A.07.24_AMD_0001_FY18_81st_Resets.pdf

PDF 432 KB Posted

Attached to
FY18 81st Various Resets-MS007 HVAC Reset Federal contract opportunity
Solicitation number
W912HP18R1004
Issued by
Department of the Army Corps of Engineers Engineering District Charleston

About this file

AMD 0001 Document

View the file

Other files for this federal contract opportunity

Other files attached to FY18 81st Various Resets-MS007 HVAC Reset, newest first.
File Type Posted
A.07.24_AMD_0002_18R1004_FY18_81st_Resets.pdf PDF
A.07.24_AMD_0001_MS007_Bldg_JK215_Asbestos_Sample_Locations.pdf PDF
A.07.24_AMD_0001_MS007_Bldg_JK215_Lead_Paint_Sample_Locations.pdf PDF
KY043_HVAC_Reset_Drawings_RTA_06_22_18.pdf PDF
FL037_ELEC_Reset_DRAWINGS_06_15_18.pdf.pdf PDF
KY043_Plumbing_Reset_Drawings_RTA_06_15_18.pdf PDF
A.07.23_Solicitation_W912HP18R1004_81st_Resets.pdf PDF
AL040_HVAC_Reset_Drawings_RTA_06_22_18.pdf PDF
NC019_HVAC_Reset_Drawings_RTA_06_26_18.pdf PDF
KY043_HVAC_PLUMB_RESETS_SPEC_RTA_06_28_18.pdf PDF
NC027_HVAC_Reset_Drawings_RTA_06_26_18.pdf PDF
NC019_HVAC_RESET_SPEC_RTA_06_28_18.pdf PDF
MS007_HVAC_Reset_Drawings_RTA_06_22_18.pdf PDF
A.07.23_Attachment_2_Descriptive_Summary_Sheet.docx DOCX document
AL040_HVAC_RESET_SPEC_RTA_06_28_18.pdf PDF
A.07.23_Attachment_1_Proposal_Data_Sheet.docx DOCX document
NC027_HVAC_RESET_SPEC_RTA_06_28_18.pdf PDF
FL037_HVAC_ELEC_RESETS_SPEC_RTA_06_28_18.pdf PDF
MS007_HVAC_RESET_SPEC_RTA_06_28_18.pdf PDF
A.07.23_Attachment_4_Project_Proposal_Chart.docx DOCX document
FL037_HVAC_Reset_Drawings_RTA_06_22_18.pdf PDF
A.07.23_Attachment_3_PPQ_Questionnaire.docx DOCX document
KY043_Plumbing_Reset_Drawings_RTA_06_15_18.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY18RESETS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation W912HP18R1004, 81st Resets, is hereby amended to revise specifications and draw ings. Proposal due date has been extended. See Continuation Page for further details. Tw o attachments have been included as a result of this AMD. They include Bldg JK215 Asbestos Sample Locations and Bldg JK215 Lead Paint Sample Locations.

1. CONTRACT ID CODE PAGE OF PAGES

1 11

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 26-Jul-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HP18R1004

X 9B. DATED (SEE ITEM 11)

29-Jun-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Jul-2018

CODE

US ARMY CORPS OF ENGINEERS, CHARLESTON

69-A HAGOOD AVENUE

CHARLESTON SC 29403

W912HP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HP18R1004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

TECHNICAL REVISION A

AL040 HVAC Reset

SPECIFICATIONS:

02 41 00 DEMOLITION

1) ADD the following Paragraph:

“1.2.3 Existing Hazardous Materials

The Hazardous Materials Assessment Report is provided in Specification Section 02 84 00 to show where hazardous material is expected to exist in the facilities. The intent of this contract is NOT to fully remove all hazardous material from the facilities. The intent is to only disturb the hazardous material as needed to perform the work in this contract, and that any hazardous material disturbed by this work is to be addressed in accordance with the Division 02 Existing Conditions specifications.

02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES

2) Paragraph 3.1 GENERAL REQUIREMENTS

DELETE the first sentence that states “Asbestos abatement work tasks shall be performed as summarized in Table 1.”

3) Paragraph 3.3.1 Removal of Mobile Objects

DELETE the sentence that states “The Government will remove Furniture and equipment from the area of work.”

And REPLACE it with “The contractor shall remove furniture and equipment from the work area as needed before work begins”.

DRAWINGS:

4) Sheet A-101, LEGEND, DELETE the second legend item and symbol “EXISTING LAY-IN ACOUSTICAL

CEILING GID SYSTEM (REINSTALLED)”.

5) Sheet A-101, DELETE GENERAL NOTE 2 that states “IN ALL SPACES THAT RECEIVE NEW CEILINGS, PROVIDE ACOUSTICAL PANELS AND GRID SYSTEM SIMILAR TO EXISTING SYSTEM”.

6) Sheet A-101, DELETE GENERAL NOTE 8 that states “NEW CEILINGS SHALL BE RE-INSTALLED TO

MATCH EXISITNG CEILING HEIGHTS” and REPLACE it with “NEW CEILINGS SHALL BE

INSTALLED TO MATCH EXISITNG CEILING HEIGHTS.”

7) Sheet A-102, LEGEND, DELETE the second legend item and symbol “EXISTING LAY-IN ACOUSTICAL

CEILING GID SYSTEM (REINSTALLED)”.

8) Sheet A-102, DELETE GENERAL NOTE 2 that states “IN ALL SPACES THAT RECEIVE NEW CEILINGS, PROVIDE ACOUSTICAL PANELS AND GRID SYSTEM SIMILAR TO EXISTING SYSTEM”.

9) Sheet A-102, DELETE GENERAL NOTE 8 that states “NEW CEILINGS SHALL BE RE-INSTALLED TO MATCH EXISITNG CEILING HEIGHTS” and REPLACE it with “NEW CEILINGS SHALL BE

INSTALLED TO MATCH EXISITNG CEILING HEIGHTS.”

10) Sheet A-103, LEGEND, DELETE the second legend item and symbol “EXISTING LAY-IN ACOUSTICAL

CEILING GID SYSTEM (REINSTALLED)”.

11) Sheet A-103, DELETE GENERAL NOTE 2 that states “IN ALL SPACES THAT RECEIVE NEW CEILINGS, PROVIDE ACOUSTICAL PANELS AND GRID SYSTEM SIMILAR TO EXISTING SYSTEM”.

12) Sheet A-103, DELETE GENERAL NOTE 8 that states “NEW CEILINGS SHALL BE RE-INSTALLED TO MATCH EXISITNG CEILING HEIGHTS” and REPLACE it with “NEW CEILINGS SHALL BE

INSTALLED TO MATCH EXISITNG CEILING HEIGHTS.”

13) Sheet M-104, DELETE the sentence in HVAC KEYED NOTE 3 that states “SEE DETAIL #3, Sheet G-005.”

14) Sheet M-105, DELETE the sentence in HVAC KEYED NOTE 6 that states “SEE DETAIL #3, Sheet G-005.”

15) Sheet M-106, DELETE the sentence in HVAC KEYED NOTE 6 that states “SEE DETAIL #3, Sheet G-005.”

16) Sheet M-702, Detail #1 VAV AIR HANDLING UNIT, on the call out for the smoke detector in the return and supply air duct, DELETE “TO FIRE ALARM PANEL” and REPLACE with “TO EXISTING FIRE ALARM

PANEL”.

FL037 HVAC Reset

SPECIFICATIONS:

17) ADD the following Paragraph:

The Hazardous Materials Assessment Report is provided in Specification Section 02 84 00 to show where hazardous material is expected to exist in the facilities. The intent of this contract is NOT to fully remove all hazardous material from the facilities. The intent is to only disturb the hazardous material as needed to perform the work in this contract, and that any hazardous material disturbed by this work is to be addressed in accordance with the Division 02 Existing Conditions specifications.

18) Paragraph 3.1 GENERAL REQUIREMENTS

DELETE the first sentence that states “Asbestos abatement work tasks shall be performed as summarized in Table

19) Paragraph 3.3.1 Removal of Mobile Objects

DELETE the sentence that states “The Government will remove Furniture and equipment from the area of work.”

And REPLACE it with “The contractor shall remove furniture and equipment from the work area as needed before work begins”.

DRAWINGS:

20) Sheets M-702, M-704 and M-706, Detail #1 VAV AIR HANDLING UNIT, on the call out for the smoke detector in the return and supply air duct, DELETE “TO FIRE ALARM PANEL” and REPLACE with “TO

EXISTING FIRE ALARM PANEL.”

FL037 Electrical Reset

21) ADD the following Paragraph:

The Hazardous Materials Assessment Report is provided in Specification Section 02 84 00 to show where hazardous material is expected to exist in the facilities. The intent of this contract is NOT to fully remove all hazardous material from the facilities. The intent is to only disturb the hazardous material as needed to perform the work in this contract, and that any hazardous material disturbed by this work is to be addressed in accordance with the Division 02 Existing Conditions specifications.

22) Paragraph 3.1 GENERAL REQUIREMENTS

DELETE the first sentence that states “Asbestos abatement work tasks shall be performed as summarized in Table

23) Paragraph 3.3.1 Removal of Mobile Objects

DELETE the sentence that states “The Government will remove Furniture and equipment from the area of work.”

And REPLACE it with “The contractor shall remove furniture and equipment from the work area as needed before work begins”.

KY043 HVAC Reset

SPECIFICATIONS:

24) ADD the following Paragraph:

The Hazardous Materials Assessment Report is provided in Specification Section 02 84 00 to show where hazardous material is expected to exist in the facilities. The intent of this contract is NOT to fully remove all hazardous material from the facilities. The intent is to only disturb the hazardous material as needed to perform the work in this contract, and that any hazardous material disturbed by this work is to be addressed in accordance with the Division 02 Existing Conditions specifications.

02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES

25) Paragraph 3.1 GENERAL REQUIREMENTS

DELETE the first sentence that states “Asbestos abatement work tasks shall be performed as summarized in Table 1.”

26) Paragraph 3.3.1 Removal of Mobile Objects

DELETE the sentence that states “The Government will remove Furniture and equipment from the area of work.”

And REPLACE it with “The contractor shall remove furniture and equipment from the work area as needed before work begins”.

DRAWINGS:

27) Sheets PD102, PD103 and PD104: DELETE the highlighted note above GENERAL NOTES AND LEGEND that states “CLEAN ALL ROOF DRAINS AND ROOF DRAIN PIPING. SECURE DOME STRAINERS TO

THEIR RESPECTIVE DRAIN BODIES AS REQUIRED.”

KY043 HVAC Reset

28) ADD the following Paragraph:

The Hazardous Materials Assessment Report is provided in Specification Section 02 84 00 to show where hazardous material is expected to exist in the facilities. The intent of this contract is NOT to fully remove all hazardous material from the facilities. The intent is to only disturb the hazardous material as needed to perform the work in this contract, and that any hazardous material disturbed by this work is to be addressed in accordance with the Division 02 Existing Conditions specifications.

29) Paragraph 3.1 GENERAL REQUIREMENTS

DELETE the first sentence that states “Asbestos abatement work tasks shall be performed as summarized in Table

30) Paragraph 3.3.1 Removal of Mobile Objects

DELETE the sentence that states “The Government will remove Furniture and equipment from the area of work.”

And REPLACE it with “The contractor shall remove furniture and equipment from the work area as needed before work begins.”

MS007 HVAC Reset

SPECIFICATIONS:

31) ADD the following Paragraph:

The Hazardous Materials Assessment Report is provided in Specification Section 02 84 00 to show where hazardous material is expected to exist in the facilities. The intent of this contract is NOT to fully remove all hazardous material from the facilities. The intent is to only disturb the hazardous material as needed to perform the work in this contract, and that any hazardous material disturbed by this work is to be addressed in accordance with the Division 02 Existing Conditions specifications.

32) Paragraph 3.1 GENERAL REQUIREMENTS

DELETE the first sentence that states “Asbestos abatement work tasks shall be performed as summarized in Table

33) Paragraph 3.3.1 Removal of Mobile Objects

DELETE the sentence that states “The Government will remove Furniture and equipment from the area of work.”

And REPLACE it with “The contractor shall remove furniture and equipment from the work area as needed before work begins.”

02 84 00 HAZARDOUS MATERIALS REPORT

34) DELETE Page 62 of 100 and 63 of 100 and REPLACE with attached Sheet ASBLOC.

35) DELETE Page 93 of 100 and 94 of 100 and REPLACE with attached Sheet LBPLOC.

DRAWINGS:

36) Sheet A-101, LEGEND, DELETE the second legend item and symbol “EXISTING LAY-IN ACOUSTICAL

CEILING GID SYSTEM (REINSTALLED)”.

37) Sheet A-101, DELETE GENERAL NOTE 3 that states “IN ALL SPACES THAT RECEIVE NEW CEILINGS, PROVIDE ACOUSTICAL PANELS AND GRID SYSTEM SIMILAR TO EXISTING SYSTEM”.

38) Sheet A-101, DELETE GENERAL NOTE 8 that states “NEW CEILINGS SHALL BE RE-INSTALLED TO

MATCH EXISITNG CEILING HEIGHTS” and REPLACE it with “NEW CEILINGS SHALL BE

INSTALLED TO MATCH EXISITNG CEILING HEIGHTS.”

39) Sheet A-102, LEGEND, DELETE the second legend item and symbol “EXISTING LAY-IN ACOUSTICAL

CEILING GID SYSTEM (REINSTALLED)”.

40) Sheet A-102, DELETE GENERAL NOTE 3 that states “IN ALL SPACES THAT RECEIVE NEW CEILINGS, PROVIDE ACOUSTICAL PANELS AND GRID SYSTEM SIMILAR TO EXISTING SYSTEM”.

41) Sheet A-102, DELETE GENERAL NOTE 8 that states “NEW CEILINGS SHALL BE RE-INSTALLED TO MATCH EXISITNG CEILING HEIGHTS” and REPLACE it with “NEW CEILINGS SHALL BE

INSTALLED TO MATCH EXISITNG CEILING HEIGHTS.”

42) Sheet A-103, LEGEND, DELETE the second legend item and symbol “EXISTING LAY-IN ACOUSTICAL

CEILING GID SYSTEM (REINSTALLED)”.

43) Sheet A-103, DELETE GENERAL NOTE 3 that states “IN ALL SPACES THAT RECEIVE NEW CEILINGS, PROVIDE ACOUSTICAL PANELS AND GRID SYSTEM SIMILAR TO EXISTING SYSTEM”.

44) Sheet A-103, DELETE GENERAL NOTE 8 that states “NEW CEILINGS SHALL BE RE-INSTALLED TO MATCH EXISITNG CEILING HEIGHTS” and REPLACE it with “NEW CEILINGS SHALL BE

INSTALLED TO MATCH EXISITNG CEILING HEIGHTS.”

45) Sheet A-104, LEGEND, DELETE the second legend item and symbol “EXISTING LAY-IN ACOUSTICAL

CEILING GID SYSTEM (REINSTALLED)”.

46) Sheet A-104, DELETE GENERAL NOTE 3 that states “IN ALL SPACES THAT RECEIVE NEW CEILINGS, PROVIDE ACOUSTICAL PANELS AND GRID SYSTEM SIMILAR TO EXISTING SYSTEM”.

47) Sheet A-104, DELETE GENERAL NOTE 8 that states “NEW CEILINGS SHALL BE RE-INSTALLED TO MATCH EXISITNG CEILING HEIGHTS” and REPLACE it with “NEW CEILINGS SHALL BE

INSTALLED TO MATCH EXISITNG CEILING HEIGHTS.”

48) Sheet M-702, Detail #1 VAV AIR HANDLING UNIT, on the call out for the smoke detector in the return and supply air duct, DELETE “TO FIRE ALARM PANEL” and REPLACE with “TO EXISTING FIRE ALARM

PANEL”.

NC019 HVAC Reset

49) ADD the following Paragraph:

The Hazardous Materials Assessment Report is provided in Specification Section 02 84 00 to show where hazardous material is expected to exist in the facilities. The intent of this contract is NOT to fully remove all hazardous material from the facilities. The intent is to only disturb the hazardous material as needed to perform the work in this contract, and that any hazardous material disturbed by this work is to be addressed in accordance with the Division 02 Existing Conditions specifications.

02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES

50) Paragraph 3.1 GENERAL REQUIREMENTS

DELETE the first sentence that states “Asbestos abatement work tasks shall be performed as summarized in Table

51) Paragraph 3.3.1 Removal of Mobile Objects

DELETE the sentence that states “The Government will remove Furniture and equipment from the area of work.”

And REPLACE it with “The contractor shall remove furniture and equipment from the work area as needed before work begins”.

NC027 HVAC Reset

SPECIFICATIONS

52) ADD the following Paragraph:

The Hazardous Materials Assessment Report is provided in Specification Section 02 84 00 to show where hazardous material is expected to exist in the facilities. The intent of this contract is NOT to fully remove all hazardous material from the facilities. The intent is to only disturb the hazardous material as needed to perform the work in this contract, and that any hazardous material disturbed by this work is to be addressed in accordance with the Division 02 Existing Conditions specifications.

02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES

53) Paragraph 3.1 GENERAL REQUIREMENTS

DELETE the first sentence that states “Asbestos abatement work tasks shall be performed as summarized in Table

54) Paragraph 3.3.1 Removal of Mobile Objects

DELETE the sentence that states “The Government will remove Furniture and equipment from the area of work.”

And REPLACE it with “The contractor shall remove furniture and equipment from the work area as needed before work begins.”

DRAWINGS:

55) Sheet A-102, DELETE the sentence in GENERAL NOTE 2 that states “ACTUAL INSTALLATION SHALL

MATCH EXISTING.” And ADD the following: “NEW ACOUSTIC CEILINGS ARE TO BE 2’X2’ LAY-IN

IN LIEU OF THE 2’X4’ SYSTEM SHOWN. ALTHOUGH NOT SHOWN IN THIS PLAN, REMOVE THE

EXISITING ACOUSTIC CEILINGS IN ROOMS 128 AND 129 AND PROVIDE NEW ACOUTSIC

CEILINGS.”

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 29-Jul-2018 02:00 PM to 07-Aug-2018 02:00 PM.

The contractor period of performance begin 10 has been added.

The following have been modified:

CONTRACT LINE ITEM SCHEDULE

FL037 HVAC/Elec Resets

CLIN

INFO

DESCRIPTION PRICE INFO

CLIN FACID Description Location Contractor Proposed Price

0001 FL037 HVAC Reset St. Petersburg (1LT Max R Stover

USARC)

OPTION

FL037 Elec Reset St. Petersburg (1LT Max R Stover

USARC)

Total: $

NC019 HVAC Reset

DESCRIPTION PRICE INFO

CLIN FACID Description Location Contractor Proposed Price

0001 NC019 HVAC Reset Garner (BG James Moore USARC) $

AL040 HVAC Reset

DESCRIPTION PRICE INFO

CLIN FACID Description Location Contractor

0001 AL040 HVAC Reset Opelika (Robert R. Marde USARC) $

MS007 HVAC Reset

DESCRIPTION PRICE INFO

CLIN FACID Description Location Contractor

0001 MS007 HVAC Reset Jackson (Jackson AFRC) $

KY043 HVAC/Plumbing Resets

DESCRIPTION PRICE INFO

CLIN FACID Description Location Contractor Proposed Price

0001 KY043 HVAC Reset Lexington (Lexington AFRC) $

0002 KY043 Plumbing Reset Lexington (Lexington AFRC)

Total: $

NC027 HVAC Reset

INFO

DESCRIPTION PRICE INFO

CLIN FACID Description Location Contractor

0001 NC027 HVAC Reset Hickory (D.W. Hudson USARC) $

BID SCHEDULE NOTES:

1. Type “No Bid” on the CLIN(s) that your firm does not intend to propose on.

2. FL037 Line 0002, Electrical Reset: In the event, FL037 Electrical Reset is not exercsied at the time of award, a separate Notice To Proceed (NTP) will be issued and the completion date will be separate from the base bid. Reference FAR Clause 52.211-10 and 52.217-7 for further details.

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been added by full text:

52.217-5 EVALUATION OF OPTIONS (JUL 1990)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

(End of provision)

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor anytime between date of contract award and 28 February 2019. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of clause)

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the days specifed in the chart below for each project. The time stated for completion shall include final cleanup of the premises.

Project

Number of days to complete after receipt of notice to proceed AL040 240 calendar days FL037 240 calendar days KY043 210 calendar days MS007 240 calendar days NC019 240 calendar days NC027 240 calendar days

If FL037 Electrical Reset is not exercised until after task order award, a separate pre-construction kick-off and NTP will be issued and it will have its own separate completion date, which is 240 calendar days from NTP. The option will not extend the established completion date of the base bid. Those established dates will become interim completion milestones. Interim evaluations will be issued and entered into the Contractor Performance Assessment Reporting System (CPARS) to appraise performance with regard to meeting interim completion milestones within the required time periods. These interim evaluations will contribute to the final performance rating.

HVAC System Testing: In the event the Heating and/or Air Conditioning Systems cannot be tested at or near design temperatures during the above period, beneficial occupancy and use of the facilities may be accepted and final testing and adjustments of the heating and/or air conditioning deferred as specified in the appropriate testing clauses of the Technical Provisions. The HVAC Testing that the Contractor schedules after substantial completion has a value to the Government of 10 percent of the value of the equipment to be tested. The Contractor shall reserve that amount to be paid on any equipment that will require testing after substantial completion pursuant to the above referenced specification paragraph.

(End of clause)

(End of Summary of Changes)