Solicitation Amendment W912P520Q0036-0001.pdf
PDF 382 KB Posted
- Solicitation number
- W912P520Q0036
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W38XDD01351640
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
W912P520Q0036-0001 (Amendment).
Project: Wilson Lock, Upper Boom Wall Anchor Brake Assembly.
The purpose of this amendment is to:
1. Post Questions & Answ ers
2. Replace draw ing 64N436R1
3. Update FAR Clause 52.252-3.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Jul-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P520Q0036
X 9B. DATED (SEE ITEM 11)
24-Jun-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Jul-2020
CODE
US ARMY CORPS OF ENGINEERS-CELRN-RC-N
DIRECTORATE OF CONTRACTING
110 9TH AVENUE SOUTH, RM A405
NASHVILLE TN 37203
W912P5 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P520Q0036
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
QUESTIONS & ANSWERS
The attached document has been modified:
Wilson Lock, Upper Boom Wall Anchor Brake Assembly
1. Industry Question: The Solicitation page 3, Section 8.3 calls out 5 CLINS but Pages 6 thru 10 list 7 CLINS.
Government Response: There are 7 CLINs. Section 8.3 should read: “… Contract Line Item Number 0001-0007.”
2. Industry Question: The Eyebolt 64N439-10 dimensions are not available as a standard item. Can a standard eyebolt be offered?
Government Response: Supplied item can be a standard, custom, or modified eyebolt however supplied product must match form, fit, and function of specified part.
3. Industry Question: The Hook Bolt 64N439-20 is not available as a standard item. Can a standard Crosby hook bolt be offered (Crosby Cat, No, 1070174, Catalog page attached) either “as is” or modified by welding then machining eye opening to the 5/8 dimension of the drawing?
Government Response: Yes, this would be acceptable
4. Industry Question: Please approve the following:
Forging steel, ASTM A668 Grade F (probably 4340 steel).
Casting iron for item 64N438-10 to be 60-45-13 ductile iron.
Our preferred iron foundry uses only foam patterns therefore no pattern can be furnished to the customer for 64N438-10.
Government Response: Steel 4340 is acceptable, iron 60-45-13 ductile iron is acceptable, patterns noted
5. Industry Question: Painting (Specification 3.2.9 – We propose epoxy-polyamide paint conforming to SSPC paint 22, color gray, such as Sherwin Williams MIL-D-24441-D Type IV, or equivalent.
Government Response: SSPC Paint 22 is acceptable.
6. Industry Question: Per Specification Paragraph SD-06 Test Reports, non-destructive test reports are called for of all “fabricated welded components.” Since none of the required items are fabricated welded components, it appears that no non-destructive testing is required for completion of this contract.
Government Response: Correct. No weld testing well be required if the contractor’s means and methods do not include welding. The government does however retain the right to review, and if necessary approve/disapprove, any quality control documentation generated throughout the performance of the contract.
7. There is no format specified for the shop drawings required by Specification Paragraph SD-02. It is proposed that the drawings be provided in PDF format. AQs built drawings will be both CAD and PDF.
W912P520Q0036
Government Response: Correct. Shop drawings should be provided in PDF format and As-built drawings should be both CAD and PDF format.
8. Industry Question: Does the fabricator need AISC certification for this?
Government Response: No. AISC certification is not required.
No additional questions will be accepted after this amendment.
The attached document has been modified:
Replace Drawing 64N436R1.
The following have been modified:
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
W912P520Q0036-0001 (Amendment).
Project: Wilson Lock, Upper Boom Wall Anchor Brake Assembly.
The purpose of this amendment is to:
1. Post Questions & Answers
2. Replace drawing 64N436R1
(End of Summary of Changes)