Text version
QUESTIONS FOR SOLICITATION – SANITARY SEWER LINE SURVEY – W912L5-16-T-0209
Delaware Air National Guard (DANG) Facility – New Castle, DE
COMMERCIAL QUESITONS AND GENERAL
1. What is the intended timetable from submittal of bids to Notice of Award (NOA); NOA to Notice to Proceed (NTP); NTP to Pre-Construction Meeting; and anticipated/required mobilization date? NOA will be a few days after proposal due date, notice to proceed with then be issued and must start work within 10 days.
2. What is the period of performance (POP) from Notice to Proceed to Contract completion? Unknown at this present time.
3. Does the Contract allow for milestone payments, based on an agreed Schedule of Values or % Complete? NO One final payment upon completion and inspection.
4. Is any available information from previous video surveys or other reports available for review by interested Bidders? NO
5. Is there any available analytical laboratory data from prior sewer cleanings or information that describes how such materials were handled in the past? NO
6. Can DANG Facility please provide a copy of any Discharge Requirements or volume limitations to be met or followed prior to discharging to the NCC Sewer Authority? IN ACORDANCE WITH DNREC AND NEW CASTLE COUNTY REGS.
7. Is there any analytical sewer discharge data available? No
8. Due to the materials of construction and age of the sewer system, jet cleaning may indirectly cause unintentional damage by exposing existing deficiencies to the existing pipe. In such cases, it would be in DANG’s best interest to perform repairs at the time of discovery. Does DANG have an allowance to cover this type of event(s)? Unknown at this present time.
9. How are you intending to evaluate proposals? Will it be by hard bid, with distinct bid items or will it be qualifications and price, or project approach and negiotiated fees? Qualifications and Price
10. How many copies of the proposal are required? 1
11. To what address should the proposal be mailed? Email prosposal only
12. To whose attention should the proposal be addressed? Delaware Air National Guard
SITE CONDITIONS AND SCOPE OF WORK QUESTIONS
1. Is DANG going to provide an electronic copy of the Sanitary Sewer system with markups, so Bidders can do their own take-offs and clearly see some of the notations made by DANG? a pdf
2. Please clarify the DRBA limits and authorities required for discharge location and any notifications will be noted on the map
3. Can DANG provide any Lift Station Drawings, Maintenance Logs, Operational history, analytical data? If available, will be provided to the contractor awarded the job at the precon mtg
4. Will any work be performed in the Munitions area? NO
5. GIS Submittal – Will DANG supply a geo-referenced Base file of the DANG Facility of concern that shows the existing sewer systems (sanitary and storm) in a .DXF or .DWG format, which will be provided to the successful Bidder? Yes
6. What is the acceptable format to be assumed for the GIS file? What Coordinate system does DANG use? Delaware State Plane? ??
7. Base Access – Once an award is made, will badges be issued for the length of the project to streamline the entry process? Yes
8. Active Landing Areas - Please clarify what procedures may be required for potential access to restricted areas, such as; notice time requirements, permitting procedures, etc. None forseen
9. Radio or Cell phone Transmission Restrictions – Please indicate where these restrictions exist other than the Munitions area. NA for the realm of this project
10. Photo Documentation – Are cameras allowed on-site to document any site conditions or other project features? Yes, except around aircraft
11. Clean Up - Does DANG have a list of approved off-site facilities for disposal or a designated area for stockpiling of debris recovered from the sewer cleanings, if required? No onsite stockpiling will be allowed. Contractor to determine where materials can be appropriately disposed of
12. What quantity of waste debris should Bidders assume for bidding purposes? Assume an average amount based on experience
13. Sewer Jet Cleaning Decant Rinseate – Please indicate which manhole will be used to off-load/de-cant liquids from the sewer jet truck. Will be indicated on the map and discussed at the precon meeting
14. As already mentioned, please provide any quantity or quality limitation requirements before discharging to the designated manhole.
15. Work Schedule – Please indicate any long term “NO WORK” dates scheduled during the expected POP for this work. Every other Monday is a down day. Work can be scheduled with coordination. Any federal or state holiday observed during the course of the job
16. Confined Space (CS) Permitting – Please provide DANG procedures for CS Entry. Typically, this type of work requires two manholes to be open at one time to allow the camera and jet cleaning to run simultaneously. For the most part, breaking the plane is not required for investigation. However, please indicate if DANG procedures allow more than one entry at a time? Yes Also, Is there a limit on manholes open at one time, assuming they are adequately guarded? No
17. Line abandonment – Based on the SOW, this is not included in the solicitation. Please confirm. If line abandonment is required, please specify what method is to be priced and diameter(s) and length(s) of pipe need to be abandoned. If noted as abandoned, inspection is not required. Abandonment procedures will be part of the next phase which will also include repairs and improvements based upon the results of the inspection.
18. Are you interested in smoke testing the system and will it be part of this scope of work? Can be submitted as an option
19. Are you interested in doing manhole inspections to the NASSCO MACP standards? There are two levels, level 1, which grabs basic information about the asset. Level 2 is more indepth and also captures all defects and problems and is geared towards determining how to rehabilitate the manhole properly. and 2. Can be submitted as an option
20. Is flow monitoring part of the scope of this project? If so, do you have an estimated amount of meters as well as a montoring period (3 months, 6 months, etc.) NO
21. If flow monitoring is part of the scope is it safe to assume you just want a hydraulic analysis and not a model. Building a model is a bit more involved than just a hydraulic analysis. N/A
22. For the cleaning operations, will we have access to water onsite? No, unless coordinated with Artesian, they own all fire hydrens.
23. Will the water used for cleaning be paid for by the base or by the contractor?
24. Will we be allowed to dewater the cleaning water back into the system without the solids? Yes
25. Is there a facility onffsite used by the base where we can dispose of the solids captured from the cleaning operations? NO
26. Are you interested in CCTV’ing the laterals as part of this project? The laterals were included in the LF calculations
File details come from the government source that posted it. Updated .