 0.2 feet. Additional elevations and/or soundings shall be taken if the Contracting Officer deems such to be necessary or advisable.
Upon award of the contract, Nashville District will furnish the government survey data to the Contractor.
3.1.1 Layout of Work
Prior to beginning construction, the surveyor shall locate all benchmarks and control points and establish the baseline provided in the drawings.
From the baseline and benchmarks provided by the Government, the Contractor shall complete the layout of the work and shall be responsible for all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modifications to the contract work. The Contractor shall furnish, at his own expense, such stakes, templates, platforms, equipment, tools and materials, and all labor as may be required in laying out any part of the work. It shall be the responsibility of the Contractor to maintain and preserve all stakes and marks established by the Contracting Officer, if any, until authorized to remove them, and if such marks are destroyed, by the Contractor or through his negligence, prior to their authorized removal, they may be replaced by the Contracting Officer, at his discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor. The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.
3.1.2 Pre-Construction Survey
A preconstruction site survey shall be required of the Contractor prior to commencement of any project work. Pre-construction survey shall include cross sections of Yellow Creek within 10 longitudinal feet of the locations provided in the Contract Drawings and shall be referenced to the provided baseline. Cross section point density shall be adequate to fully capture significant changes within the channel and fully capture, at minimum, the extents previously captured and displayed in the Contract Drawings.
In addition to this, survey shall adequately capture, at a minimum, the perimeter(s) for the following three pay items: Channel Clearing, Grubbing, and Stripping, Burn Site Stripping, and Herbicide Spraying, Mowing, and Vine Treatment which will be paid for by the unit of Square Yard (SY).
Furthermore, a pre-construction site survey shall be used to verify the existing condition of the levee for any area the Contractor will disturb, with the survey extending 25 feet past the areas of disturbance. Survey data acquired for disturbed levee area shall be such to adequately develop a terrain model with a level of accuracy to plot two-foot contours, capturing all significant levee features within the area of disturbance and signficant grade breaks. This requirement is inclusive to all locations where temporary levee ramps are to be placed, levee footprint
SECTION 01 11 00 Page 7 where Articulated Concrete Block systems are to be inplemented, and all other areas the Contractor is to traverse on the levee during the project duration, such as locations for haulage on the levee crest if action is chosen by the Contractor. In addition the Contractor shall also provide the Government a high resolution video recording of an inspection of the levee from the crest, for the full extent of the project, to utilize for further verification of the levee's pre and post construction condition.
A preconstruction survey is required for all the Bid Option Items not included in channel excavation that are measured by the cubic yard (CY) for this project. These items need be surveyed prior to associated Option construction, but not as part of the original pre-construction survey if not practicable.
Pre-Construction survey requirements shall also include any additional requirements relating to environmental concerns as described in Section
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.
3.2 SEQUENCE OF WORK
3.2.1 General
After receipt of Notice to Proceed (NTP), the Contractor shall initiate coordination meetings with the Contracting Officer and representatives.
Submission requirements pertaining to or affecting utilities and initial surveys as covered under this section shall be given to the Government for review and acceptance. The Contractor shall perform all preparatory work associated with the disposal area and channel prior to performing excavation. The Contractor may begin construction on portions of the work for which the Government has reviewed the final submission and has determined satisfactory for purposes of beginning construction. The Contracting Officer will notify the Contractor when the channel clearing work is cleared for construction. Excavation within the channel shall only occur within the acceptable timeframe between June and November, and clearing and grubbing shall only occur between 15 November and 31 March, as established in Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.
3.3 CONTRACTOR SURVEYS
3.3.1 Post-Construction Quantity and Final Surveys
The Government shall conduct a preparatory meeting with the Contractor prior to the commencement of any work requiring quantity surveys to discuss the requirements and conditions relating to quantity surveys. The Contractor shall furnish to the Contracting Officer the electronic data in Mircostation V8i compatible files (DGN) and a comma delimited ASCII file (containing at a minimum the Point Number, Northing, Easting, Elevation, and Point Descriptor) with all submitted files and drawings being at full scale in same datum as the contract drawings (provided in the general notes). Additionally, provide all CAD files to include but not limited to .dtm, .tin, .alg, (raw data point clouds) and .ASCII or .XML file types used to generate the submitted .dgn electronic drawings such as contours, .dtms, plan views, profiles, and cross sections, along with any accompanying field notes (written or electronically collected) to faciliate USACE QA/QC. Terrain model .tin files shall be translated into .XML files using the XML translater function available in AutoCAD or online to facilitate terrain model import on the USACE side. Upon completing surveys, or portions thereof, the Contractor shall not disturb the ground surface until such time that the Contracting Officer has completed Quality Assurance checks
SECTION 01 11 00 Page 8 of the Contractors' survey data. The Contracting Officer shall disapprove any survey information submitted by the Contractor that lacks sufficient data.
3.3.1.1 Quantity Surveys
Quantity surveys as used in this clause mean a topographical survey accomplished by ground methods with the display output recorded and stored in an electronic field book for further calculations in a computer.
3.3.1.1.1 Quantity Survey Method for Cubic Yard Items
Unless otherwise authorized by the Contracting Officer, use the same means of data collection for Quantity and post-constuction surveys as used for pre-construction surveys. For cubic yard (CY) pay items where the Contractor shall capture pre-construction survey cross sections, capture a post-construction cross section within ten (10) longitudinal feet along the alignment in which each pre-construction cross section was taken so that the end area method of volume calculation can be accurately applied.
The cross sections should accurately display the topography of constructed features including, but not limited to: height, width, grades, and slopes of excavation or fill for all areas requiring cubic yard (CY) unit price measurements and payments. The Pre-Construction Survey and the Post-Construction Surveys shall be submitted in Microstation (.dgn) format. Observations shall be recorded at all breaks in slopes with a maximum distance of 25 feet between observations. Cross sections shall be taken at 90-degrees to baseline or the linear constuction item and at sufficient width beyond the limits of work to delineate the work in place.
The Contracting Officer reserves the right to mandate additional cross sections be taken at locations of his or her choosing for quality assurace purposes. For cubic yard (CY) pay items, other than channel excavation, where the Contractor elects to capture a terrain model (.dtm or .tin) depicting pre-constuction conditions, capture a post construction terrain model that accurately displays all post construction topography of constructed features including, but not limited to: height, width, grades, and slopes of excavation or fill and all breaklines necessary for a level of accuracy to plot two-foot contours. Observations shall be recorded at all breaks in slopes with a maximum distance of 25 feet between observations.
3.3.1.1.2 Quantity Survey Method for Square Yard Items
Unless otherwise authorized by the Contracting Officer, use the same means of data collection for Quantity and post-constuction surveys as used for pre-construction surveys. For square yard (SY) pay items, the Contractor shall, to the satisfaction of the Contracting Officer, take boundary shots, defining the areas of the square yard (SY) pay items with a maximum distance between points being 25 feet.
3.3.1.2 Post-Construction Surveys
The Contractor shall use the the cross-section method for depicting the final post construction conditions. Cross sections shall be taken the same as directed for the Pre-Construction Survey and depict the topography of constructed features including, but not limited to: elevation, width, grades, and slopes of all items in this contract. The Contractor shall verify acceptable location of at least one random, additional section between the provided/Pre-Construction sections. These intermediate sections shall be verified and approved by the Contracting Officer and
SECTION 01 11 00 Page 9 shot by the Contractor for quality assurance purposes. Post-Construction Surveys shall be submitted in Microstation (.dgn) format. Section observations shall be recorded at all breaks in slopes with a maximum distance of 25' between observations. At a minimum, the cross sections shall extend ten feet (10') beyond the construction footprint or each item. The annotated cross-sections shall indicate the baseline; the theoretical grades and slope-lines as specified; and the actual grades and slope lines as constructed. The Contractor shall plot cross sections from the survey data to visually depict the grade and sections obtained. The Contractor shall use this survey data to develop the as-built drawings.
In addition to this, survey shall adequately capture, at a minimum, the perimeter(s) for all items paid for by the unit of Square Yard (SY) excluding the following three pay items: Channel Clearing, Grubbing, and Stripping, Burn Site Stripping, and Herbicide Spraying, Mowing, and Vine Treatment which are to be determined as part of the Pre-Construction Survey.
Post-Construction survey shall also verify satisfactory placement to include height, boundaries, and offset from adjacent top of bench slope at the disposal site. Post-Construction survey of the Disposal site shall include full topographic survey of the benches used for disposal adequate for producing a terrain model wiht a level of accuracy to plot two-foot contours to verify satisfactory placement of material. Boundaries of material placement at the disposal site shall be used for quantities of item Disposal Area Seeding, measured by Square Yard (SY).
Post-Construction survey shall also be conducted for the levee according to the same requirements as described for the Pre-Construction Survey, including a high resolution video.
The government will not be responsible for any input into the process of developing Post-Construction surveys. The survey shall be used to verify the quantity of excavation , quantities for items measured by square yard (SY), and other non-channel clearing Option items measured by the Cubic Yard (CY). after all work is complete.
CAD generated cross sections and average end area shall be used to compute the total quantity of material removed from the channel. Final surveys shall be the basis from which any disputes over changes in conditions shall be made. Promptly after completing the survey, the Contractor shall furnish all originals of all field notes and all other records relating to the survey to the Contracting Officer. The Contractor shall retain copies of all such material furnished to the Contracting Officer. The Contracting Officer must agree to any deviations from the template section prior to payment. Progress payments on partially completed work shall not be made without the data required by this paragraph. Determination of such quantities will be made by the Contracting Officer.
3.3.1.3 Surveys for Progress Payments
For periods that progress payments are requested for items measured by the cubic yard or square yard, provide the before construction survey data and after/or during construction survey data that represents the actual work in-place and to be considered for payment along with the theoretical grades and slope lines provided in the drawings. In addition to the survey data, provide plotted cross-sections and profiles indicating the theoretical grades and slope lines as specified by the contract drawings and the actual grades and slope lines as constructed. For cubic yard items, submit quantity computations calculated by the end area method. For
SECTION 01 11 00 Page 10 non-cubic yard items submit applicable, sections, profiles, construction lines, and/or survey boundaries to verify the work in place.
3.4 AVAILABILITY AND USE OF UTILITY SERVICES
3.4.1 Contractor Responsibilities
a. The Contractor shall be responsible for the availability of utilities for use on the project. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to and paid for by the Contractor. The Contractor shall carefully conserve any utilities furnished without charge.
b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
3.4.2 Alterations to Utilities
a. Where changes and relocations of utility lines are noted to be performed by others, the Contractor shall give the Contracting Officer at least ten (10) days written notice in advance of the time that the change or relocation is required. In the event that, after the expiration of ten (10) days after the receipt of such notice by the Contracting Officer, such utility lines have not been changed or relocated and delay is occasioned to the completion of the work under contract, the Contractor will be entitled to a time extension equal to the period of time lost by the Contractor after the expiration of said ten (10) day period. Any modification to existing or relocated lines required as a result of the Contractor's method of operation shall be made wholly at the Contractor's expense and no additional time will be allowed for delays incurred by such modifications.
b. Separate payment will not be made for alterations or relocations of utilities.
3.4.3 Interruptions of Utilities
a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.
b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) days prior to date of proposed interruption. The request shall give the following information:
(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)
(2) Size of line and location of shutoff.
(3) Buildings and services affected.
c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.
SECTION 01 11 00 Page 11
SECTION 01 11 00 Page 12
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
1.1.1 Mobilization and Demobilization
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.2 Performance and Payment Bonds
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.3 Temporary Fencing
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.4 Erosion Control - Channel Excavation
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.5 Erosion Control - Burn Site
1.1.5.1 Payment
1.1.5.2 Unit of Measure
1.1.6 Erosion Control - Disposal Area
1.1.6.1 Payment
1.1.6.2 Unit of Measure
1.1.7 Temporary Levee Access Ramps
1.1.7.1 Payment
1.1.7.2 Unit of Measure
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Channel Clearing, Grubbing, and Stripping
1.2.1.1 Payment
1.2.1.2 Measurement
1.2.1.3 Unit of Measure
1.2.2 Burn Site Stripping
1.2.2.1 Payment
1.2.2.2 Measurement
1.2.2.3 Unit of Measure
1.2.3 Herbicide Spraying, Mowing, and Vine Treatment
1.2.3.1 Payment
1.2.3.2 Measurement
1.2.3.3 Unit of Measure
1.2.4 Unclassified Excavation
1.2.4.1 Payment
1.2.4.2 Measurement
1.2.4.3 Unit of Measure
1.2.5 Riparian Seeding
1.2.5.1 Payment
1.2.5.2 Measurement
1.2.5.3 Unit of Measure
1.2.6 Upland Seeding
SECTION 01 20 00 Page 1
1.2.6.1 Payment
1.2.6.2 Measurement
1.2.6.3 Unit of Measure
1.2.7 Disposal Area Seeding
1.2.7.1 Payment
1.2.7.2 Measurement
1.2.7.3 Unit of Measure
1.2.8 Temporary Stream Crossings
1.2.8.1 Payment
1.2.8.2 Measurement
1.2.8.3 Unit of Measure
1.2.9 Levee Stripping
1.2.9.1 Payment
1.2.9.2 Measurement
1.2.9.3 Unit of Measure
1.2.10 Geotextiles
1.2.10.1 Payment
1.2.10.2 Measurement
1.2.10.3 Unit of Measure
1.2.11 Aggregate Void Filler/Drainage Layer
1.2.11.1 Payment
1.2.11.2 Measurement
1.2.11.3 Unit of Measure
1.2.12 Geogrid
1.2.12.1 Payment
1.2.12.2 Measurement
1.2.12.3 Unit of Measure
1.2.13 Erosion Control Blankets
1.2.13.1 Payment
1.2.13.2 Measurement
1.2.13.3 Unit of Measure
1.2.14 Levee Seeding
1.2.14.1 Payment
1.2.14.2 Measurement
1.2.14.3 Unit of Measure
1.2.15 Articulated Concrete Block Installation
1.2.15.1 Payment
1.2.15.2 Measurement
1.2.15.3 Unit of Measure
1.2.16 4000 psi Concrete
1.2.16.1 Payment
1.2.16.2 Measurement
1.2.16.3 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 20 00 Page 2
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Mobilization and Demobilization
1.1.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Contract Clause 252.236-7004 PAYMENT FOR
MOBILIZATION AND DEMOBILIZATION.
1.1.1.2 Unit of Measure
Unit of measure: job.
1.1.2 Performance and Payment Bonds
1.1.2.1 Payment
Payment will be made for costs associated with performance and payment bonds. In accordance with Contract Clause 52.228-1 BID GUARANTEE and Contract Clause 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION, the premiums for payment and performance bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety. The Contractor is advised that the pay item "Performance & Payment Bonds" is only for the cost of bonds. Other costs should be allocated to the appropriate bid items. Item is reflected in the BIDDING SCHEDULE under both the Base and Option Contracts.
1.1.2.2 Unit of Measure
Unit of measure: job.
SECTION 01 20 00 Page 3
1.1.3 Temporary Fencing
1.1.3.1 Payment
Payment will be made for costs associated with constructing, maintaining and/or moving fencing for work area(s) at channel due to project's vicinity to school and residential areas reflected in the BIDDING SCHEDULE for the Base Contract.
1.1.3.2 Unit of Measure
Unit of measure: job.
1.1.4 Erosion Control - Channel Excavation
1.1.4.1 Payment
Payment will be made for costs associated with construction and maintenance of temporary environmental protection/EPSEC measures and structures at channel clearing work area reflected in the BIDDING SCHEDULE for the Base Contract and Option 1 Contract.
1.1.4.2 Unit of Measure
Unit of measure: job.
1.1.5 Erosion Control - Burn Site
1.1.5.1 Payment
Payment will be made for costs associated with construction and maintenance of temporary environmental protection/EPSEC measures and structures at the designated burn site reflected in the BIDDING SCHEDULE for the Base Contract and Option 1 Contract.
1.1.5.2 Unit of Measure
Unit of measure: job.
1.1.6 Erosion Control - Disposal Area
1.1.6.1 Payment
Payment will be made for costs associated with construction and maintenance of temporary environmental protection/EPSEC measures and structures at the designated disposal area reflected in the BIDDING SCHEDULE for the Base Contract and Option 1 Contract.
1.1.6.2 Unit of Measure
Unit of measure: job.
1.1.7 Temporary Levee Access Ramps
1.1.7.1 Payment
Payment will be made for costs associated with construction, maintenance, and deconstruction of temporary levee access ramps for construction
SECTION 01 20 00 Page 4 vehicles/haulage reflected in the BIDDING SCHEDULE for the Base Contract.
1.1.7.2 Unit of Measure
Unit of measure: job.
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.2.1 Channel Clearing, Grubbing, and Stripping
1.2.1.1 Payment
Payment will be made for clearing, grubbing and stripping satisfactorily performed and properly disposed of in accordance with the contract drawings and specified in Section 31 11 00 CLEARING, AND GRUBBING.
Payment will be made at the contract unit price per square yard. This price shall include consideration for all required equipment, materials and associated work, and disposal of all associated materials. reflected in the BIDDING SCHEDULE under the Base Contract.
1.2.1.2 Measurement
Measurement for payment will be made to the nearest square yard of satisfactorily cleared, grubbed, and stripped area.
1.2.1.3 Unit of Measure
Unit of measure: square yard.
1.2.2 Burn Site Stripping
1.2.2.1 Payment
Payment will be made for stripping of the designated burn site satisfactorily performed and properly disposed of in accordance with Section 31 11 00 CLEARING, AND GRUBBING. Payment will be made at the contract unit price per square yard. This price shall include consideration for all required equipment, materials and associated work, and disposal of all associated materials. Item is reflected in the BIDDING SCHEDULE under the Base Contract.
1.2.2.2 Measurement
Measurement for payment will be made to the nearest square yard of satisfactorily stripped area.
1.2.2.3 Unit of Measure
Unit of measure: square yard.
SECTION 01 20 00 Page 5
1.2.3 Herbicide Spraying, Mowing, and Vine Treatment
1.2.3.1 Payment
Payment will be made for spraying herbicide, mowing, cutting vine, and basal bark treatment for Japanese knotweed and kudzu control. This price shall constitute full compensation for labor, equipment, materials, and performing all operations necessary for controlling Japanese knotweed and kudzu as specified in Section 32 92 19 SEEDING. No payment for "Herbicide Spraying, Mowing, and Vine Treatment " will be made until acceptance by the Contracting Officer or his/her representative. As is requested by the Contractor, progress payments will be made only after approval and verification of completed work by Contracting Officer or his/her representative. Item is reflected in the BIDDING SCHEDULE under the Base Contract.
1.2.3.2 Measurement
Measurement for payment will be made to the nearest square yard of satisfactorily treated knotweed and kudzu areas.
1.2.3.3 Unit of Measure
Unit of measure: square yard.
1.2.4 Unclassified Excavation
1.2.4.1 Payment
Payment will be made for costs associated with excavation of the channel, which includes performing required excavation and other operations incidental thereto and disposition of excess excavated material and unsuitable and frozen materials reflected in the BIDDING SCHEDULE under the Base Contract and Option 1 for channel excavation and under Option 2 through Option 6 for excavation for revetment key in adjacent to levee toe.
1.2.4.2 Measurement
The total quantity of excavated material for which payment will be made will be the calculated quantity based on average end area calculations as determined by Pre-Construction survey and Post-Construction survey. No allowance will be made for overdepth excavation or for the removal of any material outside the required slope lines unless authorized.