Amendment 0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 18Q0105_Amendment_0003.pdf | ||
| Amend-0002_Drawings.pdf | ||
| 18Q0105_Amend-0002_Submittal_Register.pdf | ||
| 18Q0105_Amend-0002_31_00_00.12_28.pdf | ||
| W912EF18Q0105_Amendment_0002.pdf | ||
| 18Q0105_Amend-0002_Section_00_01_15.00_28.pdf | ||
| Site_Visit_Attendees_18Q0105_MCL_Needle_Gate_Replacement.pdf | ||
| Site_Visit_Attendees_-_18R0025_LLA_Pintle_Heel.pdf | ||
| 18Q0105_Plans.pdf | ||
| W912EF18Q0105_MCL_Needle_Gate_Replacement.pdf | ||
| 18Q0105_Site_Visit_info_18Q0105.pdf | ||
| 18Q0105_Specs.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to include a secondary contract specialist, incorporate the revised w age determination WA85 and to extend the quote due date- From: 24 AUG 2018 @ 2pm PST To: 31 AUG 2018 @ 2pm PST
See Summary of Changes for details
1. CONTRACT ID CODE PAGE OF PAGES
1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Aug-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF18Q0105
X 9B. DATED (SEE ITEM 11)
03-Aug-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Aug-2018
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
CYNTHIA H JACOBSEN
201 N. THIRD AVE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:509-527-7209TEL:
JANI C LONG / CONTRACTING OFFICER
W912EF18Q0105
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 24-Aug-2018 05:00 PM to 31-Aug-2018 05:00 PM.
SECTION 00 21 00 - INSTRUCTIONS
The following have been modified:
This solicitation is a Request for Quotations (RFQ) under NAICS 237990 Other Heavy and Civil Engineering Construction
AWARD BASIS
Award will be made on the basis of lowest evaluated total price for all line items of the quotation schedule. Offeror is advised that only proposals submitted on a firm fixed price basis will be considered, and that proposals submitted on anything other than firm fixed price basis will be rejected.
Quotation is due no later than Friday, August 31, 2018 no later than 2pm PST (This instruction overrides the statement in Block Number 10 of Standard Form 18).
Quotation may be emailed (preferred) to: cynthia.h.jacobsen@usace.army.mil and kent.r.bernard@usace.army.mil, hand-delivered or mailed to: US Corps of Engineers, Attention: Contracting Division, Cynthia Jacobsen/Kent Bernard, 201 N. Third Ave, Walla Walla, WA 99362.
The resulting purchase order will be FOB Destination. Quoted price must include all shipping to destination and all Federal, State, and local taxes. Inspection and acceptance will be at destination.
OFFERORS are required to complete and submit the Standard Form 18, Bid Schedule, and Section 00 45 00, Representations and Certifications.
All work shall be in accordance with the specification, attachments, and all other terms and conditions herein.
This work is considered a construction project in excess of $2,000. The Davis Bacon Act applies. No laborer employed directly upon the site work shall receive less than the prevailing wage rates as determined by the Secretary of Labor and the wages specified in FAR Clause 52.222-6, Construction Wage Rate Requirements.
Wage Decision Number WA180085 WA85 as incorporated below.
IMPORTANT: Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required before the GSA Federal Service Desk (FSD) will activate the entity's registration. Go to https://www.gsa.gov/about-us/organization/federal-acquisition-service/office-of-systems-management/integrated-award-environment-iae/sam-update for more information.
CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY
In order to determine a contractor’s responsibility for purposes of contract award the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work.
(See the Attention to Bidders form included in this solicitation.) In accordance with FAR 9.104-1, to be determined responsible, a prospective contractor must –
(a) Have adequate financial resources to perform the contract, or the ability to obtain them;
(b) Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;
(c) Have a satisfactory performance record. (A prospective contractor shall not be determined responsible or non-responsible solely on the basis of a lack of relevant performance history except as provided in FAR 9.104-2);
(d) Have a satisfactory record of integrity and business ethics;
(e) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them;
(f) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and
(g) Be otherwise qualified and eligible to receive an award under applicable laws and regulations.
Bidder Inquiry
All inquiries regarding this solicitation are to be submitted via Bidder Inquiry. Telephone and email inquiries will not be accepted. Bidder Inquiry is a web-site that allows bidders to post questions regarding the solicitation and view all questions by other bidders and responses by USACE. Bidder Inquiry can be accessed through ProjNet at (https://www.projnet.org)
To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective vendor once the reply is available for viewing.
TIMING OF BIDDER INQUIRIES: Bidders are encouraged to submit their bidder inquiries promptly. The Government will make every effort to answer all bidder inquiries; however, the closer to the bid or proposal due date an inquiry is received, the less likely it is that a timely response can be provided.
The Bidder Inquiry Key is: CVDJM7-KTJCRX
Specific Instructions for ProjNet Bid Inquiry Access:
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Instructions for Entering Questions:
1. After you are logged in click on the "post new inquiry", it is on the left side of the window under the Word "Submit" a.) This is the window where you will enter your questions b.) Comment Classification: Click on the down arrow to the right of the words “Please select from below”, select “Public” c.) Discipline: This is where you select who this question should be directed to. Example; if the question is about an electrical drawing or specification select: “Electrical” from the pull down list.
d.) Sheet. Enter the sheet number of the drawing you are asking about.
e.) Detail. Enter the detail name of the detail shown on the drawing that you are asking about.
f.) Specification. Enter the Specification number and paragraph number.
g.) File. Use this if you are going to attach a pdf file.
h.) Question. Enter your question here.
Specific Instructions for Future ProjNet Bid Inquiry Access:
1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
For questions about the ProjNet Bidder Inquiry, please contact the Call Center help desk toll free at 1-800-428- HELP, which operates from 8AM to 5PM (Central US time zone). Bidder inquiry help questions can also be emailed to the helpdesk at staff@projnet.info
NOTICE: All bidders/offerors will be held to have reviewed the questions and responses in Bidder Inquiry prior to bid submission. Nothing is changed in the solicitation unless an amendment is issued.
The following have been modified:
WAGE DETERMINATION
General Decision Number: WA180085 08/10/2018 WA85
Superseded General Decision Number: WA20170085
State: Washington
Construction Type: Heavy including water and sewer line construction
County: Walla Walla County in Washington.
HEAVY CONSTRUCTION PROJECTS (including sewer/water construction).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.
Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/05/2018 1 02/23/2018 2 03/30/2018 3 06/29/2018 4 08/10/2018
ELEC0077-001 02/01/2013
Rates Fringes
Line Construction:
LINEMEN.....................$ 45.62 4%+12.90
* ELEC0112-014 06/01/2018
Rates Fringes
ELECTRICIAN......................$ 43.50 20.54
* ENGI0370-010 06/01/2018
Rates Fringes
POWER EQUIPMENT OPERATOR
GROUP 1.....................$ 27.51 15.95
GROUP 2.....................$ 27.83 15.95
GROUP 3.....................$ 28.44 15.95
GROUP 4.....................$ 28.60 15.95
GROUP 5.....................$ 28.76 15.95
GROUP 6.....................$ 29.04 15.95
GROUP 7.....................$ 29.31 15.95
GROUP 8.....................$ 30.41 15.95
ZONE DIFFERENTIAL (Add to Zone 1 rate): Zone 2 - $2.00
Zone 1: Within 45 mile radius of Spokane, Pasco, Washington;
Lewiston, Idaho
Zone 2: Outside 45 mile radius of Spokane, Pasco, Washington; Lewiston, Idaho
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Rollers, all types on subgrade, including seal and chip coatings
GROUP 2: Fork Lift
GROUP 3: Bulldozer (up to D-6 or equivalent)
GROUP 4: Loaders (overhead & front-end, under 4 yds. R/T);
Oiler; Drill (churn, core, calyx or diamond)
GROUP 5: Backhoe (Under 45,000 gw); Trackhoe/Excavator (under 3/4 yd.); Cranes (25 tons & under); Drilling equipment (8 unch bit and over) (robbins, reverse circulation and similar); Boom Truck (Under 25 tons)
GROUP 6: Asphalt Roller; Backhoe (45,000 gw and over to 110,000 gw); Trackhoe/Excavator (3/4 yd. to 3 yd.); Cranes (over 25 tons, to and including 45 tons), Bulldozer, 834 R/T & similar; Loader Operator (front-end & overhead, 4 yds. incl. 8 yds.); Mechanic
GROUP 7: Backhoe (Over 110,000); Trackhoe/Excavator (3 yds & over); Cranes (over 45 tons to but not including 85 tons);
Loaders (overhead & front-end, over 8 yds. to 10 yds.);
Grader/Blade
GROUP 8: Cranes (85 tons and over, and all climbing, overhead,rail and tower); Loaders (overhead and front-end, 10 yards and over)
BOOM PAY: (All Cranes, Including Tower) 180 ft to 250 ft $ .50 over scale Over 250 ft $ .80 over scale
NOTE:
In computing the length of the boom on Tower Cranes, they shall be measured from the base of the Tower to the point of the boom.
HAZMAT:
Anyone working on HAZMAT jobs, working with supplied air shall receive $1.00 an hour above classification.
IRON0014-001 07/01/2017
Rates Fringes
IRONWORKER (Reinforcing and Structural)......................$ 32.64 25.06
LABO0238-002 06/01/2018
Rates Fringes
LABORER (Spokane)
GROUP 1.....................$ 24.84 12.35
GROUP 2.....................$ 26.94 12.35
GROUP 3.....................$ 27.21 12.35
GROUP 4.....................$ 27.48 12.35
Zone Differential (Add to Zone 1 rates): Zone 2 - $2.00
BASE POINTS: Spokane, Pasco, Lewiston
Zone 1: 0-45 radius miles from the main post office.
Zone 2: 45 radius miles and over from the main post office
LABORERS CLASSIFICATIONS
GROUP 1: Flagger
GROUP 2: Common or General Laborer;
GROUP 3: Mason Tender-Cement/Concrete; Pipelayer; Chipping Guns
GROUP 4: Grade Checker
LABO0238-007 06/01/2018
Rates Fringes
Laborer, Mason Tender Brick......$ 26.94 12.35
* PAIN0005-003 07/01/2018
Rates Fringes
PAINTER (Brush, Roller, and Spray.)..........................$ 22.94 11.61
SUWA2009-051 08/07/2009
Rates Fringes
CARPENTER........................$ 24.03 6.50
CEMENT MASON/CONCRETE FINISHER...$ 17.21 0.00
LABORER: Landscape..............$ 14.67 0.00
TRUCK DRIVER: Dump Truck........$ 19.67 0.00
TRUCK DRIVER: Water Truck.......$ 24.36 8.30
TRUCK DRIVER: 10 Yard Truck.....$ 24.61 8.34
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
(End of Summary of Changes)