Amend_0003_Section_01_45_00.01_28.pdf
PDF 23 KB Posted
- Attached to
- Oil Flushing Federal contract opportunity
- Solicitation number
- W912EF-17-R-0018
About this file
Change to Section 01 45 00.01 28
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend_0003_Section_48_13_13.20_26.pdf | ||
| Amend_0003_Section_01_11_00.00_26.pdf | ||
| A.07.24._Amendment_0003.pdf | ||
| A.01.30_Technical_Specifications_(Amendment_0002).pdf | ||
| A.07.24_Solicitation_Amendment_(W912EF17R00180002).pdf | ||
| A.07.24._Solicitation_Amendment_0001.pdf | ||
| A.07.23._Atch_5_Wage_Det_2015-5511.docx | DOCX document | |
| A.07.23._Atch_1_PastPerformanceQuestionnaires.pdf | ||
| A.07.23._Solicitation.pdf | ||
| A.07.23._Atch_2_TechSpec.pdf | ||
| A.07.23._Atch_4_VOL_2_MNA_PLANS.PDF | ||
| A.07.23._Atch_6_Wage_Det_2015-5527.docx | DOCX document | |
| A.07.23._Atch_3_VOL_1_DWA_PLANS.PDF | ||
| A.07.23._Atch_7_Wage_Det_2015-5589.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Dworshak & McNary Lubrication Oil System Flushing W912EF-17-R-0018 Amend-0003
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 00.01 28
CONTRACTOR QUALITY CONTROL (SHORT FORM)
PART 1 GENERAL
1.1 SUBMITTALS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 CONTRACTOR QUALITY CONTROL (CQC) PLAN
3.1.1 Additional Requirement
3.2 CONTROL
3.2.1 Preparatory Phase
3.2.2 Initial Phase
3.2.3 Follow-up Phase
3.2.4 Additional Preparatory and Initial Phases
3.3 ORGANIZATION
3.4 SUBMITTALS
3.5 AS-BUILT DRAWINGS
3.6 DOCUMENTATION
3.7 NOTIFICATION OF NONCOMPLIANCE
ATTACHMENTS:
Sample of Quality Control Report, WWD-QCR (Rev Sep 85)
-- End of Section Table of Contents --
SECTION 01 45 00.01 28
SECTION 01 45 00.01 28
CONTRACTOR QUALITY CONTROL (SHORT FORM)
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. A designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Contractor Quality Control Plan; G ECC
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 CONTRACTOR QUALITY CONTROL (CQC) PLAN
Furnish for review by the Government, not later than 5 calendar days after receipt of Notice To Proceed, the Contractor Quality Control Plan proposed to implement the requirements of the clause entitled INSPECTION OF CONSTRUCTION of the CONTRACT CLAUSES. The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used.
The Government will consider an interim plan for the first 15 calendar days of operation. Construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the features of work included in an accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional features of work to be started.
3.1.1 Additional Requirement
The CQC System Manager shall have completed the course entitled "Construction Quality Management for Contractors" within the last five (5) years. This course will periodically be offered at various locations throughout the Pacific Northwest. For information concerning this course call your local Associated General Contractor's Plan Room.
3.2 CONTROL
Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. The controls shall be adequate to cover all construction operations, including both on-site and off-site fabrication, and shall be keyed to the proposed construction sequence. The controls shall include at least three (3) phases of control to be conducted by the CQC system manager for all definable features of work, as follows:
3.2.1 Preparatory Phase
This phase shall be performed prior to beginning work on each definable feature of work and shall include:
a. A review of each paragraph of applicable specifications.
b. A review of the contract plans.
c. A check to assure that all materials and/or equipment have been tested, submitted, and approved.
d. A check to assure that provisions have been made to provide required control inspection and testing.
e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.
f. A physical examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawing or submitted data, and are properly stored.
g. A review of the appropriate Activity Hazard Analysis to assure safety requirements are met.
h. Discussion of procedures for constructing the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that phase of work.
i. A check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.
j. The Government shall be notified at least 24 hours in advance of beginning any of the required action of the preparatory phase.
This phase shall include a meeting conducted by the CQC system manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. The results of the preparatory phase actions shall be documented by separate minutes prepared by the CQC System Manager and attached to the daily QC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.
3.2.2 Initial Phase
This phase shall be accomplished at the beginning of a definable feature of work. The following shall be accomplished:
a. A check of preliminary work to ensure that it is in compliance with contract requirements. Review minutes of the preparatory meeting.
b. Verification of full contract compliance. Verify required control inspection and testing.
c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with sample panels as appropriate.
d. Resolve all differences.
e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.
f. The Government shall be notified at least 24 hours in advance of beginning the initial phase. Separate minutes of this phase shall be prepared by the CQC system manager and attached to the daily CQC report. Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.
g. The initial phase shall be repeated for each new crew to work on-site, or any time acceptable specified quality standards are not being met.
3.2.3 Follow-up Phase
Daily inspections shall be performed to assure continuing compliance with contract requirements, including control testing, until completion of the particular feature of work. The inspections shall be made a matter of record in the CQC documentation. Final follow-up inspections shall be conducted and all deficiencies corrected prior to the start of additional features of work which may be affected by the deficient work. Do not build upon or conceal non-conforming work.
3.2.4 Additional Preparatory and Initial Phases
Additional preparatory and initial phases shall be conducted on the same definable features of work as determined by the Government if the quality of on-going work is unacceptable; or if there are changes in the applicable QC staff or in the on-site production supervision or work crew; or if work on a definable feature is resumed after a substantial period of inactivity;
or if other problems develop.
3.3 ORGANIZATION
Identify an individual within the organization at the site of the work who shall be responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor, including stoppage of work and removal of noncompliant work. The CQC System Manager shall be on the site at all times during construction, including during the work of subcontractors.
3.4 SUBMITTALS
The CQC organization shall be responsible for certifying that all submittals are in compliance with the contract requirements by signing the
ENG FORM 4025.
3.5 AS-BUILT DRAWINGS
Maintain working "as-built" contract drawings as required in SECTION
01 78 00.00 28 CLOSEOUT SUBMITTALS.
3.6 DOCUMENTATION
Maintain current records of quality control operations, activities, and tests performed, including the work of subcontractors and suppliers. These records shall be on form WWD-QCR, which is at the end of this SECTION, and shall include factual evidence that required quality control activities and/or tests have been performed, including but not limited to the following:
a. Contractor/subcontractor and their area of responsibility.
b. Operating plant/equipment with hours worked, idle, or down for repair.
c. Test and/or control activities performed with results and references to specifications/plan requirements. List deficiencies noted along with corrective action.
d. Job safety evaluations stating what was checked, results, and instructions or corrective actions.
e. List instructions given/received and conflicts in plans and/or specifications.
f. Contractor's verification statement on form WWD-QCR.
g. Work performed today, giving location, description, and by whom.
h. Material received with statement as to its acceptability and storage.
i. Identify submittals reviewed, with contract reference, by whom, and action taken.
j. These records shall indicate a description of trades working on the project; the number of personnel working; weather conditions encountered;
and any delays encountered. These records shall cover both conforming and deficient features and shall include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. The original and one (1) copy of these records in report form shall be furnished to the Government daily within 24 hours after the date(s) covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, one (1) report shall be prepared and submitted for every seven (7) calendar days of no work and on the last day of a no work period. All calendar days shall be accounted for throughout the life of the contract. The first report following a day of no work shall be for that day only. Reports shall be signed and dated by the CQC system manager. The report shall include copies of test reports and copies of reports prepared by all subordinate quality control personnel.
3.7 NOTIFICATION OF NONCOMPLIANCE
The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. After receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor at the site of the work, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order suspending or stopping all or part of the work until satisfactory corrective action has been taken.
Sample of Quality Control Report, WWD-QCR (Rev Sep 85) follows.
-- End of Section --
| PROJECT TABLE OF CONTENTS |
| DIVISION 01 - GENERAL REQUIREMENTS |
| 01 45 00.01 28 - CONTRACTOR QUALITY CONTROL SHORT FORM |
| CONTRACTOR QUALITY CONTROL SHORT FORM |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| PART 2 PRODUCTS NOT USED |
| PART 3 EXECUTION |
| 3.1 CONTRACTOR QUALITY CONTROL CQC PLAN |
| 3.1.1 Additional Requirement |
| 3.2 CONTROL |
| 3.2.1 Preparatory Phase |
| 3.2.2 Initial Phase |
| 3.2.3 Follow-up Phase |
| 3.2.4 Additional Preparatory and Initial Phases |
| 3.3 ORGANIZATION |
| 3.4 SUBMITTALS |
| 3.5 AS-BUILT DRAWINGS |
| 3.6 DOCUMENTATION |
| 3.7 NOTIFICATION OF NONCOMPLIANCE |