Questions_&_Answers__1_PS01.doc

DOC document 23 KB Posted

Attached to
Construct Hardstand
Solicitation number
W912GY18R0026
Issued by

View the file

Other files

File Type Posted
W912GY18R0026.pdf PDF
Construction_control_manual.pdf PDF
PS-01-West_-_2016-02-02.pdf PDF
Visitor_Request_form1246R_Mar-2017.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PS01- Hardstand Questions & Answers Set 1

1. Please confirm the acreage of hardstand - is it 2 acres?

ANSWER: 1.96 acres according to the drawings

2. What is the approximate depth of the gas lines?

ANSWER: Approximately 2-3 feet

3. Can some of the brush be removed off-site? If so, where can the brush be re-located to and what percentage removed?

ANSWER: Yes, 100% can be removed to the clean dirt spoils area.

4. Does the fence have to be removed?

ANSWER: Yes

5. What direction does the phone lines run?

ANSWER: East and West