A.07.23_Solicitation.pdf

PDF 639 KB Posted

Attached to
Maintain/Repair/Construct IDIQ Federal contract opportunity
Solicitation number
W912HV-17-R-0004
Issued by
Department of the Army Corps of Engineers Engineering District Alaska

About this file

Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Maintain/Repair/Construct IDIQ, newest first.
File Type Posted
Am-0001.pdf PDF
QandA's.pdf PDF
A.07.24_Solicitation_Amendment.pdf PDF
Evaluation_Orders.pdf PDF
Exhibit.xls XLS spreadsheet
ENG_4288-R.xlsx XLSX spreadsheet
Specifications.pdf PDF
Sketches.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 00 10 00 Contract Line Item Number (CLIN) Schedule

Section 00 21 00 Instructions

Section 00 22 16 Supplementary Instructions to Proposers

Section 00 45 00 Representations and Certif ications

Section 00 70 00 Conditions of the Contract

Section 00 73 00 Supplementary Conditions

Division 01-32 Specif ications, Sketches, ENG 4288-R Submittal Register, Exhibits, and Evaluation Orders are bound separately.

CHRISTOPHER E TAYLOR 046-252-0994

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

17-Apr-2017

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______ calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________4 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________01 Jun 2017 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______ calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CONTRACTING DIVISION

USACE-JAPAN DISTRICT

RM 147, BLDG. 250

CAMP ZAMA

ZAMA-CITY, KANAGAWA 252-8511

JAPAN

W912HV

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: 046-252-0994 TEL: FAX:

W912HV-17-R-0004 64

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued)

(Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912HV-17-R-0004

Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule

Solicitation Information Description: The United States Army Corps of Engineers, District of Japan has a requirement to provide construction services to the Kanto Plain (Camp Zama, Sagamihara Family Housing Area, Sagami General Depot, Yokohama North Dock and Akasaka Press Center) area on an Indefinite Delivery, Indefinite Quantity contracting vehicle.

Point of Contact:

Christopher Taylor, Contract Specialist christopher.taylor@usace.army.mil

Requests for Information are due no later than May 11, 2017 see Section 00 21 00 for more details.

Requests for Information shall reference W912HV-17-R-0004.

NO TELEPHONE CALLS WILL BE ACCEPTED.

Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule

CONTRACT MINIMUM/MAXIMUM VALUE

(a) In accordance with the requirements of FAR 52.216-22 (Section 00 70 00), the maximum contract value of work that will be ordered through the issuance of task orders under this contract shall be

¥6,000,143,100 for the life of the contract. The Government obligates itself to order not less than

¥3,500,000 in services and not more than ¥3,551,105,100 for the base of the contract. Each option year

(if exercised) the Government obligates itself to order not less than ¥3,500,000 in services and not more than ¥1,224,519,000.

(b) The government will obligate the minimum guarantee at the time of awarding the basic contract, by issuing the evaluation orders the value of which is equal to or greater than the minimum guarantee.

(c) If the Government orders work in excess of the minimum but not up to the maximum amount as established for the life of the contract, this circumstance shall not constitute the basis for an equitable adjustment in price.

STATUTORY COST LIMITATION

Project(s) to be ordered through issuance of task order under this contract may be subject to Statutory Cost Limitations. Refer to DFARS 252.236-7006, Cost Limitation, in Section 00 73 00.

Note: * Dollar amounts specified in this solicitation and the resultant contract will be calculated based on respective fiscal years’ Foreign Currency Fluctuation Defense (FCFD) budget rate and converted to Yen equivalent amount. For example, month ended 09/30/2016 FCFD budget rate for O&M (DOD) FY 2016 Budget Rate is Y121.8300. A formal FCFD budget rate will be notified to the contractor upon receipt of the official announcement.

mailto:christopher.taylor@usace.army.mil

Section 00 21 00 - Instructions

INSTRUCTIONS

1. DELIVERY OF BIDS/OFFERS

a. Each bidder/offeror is solely responsible for ensuring that their bid/offer is received by the Government as specified in the solicitation. Please read the following statements to ensure timely submittal of your bid/offer:

(1) Closely coordinate the delivery of your bid/offer in sufficient time before the bid opening date/proposal due date.

(2) Bids/offers will not be accepted at the main gate of Government facilities.

(3) Bids must be mailed to

Attention: Christopher Taylor

Contracting Division USACE-Japan District

RM 147, BLDG. 250

Camp Zama Zama-City, Kanagawa 252-8511 Japan

2. SOLICITATIONS FOR LOCAL SOURCES ONLY. This contract will be performed in its entirety in the country of Japan and is intended only for local sources. (See Federal Acquisition Regulation 5.202(a)(12) and Paragraph titled, ”Offeror Eligibility”.) (JED APR 2006)

3. SUBMISSIONS OF OFFERS IN JAPANESE YEN. Offers submitted in response to this solicitation shall be in terms of Japanese Yen, including any required bid guarantee. Offers received in other than Japanese Yen shall be rejected.

4. REQUEST FOR EXPLANATION OR INTEPRETATION. Request for explanation or interpretation of the solicitation, drawings, specifications, etc., must be submitted to the Government point of contact by

5. SIGNATURE ON OFFERS. Offers must be signed by an officer of the company or an individual who is authorized to sign offers for and on behalf of the company. An individual, other than an officer of the company, who signs an offer must submit evidence of his authority to sign such offer. This evidence must accompany the offer. Failure to comply with this requirement may be cause for rejection of the offer.

6. JOINT VENTURE. In the event the offeror is a joint venture, the offer must be signed by an authorized representative of each participant in the joint venture. Failure to comply with this requirement may be cause for rejection of the offer.

7. OFFEROR ELIGIBILITY. Only local sources will be considered under this solicitation. Local sources are sources (e.g. corporations, partnerships, or Joint Ventures [For a Joint Venture, the Joint Venture as an independent entity must satisfy the local source requirements or, in the alternative, each member of the Joint Venture must individually satisfy the local source requirements] that are physically located in Japan and authorized (i.e. licensed and registered) to perform in Japan, the type of construction work specific in this solicitation. Specifically, a prospective offeror must be duly authorized to operate and conduct business in Japan and must fully comply with all laws, decrees, labor standards, and regulations of Japan during the performance of the resulting contracts. In addition, prior to award of the contracts, offerors must be registered with the Government of Japan to do construction work in Japan and possess necessary construction licenses and permits to perform work required under this solicitation. The U.S.

Government will not offer “United States Official Contractor” status under Article XIV of the US-Japan Status of Forces Agreement (SOFA) to U.S. contractors normally resident in the United States; nor will the U.S. Government certify employees of such contractors as “Members of the Civilian Component” under Article I(b) of the SOFA.

8. DEFINITION OF THE WORDS ITEM/ITEMS.

a. This solicitation contains a base period schedule and 2 option period schedules for award to a single offeror.

b. For the purpose of this solicitation, the words "ITEM" and "ITEMS" as used in provision(s) of this section shall be construed to mean "SCHEDULE" and "SCHEDULES", respectively.

9. METHOD OF PROCUREMENT. The US Army Corps of Engineers, Japan District, intends to solicit this requirement using the source selection procedures in accordance with the provisions set forth in this Request For Proposal (RFP). Single Indefinite Delivery Indefinite Quantity (IDIQ) contract will be awarded to the offerors who submits a proposal determined to be the lowest priced, technically acceptable proposal by the Government (see Section 00 22 16).

10. PRE-AWARD SURVEYS. The Government reserves the right to conduct a preaward survey of any firm under consideration to confirm any part of the information furnished by the offeror, or to require other evidence of managerial, financial, technical, and other capabilities, the positive establishment of which is determined by the Government to be necessary for the successful performance of the contract.

11. Bidder Inquiry

Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in

ProjNet at (https://www.projnet.org) No Later Than (NLT) May 11, 2017. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective vendor once the reply is available for viewing. All timely questions and approved answers will be made available through ProjNet. Approved answers to all timely questions will also be posted in an amendment to the solicitation in the form of a report generated from ProjNet as soon as the comment/question entering period is over and all answers are finalized. In the event of a conflict between the bidder inquiry responses and the solicitation, the solicitation shall govern.

The Bidder Inquiry Key is: X3REPA-J9T28H

The Solicitation Number is : W912HV-17-R-0004

Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret

Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be provided any type of password. You will utilize your

Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

12. PRE-PROPOSAL CONFERENCE.

a. Offerors are strongly urged and expected to attend and participate in the pre-proposal conference.

The purpose of this conference is to promote uniform interpretation of the solicitation documents and work requirements and can include discussions of any problems with interpretations of the solicitation documents and work execution identified by potential offerors through written questions. In no event will a failure to attend the pre-proposal conference constitute grounds for a claim after award of the contract.

b. Offerors are encouraged to ask questions at the conference. Any questions made at the conference may or may not be addressed at the conference, but will be addressed in the minutes of the conference.

c. This pre-proposal conference and site visit will be conducted at 1300 hours on 27 April 2017. The site visit will start at the front of Bldg 645, then move to Bldg. 951. To coordinate for base access, contact Roger Riddick (Roger.K.Riddick.civ@usace.army.mil) at 046-407-4374, Lorna Alvarado (Lorna.Y.Alvarado.civ@usace.army.mil) at 046-407-8061, or Janae Ball (Janae.C.Ball.civ@usace.army.mil) at 046-407-5159.

13. ORGANIZATIONAL CONFLICTS OF INTEREST

In order to prevent a potential conflict of interest under FAR subpart 9.5, firms that prepared or assisted in preparing a statement of work, specifications, or plans for this project in any capacity (to include as a prime contractor, partner, subcontractor, or consultant) under any prior contract shall not be a bidder/offeror under this solicitation and shall not be a part of the bidder's/offeror's team in any capacity

(to include as a prime contractor, partner, subcontractor, or consultant). Failure to comply with this provision may result in termination for default.

SUPPLEMENTARY CONDITIONS

1. PAYMENT BOND NOT REQUIRED. Notwithstanding the requirement for the payment bond, as stipulated elsewhere in this contract, the payment bond requirement has been waived by the contracting officer.

2. WORKERS COMPENSATION INSURANCE (DEFENSE BASE ACT).

a. This paragraph supplements FAR Clause 52.228-3 Workers' Compensation Insurance (Defense Base Act).

b. The U.S. Army Corps of Engineers (USACE) has a blanket waiver for Japan waiving Defense

Base Act (DBA) Insurance coverage. However, this waiver does not apply to any employee who is hired in the U.S., is a resident of the U.S., or is a citizen of the U.S.

c. Contractors shall procure DBA insurance coverage commercially from a DOL authorized insurance carrier unless the contractor is under a self insurance program. The DOL table of authorized carriers and self-insured employers is available at http://www.dol.gov/owcp/dlhwc/lscarrier.htm.

3. EVIDENCE OF PROCUREMENT. The Contractor is required to submit within sixty (60) calendar days after receipt of Notice to Proceed, such positive evidence of procurement actions as may reasonably be required to satisfy the Contracting Officer that procurement is being prosecuted with such diligence as will insure completion of the work within the time specified. The required evidence of procurement actions may include, but is not limited to, a purchase order accepted and confirmed by the source of supply showing delivery date(s) and point(s) of delivery, supported by a firm, irrevocable letter of credit or other guarantee of payment acceptable to the supplier.

4. GROUND-FAULT CIRCUIT INTERRUPTERS. Ground-fault circuit interrupters for all 120-volt single phase 15- and 20-ampere receptacle outlets which are not part of the permanent wiring of the building or structure shall be provided by the Contractor in accordance with Section 11.D.05 of Engineer Manual 385-1-1.

5. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. This paragraph specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)".

In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project.

The delay must be beyond the control and without the fault or negligence of the contractor.

b. The listing below defines the monthly anticipated adverse weather days for the contract period and is based upon 20th Weather Squadron (MAC), U.S. Air Force; Iwakuni U.S. Marine Corps Air Station, Weather Service; Sasebo Naval Pacific Meteorology & Oceanography Detachment; JASDF (Japan Air http://www.dol.gov/owcp/dlhwc/lscarrier.htm

Self Defense Force), or similar data for the geographic location of the project. (More specific information may be obtained as specified under Special Contract Requirements Clause entitled "Physical Data.")

MONTHLY ANTICIPATED ADVERSE WEATHER DELAYS

WORK DAYS BASED ON (5) DAY WORK WEEK

(Misawa-Area) (Kanto Plain) (Iwakuni) (Okinawa) (Sasebo)

JAN 8 1 2 5 7

FEB 9 3 4 7 6

MAR 6 6 7 8 7

APR 3 6 6 6 7

MAY 4 4 6 6 6

JUN 5 9 8 6 12

JUL 6 6 6 6 9

AUG 6 6 5 9 9

SEP 6 7 6 7 9

OCT 4 5 4 4 8

NOV 6 4 4 4 5

DEC 7 1 3 5 5

The above schedule of anticipated adverse weather days shall constitute the base line for monthly (or portion thereof) weather time evaluations.

c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day.

d. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph (b), above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "DEFAULT (FIXED PRICE

CONSTRUCTION)".

e. For all work under this contract, adverse weather is defined as:

(1) Rainfall - # of occurrences of precipitation greater than or equal to 0.10" (2.54mm).

(2) Snowfall - # of occurrences of precipitation greater than or equal to 1.00" (25.4mm). (Not applicable to Okinawa Area)

(3) Cold Temperature - # of occurrences when daily maximum temperature does not exceed the monthly mean low temperature or 32 degrees Fahrenheit (0 degrees Celsius), whichever is lower. (Not applicable to Okinawa Area)

(4) Concurrence between snowfall and cold temperature is 80%, i.e. 80% of the time snow falls, the temperature is "cold".

(5) Wind – Number of occurrences when the wind is gusting 30 knots (56 kilometers/hour) or greater.

f. The contractor's schedule must reflect the above anticipated adverse weather delays on all weather-dependent activities.

6. TYPHOON AND STORM PREPARATIONS. In order to minimize damage to public properties and prevent personal injury, the following actions will be taken upon declaration of the typhoon conditions described below. The Contractor shall insure that the construction sites are well prepared for protection from the damages of heavy rain and strong winds. The Contractor will develop and establish the necessary procedures to be taken for storm preparation and provide in his accident prevention plan, Part I, emergency phone numbers and addresses where at least three (3) officials of the company may be reached and notified in the event that an immediate typhoon alert is declared.

Tropical Cyclone Conditions of Readiness (TCCOR)

CONDITION DEFINITION per USFJINST 15-4001 01 Mar 2013

RESPONSE

Storm Watch

The winds are not forecast to exceed 50 knots (58 mph/26 m/s) sustained (the criteria for “destructive winds”) but there still exists a probability of high winds due to the proximity of the storm.

High winds may include gusts exceeding 50 knots and/or sustained winds meeting TCCOR 1 Caution criteria. The storm is also close enough to the area that a heightened alert status is necessary in order to rapidly establish elevated TCCOR conditions should the storm deviate from the forecast track. Personnel should follow Standard Operating Procedures for TCCOR Storm Watch and stay alert for any changes to TCCOR status.

When wind gusts of 30 knots (35 mph/16 m/s) or greater are forecast, the contractor will be required to perform general area cleanup and monitor TCCOR levels.

When a local storm warning has been issued, the Contractor competent person and/or SSHO shall determine whether it is necessary to implement manufacturer recommendations for securing the equipment to include Weight Handling Equipment (WHE).

Contractor reviews project site storm preparation plans and discuss plan of action with Contracting Officer’s Representative.

Winds of 50 knots (58 mph/26 m/s) sustained or greater are possible within 72 hrs.

When wind gusts of 30 knots (35 mph/16 m/s) or greater are forecast, the contractor will be required to perform general area cleanup and monitor TCCOR levels.

Cranes shall not be operated when wind speeds at the site attain the maximum wind velocity based on the surface/load ratio recommendations of the manufacturer.

At winds greater than 20 mph (17 knots/9 m/s), the operator, rigger, lift supervisor and SSHO shall cease all crane operations, evaluate conditions and determine if the lift can proceed with Contracting Officer’s Representative acceptance.

All elevated work above 6 ft (1.8 m) shall be risk assessed by the Contractor’s competent person and/or SSHO and discussed with the Contracting Officer’s Representative for acceptance.

Winds of 50 knots (58 mph/26 m/s) sustained or greater are possible within 48 hrs.

(1) Clean and remove all loose debris and waste including scrap wood and metal, empty barrels and concrete form materials no longer required on the job site, to a safe area for proper disposition.

(2) Secure, tie down and anchor construction field office and storage facilities, scaffolding, concrete forms and supports, doors, windows, opening covers, stored lumber and other materials, mechanized construction equipment, temporary power lines and supports, and other items that maybe blown away or that might cause injury or damage.

(3) Inspect all excavation and trenching work in process, and provide necessary temporary drainage and proper protection and shoring for excavation sides and openings, in order to prevent damage to public roads and facilities by slides or flooding. Accumulation of water in the excavation of structure foundation work will be controlled and minimized.

(4) Inspect scaffolding or work platforms for loose materials, planking, etc. that could become airborne projectile hazards and secure scaffold netting, tarps, etc. from wind loads.

Winds of 50 knots (58 mph/26 m/s) sustained or greater are possible within 24 hrs.

Work required at remote areas such as off-shore facilities or high elevations will cease immediately and the workers will be evacuated to a safe area. During TCCOR 2, the Contractor will continue the actions described in TCCOR 3 above and the construction site will be inspected for storm preparation by the Contracting Officer's Representative. The Contractor shall request an inspection by calling the Contracting Officer's Representative at the appropriate Japan District field office.

1 Winds of 50 knots (58 mph/26 m/s) All work will cease immediately and the sustained or greater are possible within 12 hrs.

Contractor's representative shall insure that all necessary storm preparations, including the items listed below, are completed.

(1) All electrical circuits and equipment including temporary power lines are cut off and secured against unauthorized use.

(2) Gas cylinders, hot work equipment and flammable materials properly stored at a safe area.

(3) No igniting source is present.

(4) All workers have been evacuated from the construction site. When TCCOR 1 is declared without the normal progression through TCCOR 3 and/or 2, the Contractor will take the actions listed in TCCOR 3 above, and also follow the procedures described herein.

1 Caution Winds of 35 to 49 knots (39/17 to 56/25 mph / m/s) sustained are occurring.

Construction Sites Secured

1 Emergency Winds of 50 knots (58 mph/26 m/s) sustained or greater are occurring.

Construction Sites Secured

1 Recovery

Winds of 50 knots (58 mph/26 m/s) sustained or greater are no longer forecast to occur. Strong winds may still exist.

Contractors and Contracting Officer’s Representatives begin storm damage assessments and clean up.

Storm Clear

The storm is over and not forecast to return. Used to inform personnel that the threat of the storm is over, but the storm damage could still present a danger.

Contractor may resume normal activities.

The construction site will be investigated for all damage caused by the typhoon or high winds and the result of the investigation will be furnished in verbal or written form to the Contracting Officer's Representative as soon as practicable.

Complete and submit PODWP 134 Typhoon Damage Report for storm damages or negative report of damage to Emergency Management, Construction Division, and Safety Office.

All Clear The storm is over and not forecast to return, and recovery efforts are complete.

Resume normal activities

7. COORDINATION OF GOVERNMENT PROPERTY.

a. The Contractor shall submit, as necessary, to the Government, within thirty (30) calendar days after date of receipt of Notice to Proceed:

(1) An itemized list of Government property, if any, to be salvaged (GSP) with anticipated dates this property will be turned over to the Government by the Contractor.

(2) An itemized list of Government-Furnished Property (GFP), if any, with dates this property is anticipated to be required by the Contractor.

b. The above lists will be used by the Government for scheduling purposes. (If changes to the lists are made following initial submittal, these changes shall be made in writing and provided to the Government.)

8. ASBESTOS PROHIBITION & CERTIFICATION.

a. Materials or products containing more than one-tenth of one percent (0.1%) by total weight, of the material or product, of asbestos shall not be used in this project. The Contracting Officer, at any time prior to acceptance of the work, or during the period designated for warranty of the work, if any, may reject materials and products that contain asbestos in excess of one-tenth of one percent by weight, and direct the removal of such materials and products from the jobsite, at the sole expense of the contractor, and without additional time granted for performance of the work. After completion of this contract, if asbestos (exceeding 0.1% by weight) is discovered in the products or materials (excluding items permitted by the exception) installed by the contractor, the Government reserves the right to direct the Contractor to perform asbestos abatement and restoration work, as required, at the Contractor’s sole cost. Asbestos abatement work (removal and disposal of asbestos-containing materials and products) shall be accomplished in accordance with currently applicable United States Government standards for such work.

"Exception: Where suitable asbestos-free substitutes do not exist for a material or product, the contractor may use a material or product containing asbestos in the excess of 0.1% by weight, with the prior written approval of the Contracting Officer. The Contractor shall submit a written request for such substitution, accompanied by a certification from the manufacturer of the material or product that shall set forth, in specific detail, the amount of asbestos present in the material or product. When available, laboratory analysis of the material or product for asbestos content shall be included with the submittal."

b. The Government may conduct asbestos testing on suspected asbestos-containing materials and products excluding items permitted by the "Exception", and such testing will be conducted at the expense of the Government. However, wherever destructive testing is required, or a material or product must be utilized by the Government for testing, the Contractor, shall, at its own expense, repair or replace the material or product, or the item of work that has been disturbed by testing, if the test results confirm presence of asbestos exceeding 0.1% by weight. In the event test results indicate 0.1% or less asbestos content or complete absence of asbestos, the Contractor shall restore the test site to its original condition and the cost of restoration work, as approved by the Contracting Officer, shall be borne by the Government.

c. As a minimum, the Contractor shall furnish manufacturer's certification for the items listed below, excluding items permitted by the "Exception", certifying that they are asbestos free or do not contain asbestos in excess of 0.1% by weight, as applicable. However, when presence of asbestos is suspected in other products and materials used in this project, the Contractor shall be required to provide such certification for those additional items when so directed by the Contracting Officer. Asbestos certification shall be required for the items applicable to this project only.

(1) Vinyl sheet/vinyl tile flooring, including accessories and adhesives

(2) Insulation materials including facing

(3) Gaskets for piping and duct work

(4) Acoustical Tiles

(5) Firestopping materials

(6) Fireproofing materials

(7) Special Coating, including factory applied coatings, on sheet metal roofing and siding

(8) Wallboard for all interior and exterior applications including joint compounds

(9) Adhesives (other than Item 1) used in the project

(10) Tape materials used in the project

(11) Roofing and Siding, nonmetallic

(12) Felt materials and cushion materials

(13) Pre-mixed mortars, grouts, leveling compounds, fillers, and other cementitious materials

(14) Caulking and sealing materials

d. All submittals shall be accompanied by a certification from the manufacturer of the material or product that the material or product is asbestos-free; or shall set forth, in specific detail, the amount of asbestos present in the material or product. Documentary evidence of laboratory analysis of the material or product for asbestos content, conducted by a qualified independent testing laboratory, shall be included with the submittal.

9. PROJECT SIGN.

For task orders over JPY 15,000,000, the Contractor shall provide one project sign fabricated to size and design shown on JED-ARMY-SIGN-1 and JED-ARMY-SIGN-2. The sign shall be rigidly formed and erected at location designated by the Contracting Officer prior to commencement of work. A blue-line drawing of different letter sizes and style will be made available by the Contracting Officer to the Contractor, upon request. Prior to painting the sign, the Contractor shall submit for approval a sketch, similar to diagram shown on JED-ARMY-SIGN-1, indicating the actual information for the project. The sketch shall indicate lettering dimensions and locations. The Corps of Engineers castle logo shall be painted red per JED-ARMY-SIGN-1 and JED-ARMY-SIGN-2. No separate payment will be made for the sign, and all costs in connection therewith shall be included in the contract price for the project. The sign will be subject to the approval of the Contracting Officer. Upon completion of work under this contract, the project sign shall be removed from the job site and shall remain the property of the Contractor.

10. COST BREAKDOWNS - CONTRACT MODIFICATIONS, RFP.

a. When cost or pricing data will be required from the contractor, or any subcontractor, for the pricing of a proposed contract modification with the value in excess of $750,000 or Yen equivalent thereto (the sum of deletions and additions), FAR Clause 52.215-11, "Price Reduction for Defective Cost or Pricing Data - Modifications" and 52.215-13, "Subcontractor Cost or Pricing Data - Modifications", are applicable under this contract. Cost or Pricing data shall be submitted in accordance with Table 15-2 of FAR 15.408. The contractor is required to identify the portion of the data submitted that is factual in nature and the portion that is judgmental in nature plus contingencies included in the proposal. With regard to the judgmental factors, the contractor must identify the factual data used in arriving at the judgmental factors.

b. When the proposed price to a contract modification is at or below the cost or pricing data threshold of $750,000 or equivalent thereto, information other than cost or pricing data will be required for submission by the contractor in its own format. This information is not considered cost or pricing data and should not be certified by the contractor.

c. The contractor, when responding to any government's request for proposal letter for a proposed modification, shall furnish TWO (2) COPIES OF COST BREAKDOWN (IN ENGLISH) in sufficient detail to permit an analysis of all material, labor, equipment, subcontract and overhead costs for the establishment of price reasonableness or cost realism.

d. The cost breakdown shall include separately the direct cost for the use of the construction equipment, the direct cost of labor and of materials and equipment for incorporation in the work, and the indirect costs attributable to direct costs.

e. The information submitted shall support the price proposed and shall include sufficient detail or cross references to clearly establish the relationship of the information provided to the price proposed.

11. SAFETY STANDARDS. The successful offeror will be required to comply with the Occupational Safety and Health Act (OSHA) standards as well as the Corps of Engineers Manual 385-1-1, Safety and Health Requirements Manual.

12. PERFORMANCE OF WORK BY THE CONTRACTOR – DEFINED. For the purpose of Clause entitled, "PERFORMANCE OF WORK BY THE CONTRACTOR", of Special Contract Requirements, work on the site with the Contractor's own organization means physical activities at the site other than work performed by subcontractors, procurement of materials for installation by subcontractors, or providing equipment to be used solely by subcontractors.

13. SPECIAL TREATMENT OF PACKAGING OF EQUIPMENT AND MATERIAL. Bidders are cautioned that equipment and material requiring ocean transportation may be subjected to inordinate dangers and special treatment or packaging may be necessary to assure arrival in a condition conforming to contract requirements.

14. JAPANESE CONSUMPTION TAX. Effective April 1, 2014, the Government of Japan increased the rate of Japanese Consumption Tax from 5% to 8%. By virtue of Article XII of the Status of Forces Agreement (SOFA), materials, supplies, equipment and services procured for official purposes in Japan by the United States armed forces, or its authorized procurement agencies are EXEMPT from various Japanese Taxes, including Consumption Tax. The exemption from the Japanese Consumption Tax applies not only to Japanese prime contractors, but also to Japanese subcontractors or suppliers at every level regardless of the nationality of the prime contractor whether a Japanese or a Foreign firm. The instruments listed hereinafter have been agreed to by both governments of Japan and the U.S. as "Proof of Purchase by U.S. Forces in Japan.”

Standard Form 1034 Public Voucher for Purchases and Services other than Personal

DD Form 1155 Order for Supplies or Services

Standard Form 44 Purchase Order-Invoice-Voucher

ENG Form 93 Payment Estimate

Therefore, Japanese Consumption Tax shall NOT be included in your bid, proposal or quote.

15. PAYMENTS UNDER TASK ORDERS

a. PROGRESS PAYMENTS: In accordance with the FAR 52.232-5 - “PAYMENTS UNDER FIXED PRICE CONSTRUCTION CONTRACTS”, payments to the Contractor shall be made for the actual quantities of work performed by the Contractor and accepted by the Government under specific TASK ORDERS issued by the Contracting Officer or his/her authorized representative. Solely for the purpose of the aforementioned clause, each TASK ORDER shall be considered a separate division of the work.

b. FINAL PAYMENTS:

(1) Upon satisfactory completion by the Contractor and acceptance by the Contracting Officer of the work done by the Contractor under individual task orders, the Contractor shall be paid the balance of any money due for the work under that TASK ORDER, including any retained percentages relating to that order.

(2) Notwithstanding any other provision in this contract, before final payment of each task order issued under this contract, or before settlement upon termination of the task order, and as a condition precedent thereto, the Contractor shall execute and deliver to the Contracting Officer, a release of claims against the government arising under or by virtue of task orders under this contract, other than any claims that are specifically excepted by the Contractor from the operation of the release in amounts stated in the release.

16. KEY PERSONNEL AND SUBCONTRACTORS. In connection with the work covered by this contract, any in-house personnel and subcontractors will be limited to individuals or firms that were specifically identified and agreed to during negotiations for each task order. The contractor shall obtain the Contracting Officer’s written consent before making any substitution for these designated in-house personnel and subcontractors.

17. CONTRACT MANPOWER REPORTING.

The Contractor shall access and report using the DoD’s Contract Manpower Reporting Application (CMRA) system. Each DoD service/component has a web address link to their appropriate CMRA system. The web address for the data collection site is: http://www.ecmra.mil. On this web site address please select the link for the Department of the Army CMRA. You will be required to register for a CMRA account. There is a helpdesk and user’s manual. The Contractor is required to completely fill in all the required information. The required information includes:

a) Contracting Office, Contracting Officer, Contracting Officer’s Representative

b) Contract number, including task and delivery order number

c) Beginning and ending dates covered by the reporting period (Reporting period will be the period of performance not to exceed 12 months ending September 30 of each year)

d) Contractor name, address, phone number, email address, identity of contractor employee entering data

e) Estimated direct labor hours (including sub-contractors)

f) Estimated direct labor dollars paid this reporting period (including sub-contractors)

g) Total payment including sub-contractors

h) Predominant Federal Service Code (FSC) reflecting services provided by contractor and separate FSC codes for each sub-contractor

i) Estimated data collection cost

j) Organizational title associated with the Unit Identification Code (UIC). For Japan Engineer

District contracts, Contractor shall use

UIC: W2SN02

ORGANIZATIONAL TITLE:

U.S. Army Corps of Engineers, Japan District Contracting Division Building 250, Room 147, Camp Zama http://www.ecmra.mil/

Zama-shi, Kanagawa-ken 252-8511

k) Locations where contractor and sub-contractor perform the work

As part of the submission, Contractor will also provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period will be the period of performance not to exceed 12 months ending September 30 of each Government Fiscal Year and must be reported by October 31 of each calendar year. Contractors may use a direct XML data transfer to the database or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s system to the secure website without the need for separate data entries for each required data element at the website.

The specific formats for the XML direct transfer may be downloaded from the website.

18. OMBUDSMAN. Task and Delivery Order Ombudsman. IAW FAR 16.505 (B)(6) referring to FAR Part 16 "Ordering." The head of the agency has designated a task-order contract and delivery-order contract ombudsman. The ombudsman must review complaints from contractors and ensure that they are afforded a fair opportunity to be considered, consistent with the procedures in the contract. The ombudsman is a senior agency official who is independent of the contracting officer and may be the agency’s competition advocate.

Primary:

USACE Task and Delivery Order Ombudsman Ms. Jacqueline C. Woodson Acquisition Support Division U.S. Army Corps of Engineers 7701 Telegraph Road, Casey Building, Room 2115 Alexandria, VA 22315 Phone: 703-428-6323 Email: Jacqueline.C.Woodson@usace.army.mil

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2016 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.236-28 Preparation of Proposals--Construction OCT 1997 252.215-7008 Only One Offer OCT 2013

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Indefinite Delivery Indefinite Quantity (IDIQ) contract resulting from this solicitation.

(End of provision) mailto:Jacqueline.C.Woodson@usace.army.mil

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

Contracting Officer U.S. Army Corps of Engineers, Japan District

APO AP 96338-5010

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

Specific to each task order.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

252.204-7004 ALTERNATE A, SYSTEM FOR AWARD MANAGEMENT (FEB 2014)

(a) Definitions. As used in this provision—

“System for Award Management (SAM) database” means the primary Government repository for contractor information required for the conduct of business with the Government.

“Commercial and Government Entity (CAGE) code” means—

(1) A code assigned by the Defense Logistics Information Service (DLIS) to identify a commercial or

Government entity; or

(2) A code assigned by a member of the North Atlantic Treaty Organization that DLIS records and maintains in the CAGE master file. This type of code is known as an “NCAGE code.”

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and

Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System +4 (DUNS+4) number” means the DUNS number assigned by D&B plus a

4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional

SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts (see FAR 32.11) for the same parent concern.

“Registered in the System for Award Management (SAM) database” means that—

(1) The contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, and Contractor and Government Entity (CAGE) code into the SAM database; and

(2) The contractor has completed the Core Data, Assertions, Representations and Certifications, and Points of

Contact sections of the registration in the SAM database;

(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification

Number (TIN) with the Internal Revenue Service (IRS). The Contractor will be required to provide consent for

TIN validation to the Government as part of the SAM registration process; and

(4) The Government has marked the record “Active.”

(b) (1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the SAM database.

(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number—

(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or http://fedgov.dnb.com/webform

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business name.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company physical street address, city, state and Zip Code.

(iv) Company mailing address, city, state and Zip Code (if separate from physical).

(v) Company telephone number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii)…