AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is changing specs package, please see changes marked in red. The changes are attached.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Jul-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P418B0017

X 9B. DATED (SEE ITEM 11)

11-Jul-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Jul-2018

CODE

U.S. ARMY ENGINEER DISTRICT, BUFFALO

1776 NIAGARA STREET

BUFFALO NY 14207-3199

W912P4 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P418B0017

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

AMENDMENT No. 1 W9W912P418B0017

SOUTH BREAKWATER REPAIR

BUFFALO HARBOR

BUFFALO, NY

SPECIFICATION PAGES No. 1041

AND 1040, FROM SECTION 01 35 13

ARE REPLACED.

23 JULY 2018

1. Paragraphs 1.2.6.3, 1.2.6.5 b,1.2.6.7: Deleted text in red.

New page shown has text deleted.

2. Paragraphs 1.2.6.6,: Changed horizontal datum to New York State, East Zone

FY18 Buffalo South Breakwater CERTIFIED FINAL - RTA

FY18BUFSOUTH W912P418B0017

modification in accordance with FAR 52.249-10 "Default (Fixed Price Construction)".

1.2.5 Contract Accruals

Submit a monthly listing of accruals. Accruals are used to provide projections of the incremental costs not yet paid for, but earned. Make the accrual submittal one week before the end of each month throughout the contract duration. Provide accrual information for each line item of the Bidding Schedule.

1.2.6 PROJECT/SITE CONDITIONS

1.2.6.1 Condition and Use of Project Site

The drawings indicate elevations and the reference drawings indicate the latest elevations at the project site. Notify the Contracting Officer at least five calendar days, prior to bringing any equipment or material to the work site. Be responsible for damages that may be suffered due to his operations. See FAR 52.236-9 "Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements."

1.2.6.2 Physical Conditions

The physical conditions shown on the drawings are indicative of those that prevailed at the time of the site investigations and may be different than those at the time of construction.

1.2.6.3 Existing Structures, Equipment, Utilities & Improvements

General locations of applicable existing utilities, vegetation, structures, equipment and improvements, based upon latest information available to the Government have been shown on the drawings. However, it is the responsibility of the Contractor to establish the exact horizontal and vertical location and size of all existing utility lines which are located within the required work area. Confer with the owners of the crossings regarding their exact locations and elevations and will be held responsible for any damages done to them by the construction operations. If the Contractor damages any existing utility line, vegetation, structure, equipment or improvement, submit a report immediately to the Contracting Officer. In any event, protect existing utility lines, vegetation, structures, equipment or improvements from damage, and if damaged, perform repairs.

1.2.6.4 Use of Local Roads

Make all arrangements (including approval of routes to be used and permits required) with all local Government officials or owners for use of public and private roads and streets for the operations, and conform to all requirements regarding such use. All costs in connection with the use of local roads, including any repairs, are at no cost to the Government.

1.2.6.5 Plan of Operations

a. Submit an overall plan of operations for all phases of work. Perform work in accordance with an approved plan of operations submitted by the Contractor. Include work schedules in the plan, and notify the Contracting Officer at least 48 hours in advance of changes in work schedules. Include in the plan provisions for the coordination of construction activities

SECTION 01 35 13 Page 1040 06/21/18

FY18 Buffalo South Breakwater CERTIFIED FINAL - RTA

FY18BUFSOUTH W912P418B0017

indicated in the specifications and shown on the contract drawings.

Construction practices for placement quality of materials will follow those marine procedures normally found acceptable by the U.S. Army Corps of Engineers.

(1) Include in the plan of operations, a plan view plot of the existing conditions, as provided by the Government, using the color-shading contours as stated in section 31 32 23 RUBBLEMOUND BREAKWATER REHABILITATION. In areas that are currently above the design elevation, show no color. Grading of these areas is not required.

(2) Clearly indicate in the plan of operations how these areas will be avoided so that no stone fill is placed in those areas.

b. Complete placement of underlayer and armor stone in segments no greater than 50 feet (+/- 5 feet). Shorter segments are acceptable. Clearly indicate the intended segment length in the Plan of Operations. This will not relieve the Contractor from monitoring weather forecasts to schedule work so that unfinished work will not be left exposed to damage due to adverse weather. Repair any work unfinished work, left unprotected, and damaged due to adverse weather.

1.2.6.6 Datums and Control

The vertical plane of reference is the Low Water Datum (L.W.D.) for Lake Erie, which is 569.2 feet above mean sea level at Rimouski, Quebec (International Great Lakes Datum of 1985 (IGLD85). The horizontal datum is the North American Datum of 1983 (NAD83), New York State Plane Coordinate System, West Zone. Horizontal and vertical control to be utilized for work performed by the contractor are shown on the contract drawings.

1.2.6.7 Damage To Work

The responsibility for damage to any part of the permanent work will be as set forth in FAR 52.236-7 "Permits and Responsibilities." However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are not contract unit or lump sum prices applicable to any part of such work an equitable adjustment pursuant to FAR 52.243-4 "Changes" of the contract, will be made as full compensation for the repairs of the part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, repair damage to all work (including temporary construction, utilities, materials, equipment and plant).

1.2.6.8 Restoration

Restore areas within the required work areas which are damaged by the Contractor's operations, in accordance with the requirements of the applicable section of the specifications.

1.2.6.9 Notifications

Within five calendar days of completing the notifications required under this

SECTION 01 35 13 Page 1041 06/21/18 h5cosklm Highlight