W81G6743460367

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to change exercise and completion dates for Option 1 and 2 as w ell as adjust related language w ithin the solicitation.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-Jul-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES-15-B-0005

X 9B. DATED (SEE ITEM 11)

01-Jul-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Jul-2015

CODE

CONTRACTING DIVISION

USACE - ST. PAUL

180 5TH STREET E SUITE 700

ST. PAUL MN 55101-1678

W912ES 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912ES-15-B-0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 3

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

1.4.1 Mobilization and Demobilization

1.4.1.1 Payment

Change:

Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for Mobilization and Demobilization as specified. Work shall include, but not be limited to, providing performance and payment bonds, moving of equipment to the project site, moving of equipment off the site, construction of pipelines, and removal of pipelines for the base bid and for Options 1 and 2. See clause 252.236‐7004 Payment for Mobilization and Demobilization, and the special contract requirement titled "Supplement to Clause 252.236‐7004, Payment for Mobilization and Demobilization".

To:

Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for Mobilization and Demobilization as specified. Work shall include, but not be limited to, providing performance and payment bonds, moving of equipment to the project site, moving of equipment off the site, construction of pipelines, and removal of pipelines for the base bid. See clause 252.236‐7004 Payment for Mobilization and Demobilization, and the special contract requirement titled "Supplement to Clause 252.236‐7004, Payment for Mobilization and Demobilization".

1.4.2 2nd Mobilization and Demobilization

1.4.2.1 Payment

Change:

Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for Mobilization and Demobilization as specified. Work shall include, but not be limited to, providing performance and payment bonds, moving of equipment to the project site, moving of equipment off the site, construction of pipelines, and removal of pipelines for Options 3, 4, and 5. See clause 252.236‐7004 Payment for Mobilization and Demobilization, and the special contract requirement titled "Supplement to Clause 252.236‐7004, Payment for Mobilization and Demobilization".

To:

Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for Mobilization and Demobilization as specified. Work shall include, but not be limited to, providing performance and payment bonds, moving of equipment to the project site, moving of equipment off the site, construction of pipelines, and removal of pipelines for Options 1, 2, 3, 4, and 5.

See clause 252.236‐7004 Payment for Mobilization and Demobilization, and the special contract requirement titled "Supplement to Clause 252.236‐7004, Payment for Mobilization and Demobilization".

SECTION 00010 - SOLICITATION CONTRACT FORM

DELIVERIES AND PERFORMANCE

The following Delivery Schedule item for CLIN 1001 has been changed from:

DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

01-DEC-2016 100,000 N/A

FOB: Destination

DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

01-DEC-2017 100,000 N/A

The following Delivery Schedule item for CLIN 2001 has been changed from:

01-DEC-2016 100,000 N/A

01-DEC-2017 100,000 N/A

SECTION 00700 - CONTRACT CLAUSES

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) -

ALTERNATE I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c):

1. Complete all contract work for the base requirement, with the exception of clearing and grubbing, no later than 01 December 2016. The requirements for clearing and grubbing shall be completed by 31 March 2016.

2. Complete all contract work for Options 1, 2, 3, 4, 5, if exercised, no later than 01 December 2017.

3. Complete all contract work for Option 7A “Water supply during Year 1”, if exercised, on 01 January 2017.

Complete all contract work for Option 7B “Water supply during Year 2”, if exercised, on 01 January 2018.

The time stated for completion shall include final cleanup of the premises.

The completion date is based on the assumption that the successful bidder will receive the notice to proceed by 07 October 2015. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

(End of clause)

252.236-7004 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (DEC 1991)

(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.

(1) Sixty (60) percent of the lump sum price upon completion of the contractor's mobilization at the work site.

(2) The remaining forty (40) percent upon completion of demobilization.

(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in paragraphs (a) (1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract.

(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of --

(i) Actual mobilization costs at completion of mobilization;

(ii) Actual demobilization costs at completion of demobilization; and

(iii) The remainder of this item in the final payment under this contract.

(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1) of this clause is not subject to appeal.

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been modified:

52.217-4002 EXERCISE OF OPTION TO EXTEND SERVICES

(a) The term of the base requirement shall be from date of the award of the contract through 01 December 2016. The Government has the unilateral right to extend the term of this contract when options are exercised by the Contracting Officer as follows:

Options Option Exercise Date Completion Date

Option 1 – Remove Dredge Material 01 June 2016 01 December 2017 Option 2 – Remove Dredge Material 01 June 2016 01 December 2017 Option 3 – Remove Dredge Material 01 June 2016 01 December 2017 Option 4 – Remove Dredge Material 01 June 2016 01 December 2017 Option 5 – Remove Dredge Material 01 June 2016 01 December 2017 Option 6 - 2nd Mob/Demob (see subparagraph (c)) 01 December 2017 Option 7 – Temporary Water Supply:

7A- Water supply during Year 1 01 December 2016 01 January 2017 7B- Water supply during Year 2 01 December 2017 01 January 2018

(b) The Government may unilaterally exercise Option(s) 1, 2, 3, 4, and 5 IN NUMERICAL ORDER at any time prior to or on the Option Exercise Dates identified in this special contract requirement, including at time of award.

(c) The Government will unilaterally exercise Option 6 when/if Option 1 is exercised.

(d) The Government may unilaterally exercise Option 7 (Option 7A “Water Supply During Year 1” and/or Option 7B “Water Supply During Year 2”) at any time prior to or on the Option Exercise Dates identified in this special contract requirement.

(e) Exercise of any option shall be evidenced on a Standard Form 1442 or Standard Form 30, citing this clause as the authority for exercising the option(s). The contract term shall be extended in accordance with clause 52.211-10 Commencement, Prosecution, and Completion of Work – Alt 1.The extended contract shall be considered to include this option clause.

(f) An option shall be considered to have been exercised: (1) at the time the Government transmits written notification to the Contractor if the transmission is by fax, email, or other electronic means; or (2) at the time the Government deposits the notification in the mail. Options may be exercised subject to funds becoming available prior to commencement of any performance.

(End of Summary of Changes)