AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment:

- change the quantities of the requirement;

- adjust part of Section 01 35 13

- adjust part of Section 31 32 23.01 02

Please see the attachement for details.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Sep-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P417B0007

X 9B. DATED (SEE ITEM 11)

11-Aug-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Sep-2017

CODE

U.S. ARMY ENGINEER DISTRICT, BUFFALO

1776 NIAGARA STREET

BUFFALO NY 14207-3199

W912P4 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

X 1

W912P417B0007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 15-Sep-2017 03:00 PM to 26-Sep-2017 03:00 PM.

The contractor period of performance end date has decreased by 50 days from 354 days to 304 days.

(End of Summary of Changes)

CERTIFIED FINAL - RTA

W912P4-17-B-0007

AMENDMENT NO. 3

WEST ARROWHEAD BREAKWATER REHABILITATION

OSWEGO HARBOR

OSWEGO, NY

UPDATED BID FORM, PLANS,

AND SPECIFICATIONS

18 SEPTEMBER 2017

Item Unit No. Description Unit Price

1 Mobilization and Demobilization JA $

2 Record (As-built) Drawings JA $ (including all surveys and photographs)

3 Breakwater Repair (Sta. 22+75 ~ 24+75) (includes tie-in to existing breakwater at Sta. 24+75 or betweeen 24+75 and 25+50 if Option A is exercised)

a. Armor Stone TN $ $

b. Underlayer Stone TN $ $

c. Bedding Stone TN $ $

4 Tie-in (at south end) See the Notes and section 31 32 23.01 02.

a. Armor Stone TN $ $

b. Underlayer Stone TN $ $

c. Bedding Stone TN $ $

Total Estimated Amount (Items 1 ~ 4) $

OPTION "A"

5 Breakwater Repair (Sta. 24+75 ~ 25+50)

a. Armor Stone TN $ $

b. Underlayer Stone TN $ $

c. Bedding Stone TN $ $

Total Estimated Amount Option "A" (a ~ c) $

Total Estimated Amount (Items 1 ~ 5) $

(cont.)

3,130 -

1,367 -

397 -

SECTION 00 10 00

SOLICITATION, OFFER, AND AWARD (SF1142) AND BIDDING SCHEDULE

Bid will be based upon all work as shown on the contract drawings and in accordance with the Estimated Estimated Quantity Amount

825 -

3,042 -

727 -

10,748 -

95 -

15 -

OPTION "B"

6 Breakwater Repair (Sta. 20+50 ~ 22+75)

a. Armor Stone TN $ $

b. Underlayer Stone TN $ $

c. Bedding Stone TN $ $

Total Estimated Amount Option "B" (a ~ c) $

Total Estimated Amount (Items 1 ~ 6) $

1,862 -

107 -

10,097 -

Note 7: If any options are exercised, they will be executed within 60 days of Contract Award.

Note 1: Bids must be complete as to all the items on the schedule. Failure to complete all items on the bid schedule will render the bid Non-responsive.

Note 2: The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

Note 4: All Options quantities do not include the tie-in. The location for the tie-in will be placed based upon what options are exercised, if any, and what portion of any options are exercised. See section 31 32 23.01 02 .

Note 3: If options are executed, the government reserves the right to limit the quantity of material, up to the estimated of the exercised option item.

Note 5: The length of repair to be exercised for any option will determine the quantities exercised.

EXAMPLE: Option "A" work is from Sta. 24+75 ~ 25+50. If 60% (45 feet) of this work will be completed, then the Government will calculate the quantities required to complete 45 feet of repair, and that quantity of the option will be exercised, which may not be the same percentage (60%) of length exercised.

Note 6: Option "B" may be exercised if the total quantity of stone to perform repairs for the total length (Sta. 24+75-25+50) of Option "A" is exercised.

All notes and references to base bid and option items as shown on the contract drawings are changed to reflect the new stationing shown on the bid form.

The following changes are made to specification section 01 35 13:

The "milestone" table in paragraph 'Commencement' has been changed to the following:

Milestone Maximum Calendar Days After Receipt of Notice to Proceed (or

Start/Completion Date) Commence Work (Submittals, Administration, etc.) 10

Submittals Completed and Accepted 50

Complete Base Bid Work 304

Milestone Additional Calendar Days for Completion (if option is executed)

Complete Option "A" Work (additional days) 12

Complete Option "B" Work (additional days) 26

The following changes are made to specification section 31 32 23.01 02:

1. Paragraph 'Curing Stone' ‐ The first sentence is now "All underlayer and armor stone, dimensioned to final size, must be stockpiled at the quarry at least 15 days prior to delivery to the project site to insure that unloading‐type fractures caused by the release of stored energy concentrations will not take place and that natural moisture has time to escape."?

2. Paragraph 'Temporary Storage' ‐ The first sentence is now "Storage of stone material on the lake bottom, prior to permanent placement, is subject to approval of the Contracting Officer and will include appropriate weight adjustments for losses, which will be at the Contractor's expense."

3. Paragraph 'TIE‐IN LOCATION' has been changed to the following

The location for placing the stone for the tie‐in to the existing breakwater will vary depending upon which options, and percentage of options, are executed.

a. If no options are executed, the northerly and southerly tie‐in's will be placed starting at Sta.

22+75 and 24+75.

b. If only Option "A" is executed, the northerly tie‐in will be placed starting anywhere between Sta. 24+75 and 25+50, based upon actual length executed. The Southerly tie‐in will be placed at Sta. 22+75 EXAMPLE: If 60% of the length of Option "A" will be executed, then the tie‐in will be starting at Sta. 25+20.

h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight

b. If Options "A" and "B" are executed, the northerly tie‐in will be placed at Sta. 25+50, and the southerly tie‐in will be placed between 20+50 and 22+75 based upon actual length executed.

EXAMPLE: If all of Option "A" and 60% of the length of Option "B" will be executed, then the tie‐ in will be starting at Sta. 21+40.