AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of Amendment 02 is to change the date of w hen the Notice to Proceed w ill be issued on or about to 06 May 2020 from 01 May 2020.

Dredging may not begin earlier than 01 August 2020, unless approved by the Contracting Officer.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 13-Jun-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P419B0011

X 9B. DATED (SEE ITEM 11)

06-Jun-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-Jun-2019

CODE

U.S. ARMY ENGINEER DISTRICT, BUFFALO

1776 NIAGARA STREET

BUFFALO NY 14207-3199

W912P4 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P419B0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

0001 The Bid form has been updated with additional line items, some notes have been changed, and additional notes have been added.

0001 A single page from section 01 35 13 has been replaced with changes highlighted.

0001 Additional drawing specifications have been added to the solicitation.

0002 The purpose of Amendment 02 is to change the date of when the Notice to Proceed will be issued on or about to 06 May 2020 from 01 May 2020.

0002 The Dredging may not begin earlier than 01 August 2020, unless approved by the Contracting Officer.

(end of clause)

(End of Summary of Changes)

AMENDMENT NO. 2

W912P419B0011

BUFFALO, NEW YORK

BUFFALO HARBOR

MAINTENANCE DREDGING

UPDATE SPECIFICATIONS-

The following page replaces the original page

13 JUNE 2019

FY19 BUFFALO HARBOR DREDGE AMENDMENT NO. 2

FY19BUFFDREDGE W912P419B0011

b. The Notice to Proceed will be issued on or about 06 May 2020.

c. Dredging may not begin earlier than 01 August 2020, unless approved by the Contracting Officer

d. Environmental Window. Dredging limitations based upon Environmental conditions:

(1) The Buffalo River may be dredged only between 15 June and 30 December.

(2) The Buffalo Ship Canal may be dredged only between 1 July and 30 December.

e. Schedule of Work. Submit a complete schedule of work covering the period of time from the Notice of Award through the specified duration of the contract, including all private and Government work, and the plant intended for each project, to the Contracting Officer within 10 calendar days of receipt of the Notice of Award.

1.2.1 Contract Accruals

In conjunction with the schedule submittal requirements, submit a monthly listing of accruals. Accruals are used to provide projections of the incremental costs not yet paid for, but earned. Submit the accrual submittal one week before the end of each month throughout the contract duration. Provide accrual information for each line item of the Bidding Schedule.

1.3 PROJECT/SITE CONDITIONS

1.3.1 Condition and Use of Project Site

Notify the Contracting Officer at least 5 calendar days prior to bringing any equipment or material to the work site. Accept responsibility for damages that may be suffered due to their operations.

1.3.2 Physical Conditions

The physical conditions shown on the drawings are indicative of those that prevailed at the time of the site investigations and may be different than those at the time of dredging. Report significant variations that would require changes to the plans, specifications,or both, to the Contracting Officer immediately.

1.3.3 Waterways Navigation, Traffic and Notice to Mariners

There is a moderate amount of traffic using the Buffalo River and Ship Canal, consisting of recreational boats, tour cruise boats, tugs, barges, and ships varying in length to a maximum of 620 feet. This also applies to the route from the site of dredging to the confined disposal facility (CDF

4) (through Buffalo Outer Harbor). Become acquainted with all information and regulations pertaining to navigation & vessel traffic within the waterways and coordinate with the U.S. Coast Guard Offices indicated in paragraph entitled "Notifications" of the Section, to assure that a "NOTICE TO MARINERS" is issued prior to work activity at the project site. A copy of the requisite notice form is an attachment to this solicitation. Submit completed form to the address (shown on the form) no less than 2 weeks prior to the start of work activity at the project site. The Government will not undertake to keep the waterways free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions

SECTION 01 35 13 Page 1021 06/13/19 h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight

Amendment_No._02_W912P419B00110002_Buffalo_Dredge
144459 - FY19 Buffalo Dredging -Amendment No. 2 (13 June 2019)