Q and A for W912K6-21-Q-0028.docx
DOCX document 12 KB Posted
- Attached to
- Freedom Armory Kitchen Equipment
- Solicitation number
- W912K6-21-Q-0028
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FRC Kitchen layout schedule.pdf | ||
| Solicitation W912K6-21-Q-0028 (2).pdf | ||
| SOW_Freedom RC_Kitchen.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers for W912K6-21-Q-0028
| Q. | SOW in the overview on Beta Sam (1st section below) states installation, but the SOW in the solicitation attachment (2nd section below) states set in place. These are two different things which will affect the pricing submitted. |
| A. | Some items are strictly set in place such as tables. Other items such as the refrigerator and coffee pot need to be installed and not simply “set in place”. They need to have the water lines connected for each; the coffee pot with the copper line. For certain items, they need to be completely unpacked, assembled, and connected - installed. |
| Q. | Do you require the equipment to be consolidated elsewhere for one-time delivery or can the items ship directly to site? |
| A. | All items can be directly shipped to the site (readiness center). |