A.07.24_Solicitation_Amendment_(W912EF17R00180002).pdf
PDF 120 KB Posted
- Attached to
- Oil Flushing Federal contract opportunity
- Solicitation number
- W912EF-17-R-0018
About this file
Amendment 0002 to the solicitation. Change in CLINs and delivery dates.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A.07.24._Amendment_0003.pdf | ||
| Amend_0003_Section_48_13_13.20_26.pdf | ||
| Amend_0003_Section_01_45_00.01_28.pdf | ||
| Amend_0003_Section_01_11_00.00_26.pdf | ||
| A.01.30_Technical_Specifications_(Amendment_0002).pdf | ||
| A.07.24._Solicitation_Amendment_0001.pdf | ||
| A.07.23._Solicitation.pdf | ||
| A.07.23._Atch_2_TechSpec.pdf | ||
| A.07.23._Atch_5_Wage_Det_2015-5511.docx | DOCX document | |
| A.07.23._Atch_1_PastPerformanceQuestionnaires.pdf | ||
| A.07.23._Atch_4_VOL_2_MNA_PLANS.PDF | ||
| A.07.23._Atch_6_Wage_Det_2015-5527.docx | DOCX document | |
| A.07.23._Atch_3_VOL_1_DWA_PLANS.PDF | ||
| A.07.23._Atch_7_Wage_Det_2015-5589.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is as follow s (See attached):
Delete the follow ing CLINs & SubCLINS: 0002, 0002AA, 0002AB, 0003, 0003AA, 0003AB, 0004, 0004AA & 0004AB. Add the follow ing
CLINS: 0005, 0006, 0007 & 0008.
CLAUSES
1. Revised Clause 52.211-9 “DESIRED AND REQUIRED TIME OF DELIVERY” – revised period of performance.
SPECIFICATIONS
| 1. | Revised section 01 11 00.00 26 “SUMMARY OF WORK” |
| 2. | Revised section 01 11 00.00 28 “SUPPLEMENTARY REQUIREMENTS” |
| 3. | Revised section 48 13 13.02 26 “FLUSHING AND CLEANING OF LUBRICATING OIL SYSTEMS” |
1. CONTRACT ID CODE PAGE OF PAGES
1 14
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 07-Aug-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-17-R-0018
X 9B. DATED (SEE ITEM 11)
11-Jul-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
07-Aug-2017
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
ANDREW J SPRYS
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF-17-R-0018
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SUPPLIES OR SERVICES AND PRICES
CLIN 0001
The CLIN extended description has changed from:
Performance Period: 1 September 2017 to 31 October 2017 Line Item 0001, 0003 and 0004 shall be done in one contractor mobilization per project. Schedule work at each project, as coordinated with the COR
To:
Performance Period: 25 September 2017 to 22 December 2017. Schedule work at each project, as coordinated with the COR.
SUBCLIN 0001AA
Schedule work at each project, as coordinated with the COR
Schedule work at each project, as coordinated with the COR. All work must be completed by the end of the performance period. POP Sept 25-Oct 12, 2017
SUBCLIN 0001AB
Schedule work at each project, as coordinated with the COR
Schedule work at each project, as coordinated with the COR. All work must be completed by the end of the performance period. POP Nov 13-Dec 22, 2017
CLIN 0002
Performance Period: 1 September 2017 to 31 October 2017 Line Item 0001, 0003 and 0004
THE ENTIRE CLIN AND RELATED SUBCLINS ARE DELETED AND REPLACED WITH
CLIN 0005.
SUBCLIN 0002AA
The pricing detail quantity has decreased by 1.00 from 1.00 to 0.00.
SUBCLIN 0002AB
CLIN 0003
Performance Period: 1 September 2017 to 31 October 2017 Schedule work at each project, as
CLIN 0006.
SUBCLIN 0003AA
SUBCLIN 0003AB
CLIN 0004
Performance Period: 1 September 2017 to 31 October 2017 Line Item 0001, 0003 and 0004
CLIN 0007.
SUBCLIN 0004AA
SUBCLIN 0004AB
CLIN 0005 is added as follows:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005 1 Job
CLEAN MCNARY TRANSFORMER & LUBRICATING
FFP
OIL TANKS #1, #2, #3 and #6 Period of performance: Sept 18 - Oct 19, 2017.
Tank #1 and Tank #2 must be cleaned before Sep 25, 2017.
FOB: Destination
NET AMT
CLIN 0006 is added as follows:
0006 1 Job
CLEAN DWORSHAK CLEAN LUBRICATING OIL
FFP
TANK. POP: Oct 2-Oct 6, 2017. Schedule work to occur during the onsite high velocity flush at Dworshak.
CLIN 0007 is added as follows:
0007 1 Job
CLEAN MCNARY CLEAN LUBRICATING OIL TANK
FFP
#5 AND GRAVITY FEED LUBRICATING OIL TANK
Performance Period: Nov 13-Dec 22, 2017. Schedule work to occur during the onsite high velocity flush at McNary.
CLIN 0008 is added as follows:
0008 1 Job
CLEAN DWORSHAK DIRTY LUBRICATING OIL AND
FFP
CLEAN TRANSFORMER OIL TANKS. POP: Feb 15-Feb 28, 2018. Schedule work at each project, as coordinated with the COR.
DELIVERIES AND PERFORMANCE
The following Delivery Schedule item for SUBCLIN 0001AA has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
CONTRACTOR PERFORMANCE
SPECIALIST
DWORSHAK NATIONAL FISH
HATCHERY
276 DWORSHAK COMPLEX DRIVE
OROFINO ID 83544
208-476-1296
140261
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
POP 25-SEP-2017 TO
12-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
DWORSHAK PROJECT OFFICE
1428 NORTHFORK DRIVE
AHSAHKA ID 83520-0048
960201
The following Delivery Schedule item for SUBCLIN 0001AB has been changed from:
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT WHSE
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
960401
CAGE
POP 13-NOV-2017 TO
22-DEC-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT WHSE
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
The following Delivery Schedule item for SUBCLIN 0002AA has been changed from:
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
DWORSHAK PROJECT OFFICE
1428 NORTHFORK DRIVE
AHSAHKA ID 83520-0048
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
DWORSHAK PROJECT OFFICE
1428 NORTHFORK DRIVE
AHSAHKA ID 83520-0048
The following Delivery Schedule item for SUBCLIN 0002AB has been changed from:
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
960434
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
960434
The following Delivery Schedule item for SUBCLIN 0003AA has been changed from:
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
DWORSHAK PROJECT OFFICE
1428 NORTHFORK DRIVE
AHSAHKA ID 83520-0048
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
DWORSHAK PROJECT OFFICE
1428 NORTHFORK DRIVE
AHSAHKA ID 83520-0048
The following Delivery Schedule item for SUBCLIN 0003AB has been changed from:
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT WHSE
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT WHSE
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
The following Delivery Schedule item for SUBCLIN 0004AA has been changed from:
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
CONTRACTOR PERFORMANCE
SPECIALIST
DWORSHAK NATIONAL FISH
HATCHERY
276 DWORSHAK COMPLEX DRIVE
OROFINO ID 83544
208-476-1296
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
CONTRACTOR PERFORMANCE
SPECIALIST
DWORSHAK NATIONAL FISH
HATCHERY
276 DWORSHAK COMPLEX DRIVE
OROFINO ID 83544
208-476-1296
The following Delivery Schedule item for SUBCLIN 0004AB has been changed from:
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT WHSE
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
CAGE
POP 01-SEP-2017 TO
31-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT WHSE
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
The following Delivery Schedule for CLIN 0005 has been added:
POP 18-SEP-2017 TO
19-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT WHSE
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
The following Delivery Schedule for CLIN 0006 has been added:
CAGE
POP 02-OCT-2017 TO
06-OCT-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
DWORSHAK PROJECT OFFICE
1428 NORTHFORK DRIVE
AHSAHKA ID 83520-0048
The following Delivery Schedule for CLIN 0007 has been added:
CAGE
POP 13-NOV-2017 TO
22-DEC-2017
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
MCNARY PROJECT WHSE
82790 DEVORE ROAD
UMATILLA OR 97882-1230
541-922-1355
The following Delivery Schedule for CLIN 0008 has been added:
CAGE
POP 15-FEB-2018 TO
28-FEB-2018
N/A ARMY CORPS OF ENGINEERS
PERFORMANCE SPECIALIST
DWORSHAK PROJECT OFFICE
1428 NORTHFORK DRIVE
AHSAHKA ID 83520-0048
INSPECTION AND ACCEPTANCE
The following Acceptance/Inspection Schedule was added for CLIN 0005:
INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
Destination Government Destination Government
The following Acceptance/Inspection Schedule was added for CLIN 0006:
The following Acceptance/Inspection Schedule was added for CLIN 0007:
The following Acceptance/Inspection Schedule was added for CLIN 0008:
TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Past Performance
Questionnaire
4 06-JUL-2017
Attachment 2 Technical Specifications 111 06-JUL-2017 Attachment 3 McNary Plans 10 06-JUL-2017 Attachment 4 Dworshak Plans 12 06-JUL-2017 Attachment 5 Wage Determination
2015-5511
18 17-JAN-2017
Attachment 6 Wage Determination 2015-5527
18 12-JAN-2017
Attachment 7 Wage Determination 2015-5589
18 15-JUN-2017
to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 1 Amended Specifications
(Amendment 0002)
The following have been added by full text:
52.211-9 DESIRED AND REQUIRED TIME OF DELIVERY (JUN 1997)
(a) The Government desires delivery to be made according to the following schedule:
DESIRED DELIVERY SCHEDULE
PROJECTS/DESTINATIONS
McNary Dam US Army Corps of Engineers 82790 Devore Road Umatilla, Oregon 97882
Dworshak Dam US Army Corps of Engineers North Fork Drive, Ahsahka, Idaho 83520-0048
CLIN 0001 HIGH VELOCITY FLUSH
CLIN 0001AA Dworshak Period of performance (POP): Sept 25-Oct 12, 2017 CLIN 0001AB McNary POP Nov 13-Dec 22, 2017
- Schedule work at each project, as coordinated with the COR. All work must be completed by the end of the performance period.
CLIN 0005 CLEAN MCNARY TRANSFORMER & LUBRICATING OIL TANKS #1, #2, #3
and #6 Period of performance: Sept 18 - Oct 19, 2017
- Tank #1 and Tank #2 must be cleaned before Sep 25, 2017.
- FOB: Destination
CLIN 0006 CLEAN DWORSHAK CLEAN LUBRICATING OIL TANK
Period of performance: Oct 2-Oct 6, 2017
- FFP
- Schedule work to occur during the onsite high velocity flush at Dworshak
CLIN 0007 CLEAN MCNARY CLEAN LUBRICATING OIL TANK #5 AND GRAVITY FEED
LUBRICATING OIL TANK
Period of performance: Nov 13-Dec 22, 2017
- FFP
- Schedule work to occur during the onsite high velocity flush at McNary
CLIN 0008 CLEAN DWORSHAK DIRTY LUBRICATING OIL AND CLEAN TRANSFORMER
OIL TANKS
Period of performance: Feb 15-Feb 28, 2018
- FFP
- Schedule work at each project, as coordinated with the COR