W912L7-19-B-6001,_Replacement_Flooring_Bldg._2860.pdf

PDF 3 MB Posted

Attached to
Replace Vinyl Tile Flooring
Solicitation number
W912L7-19-B-6001
Issued by

About this file

Solicitation/ Performance Work Statement

View the file

Other files

File Type Posted
Floor_Plan_Guard_House-Disclaimer.pdf PDF
Floor_Plan_VM-ASE-Disclaimer.pdf PDF
wage_determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F7YRRP9221AW01

CONSTRUCTION CONTRACT for Project PYKL192003 Replacement Flooring Bldg. 2860 at the 164th Airlif t Wing, Memphis ANG Base, TN. Work shall be performed in accordance w ith (IAW) the Performance Work Statement (PWS). This project is a total small business set-aside. The North American Industry Classif ication System (NAICS) Code is 238330 and the Small Business Size Standard is: $15,000,000.00 in average annual receipts for the past three years. Construction project magnitude is betw een $25,000.00 and $100,000. Persons intending to submit a bid are strongly encouraged to attend the Pre-Bid Conference and Site Visit. See Section 00100 for location and date.

X

STACY POLLOCK 901-291-7108

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

14-Aug-2019

(RFP)

(IFB)

CALL:

Replacement Flooring Bldg. 2860

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________90 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________06 Sep 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

164TH AW CONTRACTING OFFICE (FA6422)

4593 SWINNEA ROAD

MEMPHIS TN 38118-7101

W912L7

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

11:00 AM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

PYKL192003

8. ADDRESS OFFER TO (If Other Than Item 7)

901-291-7434FAX:TEL: 901-291-7108 TEL: FAX:

W912L719B6001 58

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912L719B6001

Section 00010 - Solicitation Contract Form

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Rubber Tile Flooring

FFP

Replace the existing vinyl tile flooring, within Vehicle Maintenance-Aircraft Equipment (VM-ASE), Building 2860. Furnish and Install Rubber Tile Flooring, VM-ASE Office & Common Areas, Approx. 3,400 Square Feet; per the attached Performance Work Statement (PWS).

FOB: Destination

PURCHASE REQUEST NUMBER: F7YRRP9221AW01

PSC CD: Z1AA

NET AMT

0002 1 Job OPTION Rubber Tile Border

FFP

OPTIONAL: Furnish and Install Rubber Tile Border, VM-ASE Office & Common Areas, Approx. 650 Square Feet; per the attached Performance Work Statement

(PWS).

FOB: Destination

0003 1 Job OPTION Rubber Tile Border

FFP

OPTIONAL: Furnish and Install Rubber Tile Border VM-ASE Office & Common Areas - Approx. 160 Square Feet; per the attached Performance Work Statement

(PWS).

FOB: Destination

0004 1 Job OPTION Ceramic Floor Tile & Cove Base

FFP

OPTIONAL: Furnish and Install Ceramic Floor Tile & Cove Base, Guard House Rm GH1B, Approx. 32 Square Feet; per the attached Performance Work Statement

(PWS).

FOB: Destination

0005 1 Job

CMRA

FFP

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the 164th Airlift Wing, Memphis, Tennessee via a secure data collection site.

FOB: Destination

PSC CD: R699

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 POP 23-SEP-2019 TO

23-DEC-2019

N/A 164 AW/ SRM/CE (F7YRRP)

CAPT MICHAEL TODD CUTLIFF

4593 SWINNEA ROAD

MEMPHIS TN 38118-7101

901-291-7540 FOB: Destination

F7YRRP

0002 POP 23-SEP-2019 TO

23-DEC-2019

N/A (SAME AS PREVIOUS LOCATION)

0003 POP 23-SEP-2019 TO

N/A (SAME AS PREVIOUS LOCATION)

0004 POP 23-SEP-2019 TO

N/A (SAME AS PREVIOUS LOCATION)

0005 POP 23-SEP-2019 TO

N/A (SAME AS PREVIOUS LOCATION)

BID SCHEDULE NOTES

1. All information relating to this IFB, including pertinent changes/amendments and information will be emailed to the vendor email listing

2. Facsimile transmission of bid is not authorized. Electronic submission of bids will be accepted via email.

3. RESERVED

4. RESERVED.

5. A complete bid package must contain the following:

(a) Offer, Standard Form (SF) 1442 front and back signed

(b) Section 00010 Line Items- all items must be priced

(c) Section 00600, Representations and Certifications, completed and return only additional certifications found in this section In addition, the offeror must have entered current and complete data within the past year in Online Representations and Certifications at www.sam.gov.

(d) When completing the “Offeror” portion of the SF 1442 (Blocks 14 – 20), an official having the authority to contractually bind the company must sign the SF 1442 in accordance with FAR 4.102.

One copy of the SF1442 is required to have an original signature.

(e) All amendments to the solicitation must be acknowledged.

(f) Mark the front of the envelope with the following: “BID No. W912L7-19-B-6001”, and the Name and Address of Bidder. See Block 13A of SF 1442 for required number of copies.

6. Joint Venture Requirements - Parties wishing to propose as a joint venture must submit, with the Pro Forma documents, an executed copy of the joint venture agreement. The joint venture agreement shall be executed in accordance with FAR 4.102(d). Each joint venture partner shall submit evidence satisfactory to the Contracting Officer that its Board of Directors has approved its participation in the joint venture or by an instrument of similarly binding character in the case of an unincorporated entity. Offerors are reminded that to obtain an award the awardee, to include a joint venture, must be registered in the System for Award Management (SAM) database. Applicable to set-aside solicitations: Joint Ventures must meet applicable size standards (See FAR Subpart 19.1). Submit with the proposal any size determination for the Joint Venture entity received from the Small Business Administration. A Joint Venture where-in one party is not a small business may be referred to the Small Business Administration ( IAW FAR 19.302 (b)) to determine eligibility. All questions regarding Joint Ventures must be directed to the Small Business Administration (SBA) and not the Contracting Officer.

Section 00100 - Bidding Schedule/Instructions to Bidders

INSTRUCTIONS TO OFFERORS

INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1. SCOPE:

1.1. You are invited to submit a bid in response to our Invitation for Bid (IFB) W912L7-19-B-6001 entitled Replacement Flooring Bldg. 2860, Project Number PYKL192003, at Memphis ANG Base, 4593 Swinnea Rd., Memphis, TN.

1.2. As a result of this solicitation, the Government intends to award a Firm Fixed Price (FFP) contract resulting from this solicitation to the responsible offeror whose bid, conforming to the invitation for bid, will be most advantageous to the Government, considering price and other price-related factors.

1.3. This solicitation is set-aside 100% for Small Businesses.

2. NOTICE OF PRE-BID CONFERENCE AND SITE VISIT:

2.1. A pre-bid conference will be conducted on 22 August 2019 at 09:00 A.M. Central Daylight Time for the purposes of briefing on the bid requirements and answering questions regarding this solicitation. This conference will be held at 164th Civil Engineering, Building 2884 Starlifter Lane located on Memphis ANG Base, Memphis, TN. Interested Contractors are highly encouraged to attend the pre-bid conference. The site visit will be held following the conference.

2.2. Due to security conditions, all offerors must register to attend this conference and site visit. Email the following information for all attendees to Chris Rhyne at the following address:

usaf.tn.164-aw.mbx.msc@mail.mil

Firm Name and Telephone Number Visitor’s Name and Drivers License Number and State of Issue

2.3. This information must be provided in advance, not later than 3 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-bid conference.

This information will be provided to the Base Security Forces who will authorize your entrance to the site.

2.4. Visitors must arrive at the Installation’s Main Gate fourty-five (45) minutes prior to scheduled site visit in order to pick up their passes.. You will be required to present the following information upon arrival: (1) Vehicle Registration, (2) Valid Drivers License, (3) Proof of Insurance for Vehicle, (4) Safety Inspection and Car Rental agreement if applicable. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.

2.5. Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.

2.6. A record of the conference shall be made and furnished to all prospective offerors via email. The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.

3. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS:

3.1. Submit all questions in the format shown below by email to the contracting office at the addresses shown below. Do NOT contact AE or Engineering personnel directly. Doing so will only delay your answer. All questions must come through the Contracting Office.

Subject Line: Reference No. SOLICITATION W912L7-19-B-6001 Email: usaf.tn.164-aw.mbx.msc@mail.mil

PRE-PROPOSAL INQUIRY FORMAT

Date of Offeror Inquiry: _______________ From: ______________________________ Company Name: ________________________________ Address:_____________________________________________________________________________ Phone Number: _____________________________ Fax Number:______________________________ Email address: ________________________________________________________________________ Offeror Inquiry: (Please clearly state your question) (If sent via an attachment word docs are preferred to facilitate posting of answers to the master Q&A document.)

3.2. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or bids, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach offerors before the submission of their bids.

3.3. All questions and requests for information (RFI) must be received NOT LATER THAN 27 August 2019 9:00 PM CDT prior to bid due date. OFFERORS ARE STRONGLY ENCOURAGED TO

SUBMIT QUESTIONS EARLY IN THIS PROCESS.

3.4. Any interpretations made will be in the form of an amendment of the solicitation, drawings, specifications, etc., and will be furnished to all prospective offerors via email.

3.5. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of bids. Explanations or instructions given in a form other than an amendment to the solicitation shall not be binding. Questions (on a non-attribution basis) and answers shall be furnished to all prospective bidders.

4. AMENDMENTS PRIOR TO DATE SET FOR BIDS: The right is reserved, as the interest of the Government may require, to revise or amend the solicitation, specifications and/or drawings, prior to the date set for bids, as necessary. Such changes, if any, will be announced by an amendment or amendments to this Invitation for Bid. All information relating to this IFB, including pertinent changes/amendments and other information applicable prior to the date set for receipt of bid will be emailed.

5. WAGE DETERMINATION:

5.1. Davis Bacon Wage Rates are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation are. General Decision Number TN20190102 Building, dated 01/18/2019.

Applicable wage rates can be found at Applicable wage rates can be found at http://www.wdol.gov/dba.aspx

6. BID PREPARATION EXPENSES AND PRE-CONTRACT COSTS: This IFB does not commit the Government to pay costs incurred in preparation and submission of bids or for other costs incurred prior to award of a formal contract.

7. Submission Instructions:

a. DUE DATE: 6 September 2019 no later than 11:00 p.m., Central Daylight Time

b. Bid may be emailed (usaf.tn.164-aw.mbx.msc@mail.mil );

or submitted by common carrier; (USPS, UPS, FEDEX, DHL, etc.) to the address located in block 7 of SF1442

c. The bid opening will occur at the time and date specified in Block 13 of the SF1442 at 164 AW

Air National Guard Base, Contracting Office, Bldg. 4575, Memphis, TN 38118

8. INFORMATION REGARDING AVAILABILITY OF UTILITY SERVICES: Reference information found at Section 00700 FAR Provision/Clause 52.236-14, Availability and Use of Utility Services consideration when computing its offer.

9. CLAUSES:

9.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

9.2. Clauses and provisions in this document may not appear in consecutive order.

9.3. REMOVAL OF SECTIONS AT TIME OF AWARD: Sections 00100 and 00600 will be physically removed as a result of an award, but will be deemed to be incorporated by reference in that award.

10. DISPOSITION OF UNSUCCESSFUL BIDS:

In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful bids.

The Government will destroy extra copies of unsuccessful bids. No destruction certificate will be provided.

11. OFFERORS QUALIFICATIONS:

To establish its responsibility, the apparent low bidder may be requested by the Government prior to award, to submit a statement regarding his previous experience in performing comparable work, his business and technical organization, financial and bonding resources and plant available to be used in performing the work. This action may be requested to determine if the contractor is responsible.

12. The terms “bid” and “offer”, and “bidder” and “offeror” shall be construed as having the same meaning in this solicitation and resulting contract.

13. All information relating to this IFB, including pertinent changes/amendments and information will be provided via email.

14. For security reasons, all potential offerors, plan rooms and printing companies are required to be registered in the GSA System for Award Management (SAM) database. Firms can register via the SAM internet site at https://www.sam.gov/portal/public/SAM/. Interested bidders are required to submit their representations and certifications at the same site. You will need your DUNS number and MPIN in order to log in to the Online Representations and Certifications Application (ORCA) website. The solicitation and associated information and the plans and specifications will be made available only from the Contracting Officer or Engineers.

15. A complete proposal package must contain the following:

(a) Offer, Standard Form (SF) 1442 front and back signed

(b) Section 00010 Line Items- all items must be priced

(c) Representations and Certifications, completed and return only additional certifications found in this section. In addition, the offeror must have entered current and complete data within the past year in Online Representations and Certifications (ORCA), is http://orca.bpn.gov.

(d) When completing the “Offeror” portion of the SF 1442 (Blocks 14 – 20), an official having the authority to contractually bind the company must sign the SF 1442 in accordance with FAR 4.102.

One copy of the SF1442 is required to have an original signature.

(e) All amendments to the solicitation must be acknowledged.

16. A single award is contemplated. Prospective bidders must bid on all items to be considered for award.

PERFORMANCE WORK STATEMENT

Repair by Replacement Flooring Vehicle Maintenance-Aircraft Support Equipment Building 2860

Project Number PYKL192003

1.0 General:

This is a non-personnel services contract to replace the existing vinyl title flooring, with in Vehicle Maintenance-Aircraft Equipment (VM-ASE), Building 2860 at 164th AW Tennessee Air National Guard Base, Memphis, TN. Approximately 3400 Square Feet of flooring is needing removal and replacement. This includes the common areas, office areas and some storage areas. Areas of the VM-ASE building that are not included are restroom/locker rooms and the garage bay areas. The existing vinyl flooring shall be replaced with Johnsonite rubber tile shown below or equivalent flooring approved by the 164 Civil Engineering Squadron. There are separate Optional Work tasks. The first Optional Work includes the removal and replacement of the estimated 160 square feet of vinyl flooring in the Main Gate Guard House, Building 4593. The second optional work is a rubber tile decorative border of contrasting color along the walls within the offices of Bldg 2860. The third optional work is to use ceramic floor tile and ceramic base cove verse rubber tile in room GH1B, Guard House Toilet. All optional work must be itemized and listed separately in proposals.

The Government will not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers will be accountable solely to the Contractor who, in turn is responsible to the Government

1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform demolition/removal/equipment recovery, installation, and finnish work to install the rubber tile as specified in Solicitation, Contract, Performance Work Statement, Specifications, and Drawings. Performance shall achieve an acceptable quality level of ninety-eight (98) percent Services, as defined in this PWS. The flooring material shall be rated for more than 10 years under normal wear conditions. Rubber title flooring that is easy to install, repair, and clean is the preference. Rolled flooring and vinyl tile is not preferred.

The primary scope of work is the VM-ASE common area, offices and storage rooms as part of the Building Refresh program at the 164 AW base. Approximately 3400 Square Feet is estimated requiring replacement in Bldg 2890. Preferred flooring is Johnsonite rubber tile color “20 Charcoal”, texture “Forged” or equivalent material.

The first optional work is the installation of Johnsonite rubber tile color “38 Pewter,” texture “Forged” along the walls in the office areas within Bldg 2860 to create a decorative border.

The second optional work also includes the removal and replacement of an estimated 160 Square Feet is in the Main Gate Guard House Bldg 4593. Preferred flooring is Johnsonite rubber tile color “20 Charcoal”, texture “Forged” or equivalent material. No decorative border is required in the Guard House, Bldg 4593.

The third optional work is to use ceramic tile in the Guard House Toilet room, GH1B.

Preferred flooring is Crossville ceramic floor tile color grey of standard. No grout lines shall exceed 1/8 inch in width. Finish work includes sealing and installing a matching threshold.

1.2 Background: Existing flooring in VM-ASE Bldg 2860 was installed when the base was originally constructed in 2008. Funding has not been available every 5-7 years to replace aging flooring around base, therefore, the 164 Civil Engineering Squadron is using a new Base Standard of flooring that should hold up under normal wear for more than 10 years before requiring replacement. The Guard House Bldg 4593 is staffed continuously each day, seven days per week. The flooring in Guard House Bldg 4593 is in greater disrepair because it is continually staffed and exposed to more humid conditions.

1.3 The Period of Performance shall be 23 September 2019 – 23 December 2019.

1.4 General Information:

1.4.1 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS).

1.4.2 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).

1.4.3 Recognized Holidays: The following are recognized United States (US) holidays.

The contractor shall not perform services on these days:

1.4.3.1 New Year’s Day: January 1st

1.4.3.2 Martin Luther King, Jr.’s Birthday

1.4.3.3 President’s Day

1.4.3.4 Memorial Day

1.4.3.5 Independence Day: July 4th

1.4.3.6 Labor Day

1.4.3.7 Columbus Day

1.4.3.8 Veteran’s Day: November 11th

1.4.3.9 Thanksgiving Day

1.4.3.10 Christmas Day: December 25th

1.4.4 Place and Performance of Services: The contractor shall provide services between the hours of 7:00 a.m. – 4:15 p.m. on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Maintenance Hangar building 4513 at 164th AW Tennessee Air National Guard Base, Memphis, TN. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.4.4 RESERVED

1.4.4.1 RESERVED

1.4.4.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.4.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance. The Government reserves the right to direct the removal of an employee for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.

1.4.5 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. The contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of

Emergency Services or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by Department of Defense (DoD), Headquarters Department of Army (HQDA) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.4.5.1 RESERVED

1.4.5.1.1 RESERVED

1.4.5.1.2 RESERVED

1.4.5.1.3 RESERVED

1.4.5.1.4 RESERVED

1.4.5.1.5 RESERVED

1.4.5.1.6 RESERVED

1.4.5.2 For contractors that do not require a CAC, but require access to a DoD facility or installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), and applicable installation, facility and area commander installation/facility access, and local security policies and procedures (provided by a government representative).

1.4.5.3 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

1.4.5.4 RESERVED

1.4.5.4.1 RESERVED

1.4.5.4.2 RESERVED

1.4.5.4.3 RESERVED

1.4.5.4.4 RESERVED

1.4.5.4.5 RESERVED

1.4.5.5 RESERVED

1.4.5.6 AT Level 1 Awareness Training (AT): This standard language is for contractor employees with an area of performance within a Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative.

AT level I Awareness Training is available through ADLS by completing the Force Protection CBT. Advanced Distributed Learning Service (ADLS). All contractor employees and associated sub-contractor employees assigned to work on a government site and/or requiring access to a DoD network will be required to register with ADLS at commencement of services in order to complete the necessary training required of them initially and annually for the duration of the contract (i.e., DoD Information Assurance, OPSEC, Protecting Sensitive Information). ADLS website:

https://golearn.csd.disa.mil/kc/rso/login/ADLS_login.asp

1.4.5.7 RESERVED

1.4.5.8 RESERVED

1.4.5.9 iWATCH Training: The contractor and all associated subcontractors with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program. This local developed training shall be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or the KO. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The contractor shall report completion for each contractor employee and subcontractor employee to the COR within 15 calendar days after completion of training.

1.4.5.10 OPSEC Training: In accordance with AFI 10-701, Operations Security, OPSEC PMs/SMO/SMNCOs/Coordinators will provide OPSEC training or training materials to contract employees within 90 days of employees’ initial assignment to the contract and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 -

OPSEC Fundamentals) and refresher training (Protecting Sensitive Information) are both available on the ADLS website.

1.4.5.11 RESERVED

1.4.5.12 RESERVED

1.4.5.13 RESERVED

1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.4.6.1 Key Control. NOTE: All references to keys include key cards. The contractor shall establish and implement methods of ensuring that no keys/key cards issued by the Government are lost or misplaced or are used by unauthorized persons. No keys issued by the Government shall be duplicated. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The contractor shall immediately report any occurrences of lost or duplicated keys/key cards to the

COR.

1.4.6.1.1 In the event keys, other than master keys, are lost or duplicated, the contractor shall, upon direction by the KO, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the Government replaces or re-keys the locks, the Government will deduct the total cost of lock replacement or re-keying from the monthly payment due the contractor. In the event a master key is lost or duplicated, the Government will replace all locks and keys for that system, and will deduct the total cost from the monthly payment due the contractor.

1.4.6.1.2 The contactor shall prohibit the use of the Government issued keys/key cards by any persons other than the contractor’s employees. The contractor shall prohibit the opening of locked areas by contractor employees to permit entrance of persons other than contactor employees engaged in the performance of services in those areas, or personnel authorized entrance by the KO.

1.4.6.2 Lock Combinations: The contractor shall establish and implement methods of ensuring that no lock combinations are revealed to unauthorized persons. The contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations.

1.4.7 RESERVED

1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR Subpart 42.5. The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO.

The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed. The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.

1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at

FAR 22.17.

1.4.12 RESERVED

1.4.13 Data Rights: The Government has unlimited rights to all documents/materials produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.15 RESERVED

2.0 Definitions and Acronyms:

2.1 Definitions:

2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2 Contracting Officer (KO): A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3 Contracting Officer Representative (COR): An employee of the U.S. Government designated by the KO to monitor contractor performance. Such appointment will be in writing and will state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications.

This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 Defective Service: A service output that does not meet the standard of performance associated with the PWS.

2.1.5 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.6 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 Physical Security: Actions that prevent the loss or damage of Government property.

2.1.8 Quality Assurance: The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.

2.1.11 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.2 Acronyms:

AEI Army Enterprise Infostructure AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BI Background Investigation CM Contract Manager CMRA Contractor Manpower Reporting Application COR Contracting Officer Representative DA Department of the Army DD254 Department of Defense Contract Security Classification Specification DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services HQDA Headquarters, Department of the Army HSPD Homeland Security Presidential Directive

IA Information Assurance IS Information System(s) KO Contracting Officer NGB National Guard Bureau OCI Organizational Conflict of Interest PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SSN Social Security Number TE Technical Exhibit USD(I) Under Secretary of Defense for Intelligence

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S):

3.1 Property: NONE

3.2 Materials: NONE

3.3 Equipment: NONE

3.4 Services: NONE

3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

4.2 RESERVED

5.0 Construction Performance Requirements: The contractor shall: perform demolition/disposal, relocate furniture, and installation as specified in Solicitation, Contract, Performance Work Statement, Specifications, and Drawings. Performance shall achieve an acceptable quality level of ninety-eight (98) percent. Work to include but is not limited to:

5.1 Removal, disposal and subsequent replacement of flooring in VM-ASE Building 2860 and Optional Work location Main Gate Guard House Bldg 4593

5.1.1 Relocating furniture within the VM-ASE Bldg 2860. Removal and recovery of existing wall base cove. Any wall base cove that is salvageable shall be given to the Contracting Officer Representative.

5.1.2 Installation of new flooring in V-MASE Bldg 2860 common areas, office areas and storage areas.

5.1.3. OPTIONAL WORK: Install new flooring decorative border in VM-ASE Bldg 2860 offices.

5.1.4. Installation of wall base cove.

5.1.5 Move furniture back into original locations within VM-ASE Bldg 2860

5.1.6 OPTIONAL WORK: Removal, disposal and subsequent replacement of flooring in Main Gate Guard House Bldg 4593. No grout lines shall exceed 1/8 inch in width.

Finish work includes sealing and installing a matching threshold.

5.1.7 Final cleanup of work area.

5.2 Performance Requirements

5.2.1 Training: Familiarization training with the cleaning, maintenance and repair of the new flooring installed. The minimum acceptable training will be 1 hour for at least two government employees.

5.2.2 Closeout documents: The contractor shall provide all manuals, specifications and warranty documents from the materials manufacture The contractor shall provide and additional closeout documentation and contract administration documents described in the Solicitation.

5.2.3 Progress Schedules: Required for all construction projects with a performance period of 30 days or longer. Project Schedules must be approved by the government and mandatory for projects in the aircraft hangar complex.

5.2.3.1 Contractor's proposed schedule (AF Form 3064), prepared by the

Contractor and submitted through the Base Civil Engineer/Facilities Management (BCE/FMO) to the Contracting Officer, must be accomplished within ten (10) days after award. The Progress Schedule shall indicate the order in which the Contractor proposes to perform the work, the date which work will begin, and the date of anticipated completion. The AF Form 3064 must continue through the entire contract period, even if earlier completion is anticipated.

5.2.3.2 The schedule shall begin in the form of a Progress Chart of suitable scale to indicate appropriately the percentage of work scheduled for completion at any time.

5.2.3.3 In the event of differing site conditions, change in specifications, additional work, etc., which would require a time extension in excess of 60 calendar days, a revised schedule is to be prepared. The revised schedule will reflect work completed up to the date of revision, the percentages adjusted accordingly, and performance time extended to the new completion date established by a Modification (MOD) to the contract as a result of the change.

5.2.3.4 The initial and revised schedules will include time for a final inspection and correction of any punch list items, which might be discovered during the final inspection.

5.2.3.5 AF Form 3064, Contract Progress Schedule and AF Form 3065, Contract Progress Report, will be used to satisfy the requirements of FAR 52.236 15, "Schedules for Construction Contracts". The Contractor's proposed progress schedule shall be submitted in a minimum of three copies. After review by the BCE/FMO, and approval by the Contracting officer, distribution will be made as follows:

5.2.3.6 Original copies will be maintained within the Contracting office.

5.2.3.7 Signed copy maintained by the BCE/FMO.

5.2.3.8 Signed copy maintained by the Contractor.

5.2.3.9 Instructions concerning the use of the AF Form 3064, Contract Progress

Schedule, are on the reverse of the form. Additional instructions are as follows:

5.2.3.10 Block 2 will be the actual date that the contract performance period begins as determined by receipt of the Notice to Proceed.

5.2.3.11 Block 3 will be the completion date established by the contract terms.

5.2.3.12 Block 6 will be the date Contractor physically starts work under the contract.

5.2.3.13 Block 7 self explanatory (cannot be completed until work is completed).

5.2.3.14 Column B "Work Elements" must be in sufficient detail to identify all elements of work required to complete the project. Work elements must be limited to those tasks, which indicate progress and which can be readily identified and measured by the Government inspector. These elements of work shall correspond with the elements of work shown on the AF Form 3065, Contract Progress Report. Some contracts will require supplies /services with very long lead times. While this delivery time is included in the construction period, it can have an impact on the performance. Long lead time is relative to available performance period and the critical path of work.

5.2.3.15 Dates entered above columns D through Q will be the ending date for the period covered by each…