ADDENDUM__1.pdf
PDF 591 KB Posted
- Attached to
- CLEAN ROOM CONSTRUCTION Federal contract opportunity
- Solicitation number
- W912JA-17-B-0001
About this file
Addendum 1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| REQUEST_FOR_INFORMATIO1.docx | DOCX document | |
| W912JA-17-B-0001-0003_SF30.pdf | ||
| Q&A_1.pdf | ||
| Site_Visit_Roster.pdf | ||
| Pre-Bid_Conference.ppt | PPT presentation | |
| W912JA-17-B-0001-0003.pdf | ||
| W912JA-17-B-0001-0002.pdf | ||
| W912JA-17-B-0001.pdf | ||
| W912JA-17-B-0001-0001.pdf | ||
| FAKZ_162004_-_100__SPECS.pdf | ||
| FAKZ_162004_-_100__DRAWINGS.pdf | ||
| W912JA-17-B-0001-0001_SF30.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date: 10 July 2017
To: MSgt. Shanks
Subject: ADDENDUM NO. 1
Project: NEW CLEAN ROOM IN THE FUEL CELL & CORROSION
CONTROL FACILITY
Job #: SSL# 06003.02
ANG# FAKZ 162004
From: Jake Johnson
The plans and Specifications of the subject project, dated 14 April 2017 are amended as follows: (Where there are conflicts between the plans and specifications and the addendum, this addendum shall govern)
Item No. 1: Refer to drawings. Delete drawing sheet A2.1 “First Floor Plan, Elevations, Details” and replace it with the drawing titled A2.1 “First
Floor Plan, Elevations, Details” with a revised date of 10 July 2017.
Item No. 2: Contractor to relocate existing and add new fire suppression system sprinkler heads and piping as required in order to meet all applicable
NFPA 13 and UFC 3-600-01, Change 1, November 2016 requirements.
Contractor is responsible for coordinating new fire suppression systems with all HVAC, plumbing, electrical and structural systems. Refer to sheet
A2.1 for existing head locations. Existing sprinkler heads are Reliable model F1FR, recessed, ½”, K=5.6.
End of Addendum