- ugrade electrical service at sandy lake Mn
- Solicitation number
- W912ES-10-T-0105
About this file
TO ADD CLOSING DATE OF SEPT 29 2010
View the file
Other files
| File | Type | Posted |
|---|---|---|
| sandy lake elec.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912ES-10-T-0105-0002
W81G6702115671
The Scope Of Work (SOW) for this project is to replace current 30 amp campground pedestals at Sandy Lake Recreation area w ith 50 amp campground pedestals for campground sites; South Group camping, S-1 through S-21, North Group camping and N-2 through N-29, for a total of 60 campground pedestals; South Group camping site, North Group camping site and sites S-15 through S-19 each have tw o (2) campground pedestals. Upgrade the electrical services as required for the installation of new 50 amp campground pedestals. Circuits for campground pedestals shall not be connected to any other equipment and shall be limited to six (6), 50-amp campground pedestals or less.
Balance panelboard circuits for all electrical campground sites. For location of campground sites at the Sandy Lake Recreation Area, 22205 531st Lane, McGregor, Minnesota, 55760, see campground map (attachment 1). All electrical w ork shall conform to the (2008) National Electric Code (NEC) and the (2007) National Electric Safety Code (NESC).
This is a set aside for Hub Zone. The associated NAICS code is 238210 w ith a $14.0 million small business size standard.
PATRICK J MALLY 651 290-5723
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
17-Sep-2010
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________30 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________29 Sep 2010 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
USACE - ST PAUL
180 5TH STREET EAST
SUITE 700
ST. PAUL MN 55101-1678
W912ES
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
04:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
651-290-5706FAX:TEL: 651-290-5425 TEL: FAX:
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912ES-10-T-0105
Section SF 30 - BLOCK 14 CONTINUATION PAGE
SOW
1. General: The Scope Of Work (SOW) for this project is to replace current 30 amp campground pedestals at Sandy Lake Recreation area with 50 amp campground pedestals for campground sites; South Group camping, S-1 through S-21, North Group camping and N-2 through N-29, for a total of 60 campground pedestals;
South Group camping site, North Group camping site and sites S-15 through S-19 each have two (2) campground pedestals. Upgrade the electrical services as required for the installation of new 50 amp campground pedestals. Circuits for campground pedestals shall not be connected to any other equipment and shall be limited to six (6), 50-amp campground pedestals or less. Balance panelboard circuits for all electrical campground sites. For location of campground sites at the Sandy Lake Recreation Area, 22205 531st Lane, McGregor, Minnesota, 55760, see campground map (attachment 1). All electrical work shall conform to the (2008) National Electric Code (NEC) and the (2007) National Electric Safety Code
(NESC).
Note: Numbering of sites in this scope of work correspond to the numbering of sites on attachment 1.
1.1 Local Utility Company: The local utility company in the Sandy Lake area is Lake Country Power, point of contact is Carman Haglund, 1-800-421-9959, extension 2249.
2. Measurement and Payment: The payment provided for in the contract shall constitute full compensation for furnishing all materials and for performing all work under the contract in a complete and acceptable manner. The contract work shall include design, providing plant, equipment, tools, supplies, labor, supervision, incidental materials, quality control, environmental protection, testing and meeting safety requirements, and for performing all work required for which separate payment is not otherwise provided. Compensation for all work shown, specified, or essential to completion of the project (whether or not the specific material or operation is indicated) shall be included on the bidding schedule. The payment provided for in the contract includes compensation for all risk, loss, damage, and expense arising out of the nature of the work or its prosecution, subject to conditions of the contract. Payment for each contract line item will constitute full compensation for furnishing the materials and constructing the work complete in place as specified. Prior to submitting a bid, the Contractor shall verify all conductor distances. Adjustments to pricing shall not be made after contract award for conductor distances that differ from those estimated in this Scope of Work.
2.1 Unit Prices: Payment items for the work of this contract are listed in the BIDDING SCHEDULE and described below. The payment items provided for on the bidding schedule embody the majority of the work; but the work descriptions provided below do not specifically discuss all incidental work required to complete the contract work.
2.1.1 New Loop Conductors: All loop conductors shall be, one set of three (3) 250 MCM AL conductors with a #3/0 AL Ground minimum, unless otherwise required by the NEC or to reduce the voltage drop. Contractor shall calculate voltage drops. Voltage drop shall not exceed 5% from any campground pedestal to service transformer.
2.1.2 Existing Loop Modifications: Existing loop modifications will not be measured for payment. Payment will be made on a lump sum (LS) basis at the contract price and will constitute full compensation for all materials, labor, equipment and incidentals required for modification of the existing campground electrical service, equipment and loop conductors as required.
2.1.3 Electrical Design: The electrical design will not be
measured for payment. Payment will be made on a lump sum (LS) basis at the contract price and will constitute full compensation for all materials, labor, equipment and incidentals required for the electrical design for the Sandy Lake Recreation Area Campground service upgrades campground circuit balancing and campground pedestal upgrades.
2.1.4, South Meter (Acct # - 01 033 537), Campsites: South Group, S-21, S-20, S-19, S-18, S-17, S-16, S-15
All sites have two 30 amp pedestals and are double sites.
The South Meter also feeds a 20 amp electrical box on a post to service the irrigation pump.
New South Meter (Acct # - 01 033 537) Pedestals will be measured for payment by each pedestal supplied and mounted adjacent to the existing site pedestal. Payment will be made at the contract unit price for the provision of all materials, labor, equipment and incidentals for the satisfactory installation of each new pedestal supplied and mounted in place. The price bid shall include providing and mounting the new pedestals, all testing for proper operation of each pedestal, and removal and disposal of the replaced existing pedestals. Payment for connection of the pedestal to the new conductor shall be made under bid item:
Existing Loop Modification.
2.1.5, Comfort Station Meter (Acct # - 01 024 740), Campsites:
S-14, S-13, S-12, S-11, S-10, S-9
All sites have 30 amp pedestals. There are four ST sites which are tent sites and have 20 amp pedestals which are to remain. The Comfort Station Meter also feeds the following facilities:
Comfort Station: 200 amp Fish Cleaning Station: 30 amp
Comfort Station Meter (Acct # - 01 024 740) Pedestals will be measured for payment by each pedestal supplied and mounted adjacent to the existing site pedestal. Payment will be made at the contract unit price for the provision of all materials, labor, equipment and incidentals for the satisfactory installation of each new pedestal supplied and mounted in place.
The price bid shall include providing and mounting the new pedestals, all testing for proper operation of each pedestal, and removal and disposal of the replaced existing pedestals. Payment for connection of the pedestal to the new conductor shall be made under bid item: Existing Loop Modification.
2.1.6, Pump House Meter (Acct # - 01 225 228), Campsites: S-1, S-2, S-3, S-4, S-5, S-6, S-7, S-8
All sites have 30 amp pedestals. The Pump House Meter also feeds the following facilities:
Dam: 20 amp Pump House: 105 amp Gage House: 20 amp Office Building: 200 amp
Pump House Meter (Acct # - 01 225 228) Pedestals will be measured for payment by each pedestal supplied and mounted adjacent to the existing site pedestal. Payment will be made at the contract unit price for the provision of all materials, labor, equipment and incidentals for the satisfactory installation of each new pedestal supplied and mounted in place. The price bid shall include providing and mounting the new pedestals, all testing for proper operation of each pedestal, and removal and disposal of the replaced existing pedestals. Payment for connection of the pedestal to the new conductor shall be made under bid item:
Existing Loop Modification.
2.1.7, N23 Meter (Acct # - 01 028 737), Campsites: North Group, N-2, N-3, N-4, N-5, N-6, N-7, N-8, N-9, N-10, N-11, N-21, N-22, N-23
All sites have 30 amp pedestals. The N23 Meter does not feed any other facilities.
N23 Meter (Acct # - 01 028 737), Pedestals will be measured for payment by each pedestal supplied and mounted adjacent to the existing site pedestal. Payment will be made at the contract unit price for the provision of all materials, labor, equipment and incidentals for the satisfactory installation of each new pedestal supplied and mounted in place. The price bid shall include providing and mounting the new pedestals, all testing for proper operation of each pedestal, and removal and disposal of the replaced existing pedestals. Payment for connection of the pedestal to the new conductor shall be made under bid item:
Existing Loop Modification.
2.1.8, N17 Meter (Acct # - 01 028 427), Campsites: N-12, N-13, N-14, N-15, N-16, N-17, N-18, N-19, N-20, N-24, N-25, N-26, N-27, N-28, N-29
All sites have 30 amp pedestals. The N17 Meter also feeds the following facilities:
Men’s Toilet: 20 amp Lady’s Toilet: 20 amp Cabin: 50 amp
N17 Meter (Acct # - 01 028 427), Pedestals will be measured for payment by each pedestal supplied and mounted adjacent to the existing site pedestal. Payment will be made at the contract unit price for the provision of all materials, labor, equipment and incidentals for the satisfactory installation of each new pedestal supplied and mounted in place. The price bid shall include providing and mounting the new pedestals, all testing for proper operation of each pedestal, and removal and disposal of the replaced existing pedestals. Payment for connection of the pedestal to the new conductor shall be made under bid item:
Existing Loop Modification.
3. Site Visit. Contractors are encouraged to visit the site prior to bidding. Contact Jeff Steere at Sandy Lake Recreation Area (phone number (218) 426-3482).
4. Safety Plan. The Contractor shall submit a safety plan for performing the work. Safety plan shall be in conformance with the Safety and Health Requirements Manual, US Army Corps of Engineers EM 385-1-1 (latest edition). The manual shall be provided by the Corps. The safety plan shall be reviewed by the Corps and discussed at the initial pre-construction meeting to be held at the Crosslake site. The “Safety Plan” shall be approved prior to start of work. The web site for the 2008 “Safety and Health Requirements Manual”, USACE EM 385-1-1 (latest edition) is www.usace.army.mil/CESO/Pages/EM385-1-1,2008NEW!.aspx.
5. Schedule. All work shall be initiated by September 21, 2010 and completed by November 15, 2010. In addition, the campground area will remain functional during the construction.
6. Project Sign. Prior to commencement of work, the Contractor shall construct a project sign at the site of the work at a location directed by the Contracting Officer. The sign, which will identify the work with the Corps of Engineers, shall be 4 feet by 6 feet in size and shall conform to the requirements of the PROJECT SIGN drawing and installation instructions attached at the end of this section. The lettering for the 2 feet by 4 feet section of the sign with the Corps logo shall be white; all other lettering shall be black. Lettering for the project name shall be Helvetica Bold, all other lettering shall be Helvetica Regular. The sign coordinator is Mary Pizzuto @ 504.862.2000.
No separate payment will be made for construction and erection of the project sign and all costs in connection therewith will be considered an incidental obligation of the Contractor. Upon completion of the work, the sign shall become the property of the Contractor and shall be removed from the job site.
7. Power Outages to Campsites. To the maximum extent as possible, campsites shall remain energized. The contractor shall obtain approval from the Sandy Lake staff prior to de-energizing power to campsites. Power outages to campsites shall be kept to a minimum and not to exceed 2 days.
8. Minnesota One Call Excavation Notice System. For contract work performed within the State of Minnesota, the Contractor shall meet the requirements of Minnesota Statutes, Chapter 216D "One Call Excavation Notice System."
9. Electrical Design. Contractor shall submit a design that details the electrical installation. The electrical design shall be submitted within 14 calendar days of contract award. The “Electrical Design” shall be approved by the Contracting Officer prior to start of work and shall contain the following information:
a. Layout drawing of new electrical service.
b. New CT cabinets, meter socket, and electrical service equipment.
c. New panel boards.
d. New 50 amp pedestals.
e. New underground service conduit and wiring.
f. New distribution wiring and conduit.
g. Circuit runs and cable lengths.
h. Circuit voltage drop calculations.
10. Work Plan. Contractor shall submit a work plan that details the sequence and scheduling of the proposed work. The work plan shall be submitted within 10 days of “Electrical Design” approval. The work plan shall be discussed at the initial pre-construction meeting to be held at the Sandy Lake site. The “Work Plan” shall be approved prior to start of work.
11. Pavement Removal and Replacement. Where roads are cut, removed, or otherwise damaged in the prosecution of the work, the Contractor shall replace all pavements or other surfacing so removed or damaged to their preconstruction condition, unless otherwise specified or indicated. After backfill is completed on paved streets, a temporary surface shall be laid down and the street opened to the traffic in order to provide access to abutting property. Restoration of the original street surface construction shall be completed no later than 60-calendar days after starting excavation.
12. Shop Drawings. The work plan and safety plan shall be submitted as noted above. Both of these items shall be submitted prior to the pre-construction meeting. Other shop drawing submittals include the following:
a. Layout drawing of new electrical service.
b. New CT cabinets, meter socket, and electrical service equipment.
c. New panel boards.
d. New 50 amp pedestals.
e. New underground service conduit and wiring.
f. New distribution wiring and conduit.
13. Clean Up. Contractor shall be responsible for removal and disposal of all construction debris. Disposal of debris shall be off-site and meet all local and state codes.
14. Coordination. All work shall be coordinated with Jeff Steere at Sandy Lake Recreation Area.
15. Initial Meeting. A pre-construction meeting shall be held at Sandy Lake before commencing work. The safety plan, work plan, schedule, and coordination issues shall be discussed. The contractor shall submit the safety plan and work plan for review prior to the meeting.
16. Experience. Contractor shall be an experienced electrical contractor and licensed by the State of Minnesota.
17. Power. Electrical power is available, at the facility for Contractor’s use during construction; contact the Sandy Lake staff for use. Electricity provided shall be limited to that which is available without modification to the existing system.
18. Sanitary Facilities. Outdoor restrooms are available on site;
however, contractor is encouraged to provide his own sanitary facilities during construction.
19. Disposition of Removed Equipment and Material. All removed material and equipment shall become the property of the contractor unless otherwise directed by the Contracting Officer.
Material and equipment shall be disposed of per local, state and federal regulation. If a conflict exists among regulations, the more stringent shall take precedence.
Section 00010 - Solicitation Contract Form
NOTES TO OFFERORS
Notes to Quoters
1. EFFECTIVE MAY 31, 1998, ALL CONTRACTORS MUST REGISTER WITH THE DEFENSE
CENTRAL CONTRACTOR REGISTRATION (CCR) IN ORDER TO RECEIVE ANY CONTRACT AWARD.
(other than those made via the Government credit card program). Contractors may register on line at http://www.ccr.gov.
2. FACSIMILE OF QUOTES AND FACSIMILE OF MODIFICATIONS THERETO, WILL NOT
BE ACCEPTED.
3. All Quantities are estimated except where unit is given as "EA" (EACH) or "LS" (LUMP SUM).
4. The Awardee will be requested to provide the following information as soon as possible after quote opening:
a. A Financial Statement, to include a balance sheet and income statement, and
b. A Bank Certification of Financial Capability (line of credit).
This information will be treated as confidential. The financial statements should be not over 60 days old. If over 60 days old, a certification should be attached stating that the financial condition of the firm is substantially the same or, if not the same, the changes that have taken place.
5. All extensions of the unit prices shown will be subject to verification by the Government. In case of a discrepancy between the unit price and the extension, the unit price will govern.
6. The original Quotes and any modifications must be complete as to all the items on the schedule. Award will be made under FAR Part 13 to that Offeror whose offer is most advantageous to the Government, based on price, techincal and past performance. The techincal factor will be copies of contractors licence to do business in Minnesota and Licences of the Electicians. Offerors will be required to provide past performance information on recent (past 3 yrs) of relevant work of similar size and scope.
7. Unbalanced quotes. The government may reject as nonresponsive any quote that is materially unbalanced between contract line item numbers or sub-items on the quoteding schedule. A quote is materially unbalanced when it is based on prices that are significantly less than cost for some work and prices that are overstated, in relation to cost, for other work. A materially unbalanced quote may be rejected if the Contracting Officer has a reasonable doubt as to whether the quote will result in the lowest overall cost to the government even though it may be the low evaluated quote. Additionally, a quote that is so unbalanced so as to be tantamount to an advance payment will be rejected as nonresponsive even if acceptance of the quote would result in the lowest overall cost to the government.
8. Any prospective Offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing.
Questions can be faxed to the contract specialist at (651) 290-5723.
9. The addresses, phone numbers, and Internet address (if available) for references cited in these specifications are listed in the Corps of Engineer
Guide Specification (CEGS) 01090 SOURCES FOR REFERENCE PUBLICATIONS. CEGS 01090 is available on the TECHNIFO page of the Corps of Engineers Huntsville District Internet site at: http://w2.hnd.usace.army.mil/.
10. Any forthcoming amendments will only be available on this web site. E-mail notifications will be sent upon issuance of any amendments to all registered firms. E-mail message notifications may not be reliable based on system constraints. It is therefore recommended that each registered firm check this web site periodically for updates. A paper hard copy of each amendment will not be mailed unless specifically requested in writing.
POC:
U.S. Army Corps of Engineers Attn: patrick mally, Contracting 180 5th St. East, Suite 700 St. Paul M 551014-1678
Fax: 651-290-5723
Email: patrick.j.mally@usace.army.mil
The U.S. Army Corps of Engineers as part of the Federal Government is tax-exempt. Federal Tax ID# 62-1642142.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lump Sum
ELECTRICAL UPGRADE
FFP
SANDY LAKE RECREATION AREA ELECTRICAL UPGRADE FROM 30 TO
50 AMP SERVICE. SEE SOW FOR MORE DETAILED INFO ON WORK.
FOB: Destination
MILSTRIP: W81G6702115671
PURCHASE REQUEST NUMBER: W81G6702115671
NET AMT
Section 00100 - Bidding Schedule/Instructions to Bidders
CLAUSES INCORPORATED BY FULL TEXT
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)
Offers submitted in response to this solicitation shall be in the English language. Offers received in other than English shall be rejected.
(End of provision)
52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)
Offers submitted in response to this solicitation shall be in terms of U.S. dollars. Offers received in other than U.S.
dollars shall be rejected.
52.214-4002 ALL OR NONE QUALIFICATIONS (APR 1984) FAR 14.404-5
A bidder/offeror must quote on all items in this solicitation to be eligible for award. The Government will award on a “All or None” basis. Evaluation of bids/offers will be based, among other factors, upon the total price quoted for all items.
52.222-5 DAVIS-BACON ACT--SECONDARY SITE OF THE WORK (JUL 2005)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Davis-Bacon Act, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
52.222-8 PAYROLLS AND BASIC RECORDS (JUN 2010)
(a) Payrolls and basic records relating thereto shall be maintained by the Contractor during the course of the work and preserved for a period of 3 years thereafter for all laborers and mechanics working at the site of the work. Such records shall contain the name, address, and social security number of each such worker, his or her correct classification, hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in section 1(b)(2)(B) of the Davis-Bacon Act), daily and weekly number of hours worked, deductions made, and actual wages paid. Whenever the Secretary of Labor has found, under paragraph (d) of the clause entitled Davis-Bacon Act, that the wages of any laborer or mechanic include the amount of any costs reasonably anticipated in providing benefits under a plan or program described in section 1(b)(2)(B) of the Davis-Bacon Act, the Contractor shall maintain records which show that the commitment to provide such benefits is enforceable, that the plan or program is financially responsible, and that the plan or program has been communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated or the actual cost incurred in providing such benefits. Contractors employing apprentices or trainees under approved programs shall maintain written evidence of the registration of apprenticeship programs and certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs.
(b)(1) The Contractor shall submit weekly for each week in which any contract work is performed a copy of all payrolls to the Contracting Officer. The payrolls submitted shall set out accurately and completely all of the information required to be maintained under paragraph(a) of this clause, except that full social security numbers and home addresses shall not be included on weekly transmittals. Instead the payrolls shall only need to include an individually identifying number for each employee (e.g., the last four digits of the employee's social security number). The required weekly payroll information may be submitted in any form desired. Optional Form WH-347 is available for this purpose and may be obtained from the U.S. Department of Labor Wage and Hour Division website at http://www.dol.gov/whd/forms/wh347.pdf. The Prime Contractor is responsible for the submission of copies of payrolls by all subcontractors. Contractors and subcontractors shall maintain the full social security number and current address of each covered worker, and shall provide them upon request to the Contracting Officer, the Contractor, or the Wage and Hour Division of the Department of Labor for purposes of an investigation or audit of compliance with prevailing wage requirements. It is not a violation of this section for a Prime Contractor to require a subcontractor to provide addresses and social security numbers to the Prime Contractor for its own records, without weekly submission to the Contracting Officer.
(2) Each payroll submitted shall be accompanied by a "Statement of Compliance," signed by the Contractor or subcontractor or his or her agent who pays or supervises the payment of the persons employed under the contract and shall certify--
(i) That the payroll for the payroll period contains the information required to be maintained under paragraph (a) of this clause and that such information is correct and complete;
(ii) That each laborer or mechanic (including each helper, apprentice, and trainee) employed on the contract during the payroll period has been paid the full weekly wages earned, without rebate, either directly or indirectly, and that no deductions have been made either directly or indirectly from the full wages earned, other than permissible deductions as set forth in the Regulations, 29 CFR Part 3; and
(iii) That each laborer or mechanic has been paid not less than the applicable wage rates and fringe benefits or cash equivalents for the classification of work performed, as specified in the applicable wage determination incorporated into the contract.
(3) The weekly submission of a properly executed certification set forth on the reverse side of Optional Form WH- 347 shall satisfy the requirement for submission of the "Statement of Compliance" required by subparagraph (b)(2) of this clause.
(4) The falsification of any of the certifications in this clause may subject the Contractor or subcontractor to civil or criminal prosecution under Section 1001 of Title 18 and Section 3729 of Title 31 of the United States Code.
(c) The Contractor or subcontractor shall make the records required under paragraph (a) of this clause available for inspection, copying, or transcription by the Contracting Officer or authorized representatives of the Contracting Officer or the Department of Labor. The Contractor or subcontractor shall permit the Contracting Officer or representatives of the Contracting Officer or the Department of Labor to interview employees during working hours on the job. If the Contractor or subcontractor fails to submit required records or to make them available, the Contracting Officer may, after written notice to the Contractor, take such action as may be necessary to cause the suspension of any further payment. Furthermore, failure to submit the required records upon request or to make such records available may be grounds for debarment action pursuant to 29 CFR 5.12.
(End of clause)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (FEB 1999)
(a) Segregated facilities, as used in this clause, means any waiting rooms, work areas, rest rooms and wash rooms, restaurants and other eating areas, time clocks, locker rooms and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing facilities provided for employees, that are segregated by explicit directive or are in fact segregated on the basis of race, color, religion, sex, or national origin because of written or oral policies or employee custom. The term does not include separate or single-user rest rooms or necessary dressing or sleeping areas provided to assure privacy between the sexes.
(b) The Contractor agrees that it does not and will not maintain or provide for its employees any segregated facilities at any of its establishments, and that it does not and will not permit its employees to perform their services at any location under its control where segregated facilities are maintained. The Contractor agrees that a breach of this clause is a violation of the Equal Opportunity clause in this contract.
(c) The Contractor shall include this clause in every subcontract and purchase order that is subject to the Equal Opportunity clause of this contract.
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
2.2 6.9
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is MN, Aitkin Co, Sandy Lake
52.222-25 AFFIRMATIVE ACTION COMPLIANCE (APR 1984)
The offeror represents that
(a) [ ] it has developed and has on file, [ ] has not developed and does not have on file, at each establishment, affirmative action programs required by the rules and regulations of the Secretary of Labor (41 CFR 60-1 and 60-2), or
(b) [ ] has not previously had contracts subject to the written affirmative action programs requirement of the rules and regulations of the Secretary of Labor.
52.222-26 EQUAL OPPORTUNITY (MAR 2007)
(a) Definition. United States, as used in this clause, means the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.
(b)(1) If, during any 12-month period (including the 12 months preceding the award of this contract), the Contractor has been or is awarded nonexempt Federal contracts and/or subcontracts that have an aggregate value in excess of $10,000, the Contractor shall comply with this clause, except for work performed outside the United States by employees who were not recruited within the United States. Upon request, the Contractor shall provide information necessary to determine the applicability of this clause.
(2) If the Contractor is a religious corporation, association, educational institution, or society, the requirements of this clause do not apply with respect to the employment of individuals of a particular religion to perform work connected with the carrying on of the Contractor's activities (41 CFR 60-1.5).
(c) (1) The Contractor shall not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. However, it shall not be a violation of this clause for the Contractor to extend a publicly announced preference in employment to Indians living on or near an Indian reservation, in connection with employment opportunities on or near an Indian reservation, as permitted by 41 CFR 60-1.5.
(2) The Contractor shall take affirmative action to ensure that applicants are employed, and that employees are treated during employment, without regard to their race, color, religion, sex, or national origin. This shall include, but not be limited to, (i) employment, (ii) upgrading, (iii) demotion, (iv) transfer, (v) recruitment or recruitment advertising, (vi) layoff or termination, (vii) rates of pay or other forms of compensation, and (viii) selection for training, including apprenticeship.
(3) The Contractor shall post in conspicuous places available to employees and applicants for employment the notices to be provided by the Contracting Officer that explain this clause.
(4) The Contractor shall, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, or national origin.
(5) The Contractor shall send, to each labor union or representative of workers with which it has a collective bargaining agreement or other contract or understanding, the notice to be provided by the Contracting Officer advising the labor union or workers' representative of the Contractor's commitments under this clause, and post copies of the notice in conspicuous places available to employees and applicants for employment.
(6) The Contractor shall comply with Executive Order 11246, as amended, and the rules, regulations, and orders of the Secretary of Labor.
(7) The Contractor shall furnish to the contracting agency all information required by Executive Order 11246, as amended, and by the rules, regulations, and orders of the Secretary of Labor. The Contractor shall also file Standard Form 100 (EEO-1), or any successor form, as prescribed in 41 CFR part 60-1. Unless the Contractor has filed within the 12 months preceding the date of contract award, the Contractor shall, within 30 days after contract award, apply to either the regional Office of Federal Contract Compliance Programs (OFCCP) or the local office of the Equal Employment Opportunity Commission for the necessary forms.
(8) The Contractor shall permit access to its premises, during normal business hours, by the contracting agency or the OFCCP for the purpose of conducting on-site compliance evaluations and complaint investigations. The Contractor shall permit the Government to inspect and copy any books, accounts, records (including computerized records), and other material that may be relevant to the matter under investigation and pertinent to compliance with Executive Order 11246, as amended, and rules and regulations that implement the Executive Order.
(9) If the OFCCP determines that the Contractor is not in compliance with this clause or any rule, regulation, or order of the Secretary of Labor, this contract may be canceled, terminated, or suspended in whole or in part and the
Contractor may be declared ineligible for further Government contracts, under the procedures authorized in Executive Order 11246, as amended. In addition, sanctions may be imposed and remedies invoked against the Contractor as provided in Executive Order 11246, as amended; in the rules, regulations, and orders of the Secretary of Labor; or as otherwise provided by law.
(10) The Contractor shall include the terms and conditions of this clause in every subcontract or purchase order that is not exempted by the rules, regulations, or orders of the Secretary of Labor issued under Executive Order 11246, as amended, so that these terms and conditions will be binding upon each subcontractor or vendor.
(11) The Contractor shall take such action with respect to any subcontract or purchase order as the contracting officer may direct as a means of enforcing these terms and conditions, including sanctions for noncompliance;
provided, that if the Contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of any direction, the Contractor may request the United States to enter into the litigation to protect the interests of the United States.
(c) Notwithstanding any other clause in this contract, disputes relative to this clause will be governed by the procedures in 41 CFR 60-1.1.
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to
(1) conditions bearing upon transportation, disposal, handling, and storage of materials;
(2) the availability of labor, water, electric power, and roads;
(3) uncertainties of weather, river stages, tides, or similar physical conditions at the site;
(4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
52.236-8 OTHER CONTRACTS (APR 1984)
The Government may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting:
Name: Jeff Steere Address:
Telephone: 218-426-3482
52.236-28 PREPARATION OF PROPOSALS--CONSTRUCTION (OCT 1997)
(a) Proposals must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a proposal must initial each erasure or change appearing on any proposal form.
(b) The proposal form may require offerors to submit proposed prices for one or more items on various bases, including--
(1) Lump sum price;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of paragraphs (b)(1) through (b)(3) of this provision.
(c) If the solicitation requires submission of a proposal on all items, failure to do so may result in the proposal being rejected without further consideration. If a proposal on all items is not required, offerors should insert the words “no proposal” in the space provided for any item on which no price is submitted.
(d) Alternate proposals will not be considered unless this solicitation authorizes their submission.
52.236-4002 WORK PERFORMED BY THE CONTRACTOR
The successful bidder must furnish the Contracting Officer within 10 days after the award, the items of work which he will perform with his own forces, the percentage of the total work this represents, and the estimated cost thereof. (See Section 00700, clause 52.236-1.
52.236-4005 UNAVAILABILITY OF UTILITY SERVICES
The responsibility shall be upon the Contractor to provide and maintain at its expense, adequate utilities for its use for construction and domestic consumption, and to install and maintain necessary connections and lines for same, but only at such locations and in such manner as may be approved by the Contracting Officer. Before final acceptance, temporary connections and lines installed by the Contractor shall be removed in a manner satisfactory to the Contracting Officer.
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil/
(End of provision
252.225-7031 SECONDARY ARAB BOYCOTT OF ISRAEL (JUN 2005)
(a) Definitions. As used in this provision--
(1) Foreign person means any person (including any individual, partnership, corporation, or other form of association) other than a United States person.
(2) United States means the 50 States, the District of Columbia, outlying areas, and the outer Continental Shelf as defined in 43 U.S.C. 1331.
(3) United States person is defined in 50 U.S.C. App. 2415(2) and means--
(i) Any United States resident or national (other than an individual resident outside the United States who is employed by other than a United States person);
(ii) Any domestic concern (including any permanent domestic establishment of any foreign concern); and
(iii) Any foreign subsidiary or affiliate (including any permanent foreign establishment) of any domestic concern that is controlled in fact by such domestic concern.
(b) Certification. If the offeror is a foreign person, the offeror certifies, by submission of an offer, that it--
(1) Does not comply with the Secondary Arab Boycott of Israel; and
(2) Is not taking or knowingly agreeing to take any action, with respect to the Secondary Boycott of Israel by Arab countries, which 50 U.S.C. App. 2407(a) prohibits a United States person from taking.
Section 00600 - Representations & Certifications
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (FEB 2009)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238210 .
(2) The small business size standard is $14,000,000.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the clause at 52.204-7, Central Contractor Registration, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the clause at 52.204-7 is not included in this solicitation, and the offeror is currently…