SEE SCHEDULE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide answ ers to questions received and extend the hour and date for receipt of offers. See
Summary of Changes for questions and answ ers. The due date for offers is changed from 27 September 2022, 04:30 PM CDT to 28
September 2022, 01:00 PM CDT. Ensure to sign this amendment and return w ith response.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Sep-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912NW22Q0114
X 9B. DATED (SEE ITEM 11)
19-Sep-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Sep-2022
CODE
ARMY CONTRACTING COMMAND - REDSTONE
CONTRACTING OFFICE
CORPUS CHRISTI ARMY DEPOT
9035 OCEAN DR. BLDG 10, MAIL STOP 18
CORPUS CHRISTI TX 78419-5260
W912NW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912NW22Q0114
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTION AND ANSWER II
W912NW22Q0114 Cooling Tower Rental
Question & Answer Part II
1. Condenser water points. Are there valved flanged locations or do we need to Install them?
ANSWER: The plan is to use the condenser water connection on the existing chiller and pump with hoses. No additional flanges need to be installed.
2. Electrical point. Is there an existing disconnect for to make power connection?
ANSWER: There is power connections available in the mechanical room to connect power to. CCAD will be responsible for connecting the power. Contractor will provide power leads.
3. Make up water connection point.
ANSWER: Make up water can be provided from the mechanical room. Domestic water connections are available in there.
4. 500 Tons is a vague description of your requirements and sets up the possibility of an undersized cooling tower being provided due to Nominal Tonnage being defined as 95F entering temperature to 85F leaving temperature at a wet bulb temperature of 78F. However, your design wet bulb temperature as published by ASHRAE is 81F. Please clarify to all bidders what wet bulb temperature is desired for proper sizing.
ANSWER: Size tower with 80 degree F wet bulb temperature and condenser water flow rate is 1400 GPM.
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 27-Sep-2022 04:30 PM to 28-Sep-2022 01:00 PM.
(End of Summary of Changes)