Mill Creek levee Maintenance Phase II W912EF-16-B-0013
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 28 GENERAL REQUIREMENTS
01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS
01 14 00.10 28 PROJECT SITE RESTRICTIONS
01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY
(OPSEC)
01 22 00.00 28 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.01 28 CONTRACTOR QUALITY CONTROL
01 45 02.00 28 QUALITY CONTROL SYSTEM (QCS)
01 51 00.00 28 TEMPORARY UTILITIES
01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS
01 57 20.00 28 ENVIRONMENTAL PROTECTION
01 78 00.00 28 CLOSEOUT SUBMITTALS
DIVISION 31 - EARTHWORK
31 00 00.00 28 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 17.00 28 FLEXIBLE PAVEMENT REPAIR
32 15 00.00 28 AGGREGATE SURFACE COURSE
32 92 19.00 28 SEEDING AND SOD PLACEMENT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
This page intentionally left blank
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/
Army Wounded Warrior Program -http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material http://www.whitehouse.gov/sites/default/files/docs/white_house _business_council_-_guide_to_hiring_veterans_0.pdf
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 FIELD VERIFICATION OF SITE CONDITIONS
1.4 DEFINITIONS
1.5 PROJECT SCHEDULE
1.6 REGULAR CLEANUP AND DEBRIS DISPOSAL
1.7 EQUIPMENT LIST
1.8 TESTING OF EQUIPMENT
1.9 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.10 PRE-WORK AND POST WORK SURVEYS
1.11 FIRE CONTROL
1.12 PROJECT SUPERINTENDENT
1.13 KEY PERSONNEL SUBSTITUTION
1.14 POST AWARD MEETINGS
1.14.1 Pre-Work/Pre-Construction
1.14.2 Pre-Construction
1.14.2.1 Minutes
1.15 WEEKLY PRODUCTION MEETINGS
1.15.1 Minutes
1.16 ADDITIONAL MEETINGS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
ATTACHMENTS:
Weekly Meeting Agenda Template
-- End of Section Table of Contents --
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
Comply with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only.
Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
ALL SUBMITTALS ARE REQUIRED FOR EACH TASK ORDER.
SD-01 Preconstruction Submittals
Project Schedule; G C
Equipment List; I C
Pre-Work Survey Photos And Report; I C
Project Superintendent; I C
SD-07 Certificates
Key Personnel Substitution; G C
SD-11 Closeout Submittals
Post-Work Survey Photos And Report; I C
1.3 FIELD VERIFICATION OF SITE CONDITIONS
Field verify all elevations, dimensions, and coordinates of existing features indicated on the contract drawings that affect new construction.
Any deviations shall be updated as per SECTION 01 78 00.00 28, CLOSEOUT
SUBMITTALS, paragraph MAINTAIN WORKING AS-BUILT CONTRACT DRAWINGS AND FIO
DRAWINGS.
1.4 DEFINITIONS
a. Qualified Person.
As defined in EM 385-1-1 ; "DEFINITIONS", unless otherwise specified.
b. F.O.B.
An abbreviation for free on board, which means that a vendor or consignor will deliver goods on a railroad car, truck, vessel, or other conveyance without any expense to the purchaser or consignee.
1.5 PROJECT SCHEDULE
a. Furnish a schedule for the complete project in accordance with Clause 52.236-15 Schedules for Construction Contracts within 15 days after receipt of Notice to Proceed.
b. Provide two (2) sets of data CD's containing the Project Schedule in the original format the schedule was developed in (e.g. .xer, .xls., .mpp, etc.). Label each CD indicating the full contract number, data date and file name. Each schedule shall have a unique file name as determined by the Contractor. In addition to CD submittals, e-mail a copy of the current schedule to the Contracting Officer's Representative.
1.6 REGULAR CLEANUP AND DEBRIS DISPOSAL
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials shall become the property of the Contractor and shall be removed from the job site daily in accordance with Federal, State, and local regulations. Furnish waste containers. All waste containers provided by the Contractor shall be emptied daily.
1.7 EQUIPMENT LIST
Furnish a complete list of all equipment to be used on the Project 30 days prior to commencement of on-site work. Submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the Project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.8 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it shall be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks shall be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1 .
Equipment shall be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
1.9 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Reference FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984).
1.10 PRE-WORK AND POST WORK SURVEYS
Conduct a pre-work survey prior to start of on-site work and a post-work survey during project closeout, with the Contracting Officer Representative, of the Government facilities at the work areas. The results of the surveys shall be documented by digital photographs and descriptive narrative reports. A color copy of the survey photographs and narrative reports shall be submitted to the Contracting Officer within five (5) days after survey has been completed.
1.11 FIRE CONTROL
Each piece of internal combustion engine driven equipment used at the work site shall be equipped with a fire extinguisher in accordance with recommendation National Fire Protection Association (NFPA) as appropriate. The minimum approved rating of extinguishers shall not be less than 5-B:C.
1.12 PROJECT SUPERINTENDENT
At all times during performance of this contract and until the work is completed and accepted, assign and have on the worksite, a competent superintendent as per FAR Clause 52.236-6 "Superintendence by the Contractor". Submit Superintendent name and contact information prior to start of on-site construction.
1.13 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (Project Superintendent, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer. Personnel shall possess the qualifications that meet or exceed those stated in the specifications for the position of the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement.
1.14 POST AWARD MEETINGS
1.14.1 Pre-Work/Pre-Construction
A combined Pre-Work/Pre-Construction Meeting will be held within 15 calendar days after receipt of Notice to Proceed. Attend the Pre-Work/ Pre-Construction Meeting. Senior level members of the Contractor's staff and the Contractor's Project Superintendent and QC system manager shall attend this meeting. The Government will lead the first portion of the meeting and take the meeting minutes. The Government will discuss the overall contract requirements.
1.14.2 Pre-Construction
For the Pre-Construction part of the meeting, the Project Superintendent shall lead the meeting and discuss the Contractor's plan on executing the work at the Project site, schedule, required clearances and timeframe for clearances, and plan for implementing safety and quality control. The Government will have key members from the Project staff to discuss Environmental and clearance issues for the Project.
1.14.2.1 Minutes
The Project Superintendent shall be responsible for taking the meeting minutes for this portion of the meeting and shall send them electronically within 48 hours after the meeting to the Government's Contracting Officer, Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.15 WEEKLY PRODUCTION MEETINGS
During all onsite construction work the Project Superintendent shall lead a weekly production meeting using the attached "Weekly Meeting Agenda Template" to brief the Government on the status of the project. All elements listed in the agenda shall be thoroughly discussed. For example, the Project Superintendent shall provide the Government a three (3) week "look-ahead" that describes all the planned construction activities, onsite and offsite, over the next three (3) weeks. These activities shall align to the overall construction schedule submitted under SECTION 01 11 01.00 28SUPPLEMENTARY REQUIREMENTS, and if the three (3) week "look-ahead" differs from the construction schedule, the construction schedule shall be updated to include these changes by the next scheduled update. Key members of the Contractor's staff shall attend this meeting, including the Quality Control System Manager, who is responsible for discussing QC aspects of the work as outlined under SECTION 01 45 00.01 28 CONTRACTOR QUALITY CONTROL and Site Safety and Health Officer (SSHO). The Government reserves the right to require any person from the Contractor's staff, such as the Project Manager, Engineer, scheduler, etc., or key subcontractor personnel to attend this meeting, if Government feels their participation is required.
1.15.1 Minutes
The Project Superintendent shall be responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.16 ADDITIONAL MEETINGS
Record the minutes of all meetings, including all conference calls, that occur between the Contractor and Government. Send minutes electronically within 24 hours of the meeting to the Contracting Officer for concurrence.
E-mail subject line shall include project name and meeting topic.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
Weekly Meeting agenda template
Schedule - Work scheduled over the next week Three week look ahead Overall Schedule Review
Submittals Review- Submittal Register Submittals approved by QC Outstanding Submittals RFI’s Letters
Coordination - Clearances required over the next week, include the following:
A description of the work to be performed under the Clearance.
Determine the correct energy isolation points needed to perform the work safely.
Physical barriers, protective grounds, piping blanks, or bulkheads that shall be used, including locations.
Determine the procedure and method of testing for stored energy if applicable.
The date and time the Clearance shall be required.
The estimated length of time the system or equipment shall be out of service and the time to return the system or equipment to service in an emergency.
Coordination issues
Safety- Review of AHA’s for ongoing work Pending AHA’s
Required for new work Status of Gov’t approval
Safety issues
QC -
Preparatory meetings Held over last week- status of meeting minutes
Required over the next week Initial meetings over the next week Follow up over the next week Rework list Review Deficiency tracking log
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 WORK SEQUENCE
1.3 PROJECT SECURITY
1.3.1 Vehicle Access
1.3.2 Identification of Employees
1.4 FACILITY OCCUPANCY CLOSURE
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
Responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 WORK SEQUENCE
Work zones, as indicated, shall be completed in the following sequence:
Zone A, then Zone B, Zone C, Zone D, Zone E, Zone F. Begin work in each zone at the downstream end, and complete each zone at the upstream end.
Work may progress into the next zone in sequence from the previous zone, as part of a single task order, but no zone may be skipped in the sequence.
1.3 PROJECT SECURITY
Weapons, alcohol, and illegal drugs are not allowed on the project site.
1.3.1 Vehicle Access
Only Contractor's work vehicles and equipment that are essential to the conduct of the work will be allowed in the work areas. All Contractor vehicles shall display suitable permanent or temporary identification.
1.3.2 Identification of Employees
Every Contractor employee (prime or subcontractor) shall have a hard hat meeting the requirements of EM 385-1-1 . Hardhat's shall display the Prime Contractor name, subcontractor name, and the employee's name. Contractor employee hardhat's shall not be white with red markings.
1.4 FACILITY OCCUPANCY CLOSURE
Provide 15 days advance notice to the Contracting Officer prior to closure of streets, walks, and other facilities at the project site.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used) -- End of Section --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
1.1 SUBMITTALS
1.2 Anti-Terrorism (AT) Awareness LEVEL 1 TRAINING
1.3 SUSPICIOUS ACTIVITY REPORTING TRAINING
1.4 PRE-SCREEN EMPLOYEES USING E-VERIFY PROGRAM
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS: This contract does not require access to or handling of classified material.
This contract does not require access to secured and restricted areas, sensitive information, or equipment.
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. The designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
In additional to the initial task order the following submittals shall be submitted again no later than 30 days prior to commencement of on-site work for every subsequent awarded task order.
SD-01 Preconstruction Submittals
Anti Terrorism (AT) Level 1; I, SLE
Suspicious Activity Reporting Training; I, SLE
Pre-Screen Employees Using E-Verify Program; I, SLE
1.2 Anti-Terrorism (AT) Awareness LEVEL 1 TRAINING
Access to USACE work sites requires the completion of the Anti Terrorism (AT) Level 1 Awareness training within thirty (30) days after Notice to Proceed and annually thereafter until project completion. Submit certificates of completion for each employee, this includes all sub contractor employees, to the Contracting Officer within five (5) calendar days after initial completion of training or annual refresher. Retain employee training certificates for the duration of the contract and maintain a current roster of those who have completed the training and the most recent date that the training was completed. Submit an updated roster to the Contracting Officer no later than five (5) calendar days after completion of refresher training or a new employee completes certification. AT Level I Awareness training can be completed in approximately two (2) hours and is available at the following website shown below:
a. AT Level I Awareness training:
Website: http://jko.jten.mil/courses/atl1/launch.html .
1.3 SUSPICIOUS ACTIVITY REPORTING TRAINING
All Contractor employees, including all sub contractor employees that will be on the work site, shall complete one of the following training's on the suspicious activity reporting program: iWATCH, CORPS WATCH, SEE SOMETHING, SAY SOMETHING. The links to the training sites are below. This training informs about the types of behavior to watch for and instructions to report suspicious activity to the security representative. Complete this training within thirty (30) calendar days of Notice to Proceed and within thirty (30) calendar days of new employees, this includes all sub contractor employees, commencing performance. Report results to the Contracting Officer no later than five (5) calendar days after the completion of the training.
a. iWATCH \ Website:
http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx
b. CORPS WATCH Website:
http://www.spa.usace.army.mil/Missions/CivilWorks/Recreation/CorpsWatch.aspx
c. SEE SOMETHING, SAY SOMETHING Website: https://www.dhs.gov/see-something-say-something
1.4 PRE-SCREEN EMPLOYEES USING E-VERIFY PROGRAM
Pre-screen employees, this includes all sub contractor employees, using the E-verify Program referenced below to meet the established eligibility requirements. Ensure that each employee has two valid forms of Government issued identification prior to enrollment. An initial list of verified and eligible employees must be provided to the Contracting Officer no later than three (3) business days after the initial contract award. Contracts with individuals use Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.
a. US Citizenship and Immigration Services Website: http://www.uscis.gov/e-verify
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 ESTIMATED CUT AND FILL QUANITY
1.2 ITEMS 0001, 1001, 2001, 3001 AND 4001 LEFT BANK LEVEE ALIGNMENT
STAGING
1.3 ITEMS 0002, 1002, 2002, 3002 AND 4002 ZONE A STA 0+00 TO 27+75
1.3.1 Items Ending In AA, BA And CA For Grubbing
1.3.2 Items Ending In AB, BB And CB For Excavation And Fill Placement
1.3.3 Items Ending In AC, BC And CC For Gravel Roadway Placement
1.3.4 Items Ending In AD, BD And CD For Hydroseeding
1.4 ITEMS 0003, 1003, 2003, 3003 and 4003 FOR ZONE B STA 27+75 TO 37+50
1.4.1 Items ending in AA For Grubbing
1.4.2 Items Ending In AB for Excavation And Fill Placement
1.4.3 Items Ending In AC For Gravel Roadway Placement
1.4.4 Items Ending In AD For Hydroseeding
1.5 ITEMS 0004, 1004, 2004, 3004 And 4004 FOR ZONE C STA 37+75 TO 47+00
1.5.1 Items Ending In AA For Grubbing
1.5.2 Items Ending In AB for Excavation And Fill Placement
1.5.3 Items Ending In AC For Gravel Roadway Placement
1.5.4 Items Ending In AD For Hydroseeding
1.6 ITEMS 0005, 1005, 2005, 3005 AND 4005 LEFT BANK LEVEE ALIGNMENT
AS-CONSTRUCTED SURVEY TOPO AND DATA
1.7 ITEMS 0006, 1006, 2006, 3006 AND 4006 RIGHT BANK LEVEE ALIGNMENT
STAGING
1.8 ITEMS 0007, 1007, 2007, 3007 AND 4007 ZONE D STA 3+50 TO 18+75
1.8.1 Items Ending In AA And BA For Grubbing
1.8.2 Items Ending In AB And BB for Excavation And Fill Placement
1.8.3 Items Ending In AC BC For Hydroseeding
1.9 ITEMS 0008, 1008, 2008, 3008 AND 4008 ZONE E STA 18+75 TO 42+00
1.9.1 Items Ending In AA, BA And CA For Grubbing
1.9.2 Items Ending In AB, BB And CB for Excavation And Fill Placement
1.9.3 Items Ending In AC, BC And CC For Hydroseeding
1.10 ITEMS 0009, 1009, 2009, 3009 AND 4009 ZONE F STA 42+00 TO 54+86.6
1.10.1 Items Ending In AA And BA For Grubbing
1.10.2 Items Ending In AB And BB for Excavation And Fill Placement
1.10.3 Items Ending In 9AC For Hydroseeding
1.10.4 Items Ending In 9BC Furnish And Plant Sod
1.11 ITEMS 0010, 1010, 2010, 3010 AND 4010 RIGHT BANK LEVEE ALIGNMENT
AS-CONSTRUCTED SURVEY TOPO AND DATA
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 28
ATTACHMENTS:
10 Left Bank Center Line
20 Right Bank Center Line
-- End of Section Table of Contents --
MEASUREMENT AND PAYMENT
PART 1 GENERAL
In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.
1.1 ESTIMATED CUT AND FILL QUANITY
Attached at the end of this section are two (2) end area volume report estimates calculated by the Government. 10 Left Bank Center Line and 20 Right Bank Center Line. The volumes represent only the excavation and fill placement between the existing and final construction grade lines.
1.2 ITEMS 0001, 1001, 2001, 3001 AND 4001 LEFT BANK LEVEE ALIGNMENT STAGING
Staging will be measured for payment by the number of times (JOB) all equipment for the work is staged on the left bank levee alignment work site. Payment will be made at the unit price for Items, "LEFT BANK LEVEE ALIGNMENT STAGING". Payment shall be full compensation for work to stage all equipment required to perform the work one time for each Task Order, complete, as specified and approved.
1.3 ITEMS 0002, 1002, 2002, 3002 AND 4002 ZONE A STA 0+00 TO 27+75
1.3.1 Items Ending In AA, BA And CA For Grubbing
Grubbing will be measured for payment by the number of Linear Feet (LF) grubbed in Zone A. Payment will be made at the unit price for Items, "Grubbing". Payment shall be full compensation for all work required for grubbing the required LF per task order in Zone A, complete, as specified and approved.
1.3.2 Items Ending In AB, BB And CB For Excavation And Fill Placement
Excavation and fill placement will be measured for payment by the number of Linear Feet (LF) excavated in Zone A. Payment will be made at the unit price for Items, "Excavation And Fill Placement". Payment shall be full compensation for all work required for excavation and fill placement of the required LF per task order in Zone A, complete, as specified and approved.
1.3.3 Items Ending In AC, BC And CC For Gravel Roadway Placement
Gravel roadway placement will be measured for payment by the number of Linear Feet (LF) gravel roadway placed in Zone A. Payment will be made at the unit price for Items, "Gravel Roadway Placement". Payment shall be full compensation for all work required for the gravel roadway placement of the required LF per task order in Zone A, complete, as specified and approved.
1.3.4 Items Ending In AD, BD And CD For Hydroseeding
Hydroseeding will be measured for payment by the number of Linear Feet (LF) hydroseeded in Zone A. Payment will be made at the unit price for Items, "Hydroseeding". Payment shall be full compensation for all work required for the hydroseeding of the required LF per task order in Zone A, complete, as specified and approved.
1.4 ITEMS 0003, 1003, 2003, 3003 and 4003 FOR ZONE B STA 27+75 TO 37+50
1.4.1 Items ending in AA For Grubbing
Grubbing will be measured for payment by the number of Linear Feet (LF) grubbed in Zone B. Payment will be made at the unit price for Items, "Grubbing". Payment shall be full compensation for all work required for grubbing of the required LF per task order in Zone B, complete, as specified and approved.
1.4.2 Items Ending In AB for Excavation And Fill Placement
Excavation and fill placement will be measured for payment by the number of Linear Feet (LF) excavated in Zone B. Payment will be made at the unit price for Item Number 0008AB, "Excavation And Fill Placement". Payment shall be full compensation for all work required for excavation and fill placement of the required LF per task order in Zone B, complete, as specified and approved.
1.4.3 Items Ending In AC For Gravel Roadway Placement
Gravel roadway placement will be measured for payment by the number of Linear Feet (LF) gravel roadway placed in Zone B. Payment will be made at the unit price for Items, "Gravel Roadway Placement". Payment shall be full compensation for all work required for the gravel roadway placement of the required LF per task order in Zone B, complete, as specified and approved.
1.4.4 Items Ending In AD For Hydroseeding
Hydroseeding will be measured for payment by the number of Linear Feet (LF) hydroseeded in Zone E. Payment will be made at the unit price for Items, "Hydroseeding". Payment shall be full compensation for all work required for the hydroseeding of the required LF per task order in Zone B, complete, as specified and approved.
1.5 ITEMS 0004, 1004, 2004, 3004 And 4004 FOR ZONE C STA 37+75 TO 47+00
1.5.1 Items Ending In AA For Grubbing
Grubbing will be measured for payment by the number of Linear Feet (LF) grubbed in Zone C. Payment will be made at the unit price for Items, "Grubbing". Payment shall be full compensation for all work required for grubbing of the required LF per task order in Zone C, complete, as specified and approved.
1.5.2 Items Ending In AB for Excavation And Fill Placement
Excavation and fill placement will be measured for payment by the number of Linear Feet (LF) excavated in Zone C. Payment will be made at the unit price for Item Number 0008AB, "Excavation". Payment shall be full compensation for all work required for excavation and fill placement of the required LF per task order in Zone C, complete, as specified and approved.
1.5.3 Items Ending In AC For Gravel Roadway Placement
Gravel roadway placement will be measured for payment by the number of Linear Feet (LF) gravel roadway placed in Zone C. Payment will be made at the unit price for Items, "Gravel Roadway Placement". Payment shall be full compensation for all work required for the gravel roadway placement of the required LF per task order in Zone C, complete, as specified and approved.
1.5.4 Items Ending In AD For Hydroseeding
Hydroseeding will be measured for payment by the number of Linear Feet (LF) hydroseeded in Zone C. Payment will be made at the unit price for Items, "Hydroseeding". Payment shall be full compensation for all work required for the hydroseeding of the required LF per task order in Zone C, complete, as specified and approved.
1.6 ITEMS 0005, 1005, 2005, 3005 AND 4005 LEFT BANK LEVEE ALIGNMENT
AS-CONSTRUCTED SURVEY TOPO AND DATA
Left bank survey will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for Items, "Left Bank Levee Alignment As-Constructed Survey Topo And Data," which price and payment shall be full compensation for all work required to perform the survey and supply all data per task order, complete, as specified and approved.
1.7 ITEMS 0006, 1006, 2006, 3006 AND 4006 RIGHT BANK LEVEE ALIGNMENT
STAGING
Staging will be measured for payment by the number of times (JOB) all equipment for the work is staged on the left bank levee alignment work site. Payment will be made at the unit price for Items, "RIGHT BANK LEVEE ALIGNMENT STAGING". Payment shall be full compensation for work to stage all equipment required to perform the work one time for each Task Order, complete, as specified and approved.
1.8 ITEMS 0007, 1007, 2007, 3007 AND 4007 ZONE D STA 3+50 TO 18+75
1.8.1 Items Ending In AA And BA For Grubbing
Grubbing will be measured for payment by the number of Linear Feet (LF) grubbed in Zone D. Payment will be made at the unit price for Items, "Grubbing". Payment shall be full compensation for all work required for grubbing of the required LF per task order in Zone D, complete, as specified and approved.
1.8.2 Items Ending In AB And BB for Excavation And Fill Placement
Excavation and fill placement will be measured for payment by the number of Linear Feet (LF) excavated in Zone D. Payment will be made at the unit price for Ites, "Excavation And Fill Placement". Payment shall be full compensation for all work required for excavation and fill placement of the required LF per task order in Zone D, complete, as specified and approved.
1.8.3 Items Ending In AC BC For Hydroseeding
Hydroseeding will be measured for payment by the number of Linear Feet (LF) hydroseeded in Zone D. Payment will be made at the unit price for Items, "Hydroseeding". Payment shall be full compensation for all work required for the hydroseeding of the required LF per task order in Zone D, complete, as specified and approved.
1.9 ITEMS 0008, 1008, 2008, 3008 AND 4008 ZONE E STA 18+75 TO 42+00
1.9.1 Items Ending In AA, BA And CA For Grubbing
Grubbing will be measured for payment by the number of Linear Feet (LF) grubbed in Zone E. Payment will be made at the unit price for Items, "Grubbing". Payment shall be full compensation for all work required for grubbing of the required LF per task order in Zone E, complete, as specified and approved.
1.9.2 Items Ending In AB, BB And CB for Excavation And Fill Placement
Excavation and fill placement will be measured for payment by the number of Linear Feet (LF) excavated in Zone E. Payment will be made at the unit price for Items, "Excavation And Fill Placement". Payment shall be full compensation for all work required for excavation and fill placement of the required LF per task order in Zone E, complete, as specified and approved.
1.9.3 Items Ending In AC, BC And CC For Hydroseeding
Hydroseeding will be measured for payment by the number of Linear Feet (LF) hydroseeded in Zone E. Payment will be made at the unit price for Items, "Hydroseeding". Payment shall be full compensation for all work required for the hydroseeding of the required LF per task order in Zone E, complete, as specified and approved.
1.10 ITEMS 0009, 1009, 2009, 3009 AND 4009 ZONE F STA 42+00 TO 54+86.6
1.10.1 Items Ending In AA And BA For Grubbing
Grubbing will be measured for payment by the number of Linear Feet (LF) grubbed in Zone F. Payment will be made at the unit price for Items, "Grubbing". Payment shall be full compensation for all work required for grubbing of the required LF per task order in Zone F, complete, as specified and approved.
1.10.2 Items Ending In AB And BB for Excavation And Fill Placement
Excavation and fill placement will be measured for payment by the number of Linear Feet (LF) excavated in Zone F. Payment will be made at the unit price for Items, "Excavation And Fill Placement". Payment shall be full compensation for all work required for excavation and fill placement of the required LF per task order in Zone F, complete, as specified and approved.
1.10.3 Items Ending In 9AC For Hydroseeding
Hydroseeding will be measured for payment by the number of Linear Feet (LF) hydroseeded in Zone F. Payment will be made at the unit price for
Items, "Hydroseeding". Payment shall be full compensation for all work required for the hydroseeding of the required LF per task order in Zone F, complete, as specified and approved.
1.10.4 Items Ending In 9BC Furnish And Plant Sod
Hydroseeding furnish and plant sod will be measured for payment by the number of Linear Feet (LF) of sod planted in Zone F. Payment will be made at the unit price for Items "Furnish And Plant Sod ". Payment shall be full compensation for all work required for furnishing and planting sod for the required LF per task order in Zone F, complete, as specified and approved.
1.11 ITEMS 0010, 1010, 2010, 3010 AND 4010 RIGHT BANK LEVEE ALIGNMENT
AS-CONSTRUCTED SURVEY TOPO AND DATA
Right bank survey will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for Items, "Right Bank Levee Alignment As-Constructed Survey Topo And Data," which price and payment shall be full compensation for all work required to perform the survey and supply all data per task order, complete, as specified and approved.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
Alignment Name:
Baseline
Station Mass
Factor Area Volume Adjusted Factor Area Volume Adjusted Factor Volume Adjusted Factor Volume Adjusted Ordinate
Zone A
0+00.000 1 0 0 0 1 6 0 0 1 0 0 1 0 0 0
0+25.000 1 0 0 0 1 4 5 5 1 0 0 1 0 0 -5
0+50.000 1 0 0 0 1 3 3 3 1 0 0 1 0 0 -8
0+75.000 1 5 3 3 1 2 2 2 1 0 0 1 0 0 -7
1+00.000 1 11 7 7 1 0 1 1 1 0 0 1 0 0 -1
1+01.808 0
1+25.000 1 18 13 13 1 0 0 0 1 0 0 1 0 0 12
1+50.000 1 31 23 23 1 1 1 1 1 0 0 1 0 0 34
1+75.000 1 36 31 31 1 1 1 1 1 0 0 1 0 0 64
2+00.000 1 34 32 32 1 1 1 1 1 0 0 1 0 0 95
2+25.000 1 35 32 32 1 0 1 1 1 0 0 1 0 0 127
2+50.000 1 37 33 33 1 0 0 0 1 0 0 1 0 0 160
2+75.000 1 29 30 30 1 1 1 1 1 0 0 1 0 0 190
3+00.000 1 22 24 24 1 1 1 1 1 0 0 1 0 0 212
3+25.000 1 18 18 18 1 0 0 0 1 0 0 1 0 0 230
3+50.000 1 12 14 14 1 0 0 0 1 0 0 1 0 0 244
3+75.000 1 10 10 10 1 0 0 0 1 0 0 1 0 0 253
4+00.000 1 8 8 8 1 0 0 0 1 0 0 1 0 0 261
4+25.000 1 14 10 10 1 0 0 0 1 0 0 1 0 0 271
4+50.000 1 8 11 11 1 1 0 0 1 0 0 1 0 0 282
4+75.000 1 2 5 5 1 3 2 2 1 0 0 1 0 0 285
5+00.000 1 7 5 5 1 6 4 4 1 0 0 1 0 0 285
5+25.000 1 11 9 9 1 7 6 6 1 0 0 1 0 0 288
5+50.000 1 18 14 14 1 6 6 6 1 0 0 1 0 0 296
5+75.000 1 20 18 18 1 3 4 4 1 0 0 1 0 0 309
6+00.000 1 22 19 19 1 2 2 2 1 0 0 1 0 0 326
6+25.000 1 22 20 20 1 3 2 2 1 0 0 1 0 0 344
6+50.000 1 22 21 21 1 4 3 3 1 0 0 1 0 0 362
6+75.000 1 22 21 21 1 5 4 4 1 0 0 1 0 0 378
7+00.000 1 22 20 20 1 5 4 4 1 0 0 1 0 0 394
7+25.000 1 19 19 19 1 5 4 4 1 0 0 1 0 0 408
7+50.000 1 17 17 17 1 4 4 4 1 0 0 1 0 0 421
7+75.000 1 19 17 17 1 4 4 4 1 0 0 1 0 0 434
8+00.000 1 18 17 17 1 5 4 4 1 0 0 1 0 0 447
8+25.000 1 18 17 17 1 3 4 4 1 0 0 1 0 0 459
8+50.000 1 16 16 16 1 3 3 3 1 0 0 1 0 0 472
8+75.000 1 16 15 15 1 6 4 4 1 0 0 1 0 0 483
9+00.000 1 16 15 15 1 2 4 4 1 0 0 1 0 0 494
9+25.000 1 19 16 16 1 2 2 2 1 0 0 1 0 0 509
9+50.000 1 19 18 18 1 1 1 1 1 0 0 1 0 0 525
9+75.000 1 22 19 19 1 1 1 1 1 0 0 1 0 0 544
10+00.000 1 24 21 21 1 1 1 1 1 0 0 1 0 0 564
10+25.000 1 23 22 22 1 1 1 1 1 0 0 1 0 0 585
10+50.000 1 30 25 25 1 2 1 1 1 0 0 1 0 0 609
10+75.000 1 31 28 28 1 2 2 2 1 0 0 1 0 0 635
11+00.000 1 28 27 27 1 3 2 2 1 0 0 1 0 0 661
11+25.000 1 28 26 26 1 3 2 2 1 0 0 1 0 0 684
11+50.000 1 31 27 27 1 3 3 3 1 0 0 1 0 0 709
11+75.000 1 35 31 31 1 3 3 3 1 0 0 1 0 0 737
12+00.000 1 37 34 34 1 2 2 2 1 0 0 1 0 0 768
12+25.000 1 39 35 35 1 1 1 1 1 0 0 1 0 0 802
12+50.000 1 39 36 36 1 1 1 1 1 0 0 1 0 0 838
12+75.000 1 37 36 36 1 1 1 1 1 0 0 1 0 0 873
13+00.000 1 34 33 33 1 2 1 1 1 0 0 1 0 0 904
13+25.000 1 32 31 31 1 2 1 1 1 0 0 1 0 0 934
13+50.000 1 35 31 31 1 1 1 1 1 0 0 1 0 0 964
13+75.000 1 34 32 32 1 1 1 1 1 0 0 1 0 0 995
14+00.000 1 30 30 30 1 5 3 3 1 0 0 1 0 0 1022
14+25.000 1 28 27 27 1 5 5 5 1 0 0 1 0 0 1044
14+50.000 1 24 24 24 1 3 4 4 1 0 0 1 0 0 1065
14+75.000 1 26 24 24 1 3 3 3 1 0 0 1 0 0 1086
15+00.000 1 29 26 26 1 3 3 3 1 0 0 1 0 0 1109
- - - - - - - - - - Fill - - - - - - - - - - - - - - - - - - Cut - - - - - - - - - - - - - - - - Fill - - - - - - - -
All units in this report are in feet, square feet and cubic yards unless specified otherwise. Quantities are based on the volume differences between the existing surface and the design surface and not adjusted for swell or shrink. Quantities shown do not account for the volume to be lost to grubbing operations.
- - - - - - - - - - - - - - - - Station Quantities - - - - - - - - - - - - - - - - - Added Quantities (Aggregate Surface Course) -
- - - - - - - - - - Cut - - - - - - - - - -
End Area Volume Report Report Created: 3/11/2016
Time: 4:36pm
10 Left Bank Levee Centerline
Note:
15+25.000 1 28 26 26 1 3 3 3 1 0 0 1 0 0 1132
15+50.000 1 25 24 24 1 4 4 4 1 0 0 1 0 0 1153
15+75.000 1 23 22 22 1 5 4 4 1 0 0 1 0 0 1171
16+00.000 1 25 22 22 1 4 4 4 1 0 0 1 0 0 1190
16+25.000 1 25 23 23 1 3 3 3 1 0 0 1 0 0 1210
16+50.000 1 19 20 20 1 11 6 6 1 0 0 1 0 0 1224
16+75.000 1 24 20 20 1 7 8 8 1 0 0 1 0 0 1235
17+00.000 1 27 24 24 1 6 6 6 1 0 0 1 0 0 1253
17+25.000 1 29 26 26 1 7 6 6 1 0 0 1 0 0 1273
17+50.000 1 31 28 28 1 7 6 6 1 0 0 1 0 0 1294
17+75.000 1 31 29 29 1 7 7 7 1 0 0 1 0 0 1317
18+00.000 1 34 30 30 1 4 5 5 1 0 0 1 0 0 1342
18+25.000 1 42 35 35 1 4 4 4 1 0 0 1 0 0 1373
18+50.000 1 42 39 39 1 4 4 4 1 0 0 1 0 0 1408
18+75.000 1 43 39 39 1 2 3 3 1 0 0 1 0 0 1444
19+00.000 1 47 42 42 1 2 2 2 1 0 0 1 0 0 1484
19+25.000 1 46 43 43 1 2 2 2 1 0 0 1 0 0 1525
19+50.000 1 42 41 41 1 1 1 1 1 0 0 1 0 0 1565
19+75.000 1 40 38 38 1 2 1 1 1 0 0 1 0 0 1601
20+00.000 1 37 36 36 1 3 2 2 1 0 0 1 0 0 1634
20+25.000 1 44 38 38 1 2 2 2 1 0 0 1 0 0 1669
20+50.000 1 45 41 41 1 1 2 2 1 0 0 1 0 0 1709
20+75.000 1 46 42 42 1 1 1 1 1 0 0 1 0 0 1750
21+00.000 1 42 41 41 1 1 1 1 1 0 0 1 0 0 1790
21+25.000 1 37 37 37 1 3 2 2 1 0 0 1 0 0 1825
21+50.000 1 33 33 33 1 3 3 3 1 0 0 1 0 0 1855
21+75.000 1 28 28 28 1 2 2 2 1 0 0 1 0 0 1881
22+00.000 1 30 27 27 1 2 2 2 1 0 0 1 0 0 1906
22+25.000 1 33 29 29 1 4 3 3 1 0 0 1 0 0 1932
22+50.000 1 34 31 31 1 3 3 3 1 0 0 1 0 0 1960
22+75.000 1 34 31 31 1 2 2 2 1 0 0 1 0 0 1989
23+00.000 1 36 32 32 1 2 2 2 1 0 0 1 0 0 2020
23+25.000 1 37 34 34 1 2 2 2 1 0 0 1 0 0 2052
23+50.000 1 38 35 35 1 2 2 2 1 0 0 1 0 0 2085
23+75.000 1 38 35 35 1 2 2 2 1 0 0 1 0 0 2118
24+00.000 1 39 35 35 1 4 3 3 1 0 0 1 0 0 2151
24+25.000 1 33 33 33 1 3 3 3 1 0 0 1 0 0 2181
24+50.000 1 42 34 34 1 3 3 3 1 0 0 1 0 0 2212
24+75.000 1 46 40 40 1 3 3 3 1 0 0 1 0 0 2250
25+00.000 1 46 42 42 1 7 5 5 1 0 0 1 0 0 2288
25+25.000 1 40 40 40 1 5 5 5 1 0 0 1 0 0 2322
25+50.000 1 36 35 35 1 6 5 5 1 0 0 1 0 0 2352
25+75.000 1 31 31 31 1 5 5 5 1 0 0 1 0 0 2379
26+00.000 1 39 32 32 1 3 3 3 1 0 0 1 0 0 2407
26+25.000 1 38 36 36 1 2 2 2 1 0 0 1 0 0 2441
26+50.000 1 37 35 35 1 3 2 2 1 0 0 1 0 0 2473
26+75.000 1 44 38 38 1 4 3 3 1 0 0 1 0 0 2508
27+00.000 1 44 41 41 1 5 4 4 1 0 0 1 0 0 2545
27+25.000 1 41 40 40 1 6 5 5 1 0 0 1 0 0 2580
27+50.000 1 43 39 39 1 6 6 6 1 0 0 1 0 0 2613
27+75.000 1 28 33 33 1 6 6 6 1 0 0 1 0 0 2640
Zone A
Zone B
27+75.000 1 28 33 33 1 6 6 6 1 0 0 1 0 0 2640
28+00.000 1 0 13 13 1 6 6 6 1 0 0 1 0 0 2648
28+25.000 1 0 0 0 1 6 6 6 1 0 0 1 0 0 2642
28+50.000 1 0 0 0 1 5 5 5 1 0 0 1 0 0 2637
28+75.000 1 43 20 20 1 6 5 5 1 0 0 1 0 0 2651
29+00.000 1 48 42 42 1 6 6 6 1 0 0 1 0 0 2687
29+25.000 1 51 46 46 1 4 5 5 1 0 0 1 0 0 2728
29+50.000 1 47 46 46 1 4 4 4 1 0 0 1 0 0 2770
29+75.000 1 36 39 39 1 3 3 3 1 0 0 1 0 0 2806
30+00.000 1 53 41 41 1 3 3 3 1 0 0 1 0 0 2844
30+25.000 1 54 49 49 1 2 2 2 1 0 0 1 0 0 2891
30+50.000 1 66 55 55 1 2 2 2 1 0 0 1 0 0 2945
30+75.000 1 74 64 64 1 2 2 2 1 0 0 1 0 0 3008
31+00.000 1 73 67 67 1 2 1 1 1 0 0 1 0 0 3074
31+25.000 1 70 65 65 1 1 1 1 1 0 0 1 0 0 3138
31+50.000 1 67 63 63 1 3 2 2 1 0 0 1 0 0 3199
31+75.000 1 60 59 59 1 4 3 3 1 0 0 1 0 0 3255
32+00.000 1 53 52 52 1 3 4 4 1 0 0 1 0 0 3303
32+25.000 1 47 46 46 1 3 3 3 1 0 0 1 0 0 3347
32+50.000 1 47 43 43 1 3 3 3 1 0 0 1 0 0 3387
32+75.000 1 54 46 46 1 3 3 3 1 0 0 1 0 0 3430
33+00.000 1 63 53 53 1 4 3 3 1 0 0 1 0 0 3481
33+25.000 1 67 60 60 1 5 4 4 1 0 0 1 0 0 3536
33+50.000 1 63 60 60 1 4 4 4 1 0 0 1 0 0 3592
33+75.000 1 55 54 54 1 5 4 4 1 0 0 1 0 0 3641
34+00.000 1 58 52 52 1 3 4 4 1 0 0 1 0 0 3690
34+25.000 1 60 54 54 1 3 3 3 1 0 0 1 0 0 3741
34+50.000 1 62 56 56 1 11 6 6 1 0 0 1 0 0 3791
34+75.000 1 23 39 39 1 4 7 7 1 0 0 1 0 0 3823
35+00.000 1 42 30 30 1 6 4 4 1 0 0 1 0 0 3849
35+25.000 1 28 32 32 1 11 7 7 1 0 0 1 0 0 3874
35+50.000 1 54 38 38 1 5 7 7 1 0 0 1 0 0 3905
35+75.000 1 60 52 52 1 3 3 3 1 0 0 1 0 0 3953
36+00.000 1 69 59 59 1 3 3 3 1 0 0 1 0 0 4010
36+25.000 1 71 64 64 1 4 3 3 1 0 0 1 0 0 4071
36+50.000 1 66 63 63 1 6 5 5 1 0 0 1 0 0 4128
36+75.000 1 65 60 60 1 5 5 5 1 0 0 1 0 0 4183
37+00.000 1 65 59 59 1 3 4 4 1 0 0 1 0 0 4239
37+25.000 1 54 55 55 1 3 3 3 1 0 0 1 0 0 4291
37+50.000 1 27 37 37 1 4 3 3 1 0 0 1 0 0 4325
Zone B
Zone C
37+50.000 1 27 37 37 1 4 3 3 1 0 0 1 0 0 4325
37+75.000 1 6 15 15 1 4 3 3 1 0 0 1 0 0 4337
38+00.000 1 10 8 8 1 9 6 6 1 0 0 1 0 0 4339
38+25.000 1 15 12 12 1 12 10 10 1 0 0 1 0 0 4340
38+50.000 1 6 10 10 1 13 12 12 1 0 0 1 0 0 4338
38+75.000 1 5 5 5 1 12 12 12 1 0 0 1 0 0 4332
39+00.000 1 0 3 3 1 16 13 13 1 0 0 1 0 0 4321
39+25.000 1 0 0 0 1 33 23 23 1 0 0 1 0 0 4298
39+50.000 1 0 0 0 1 40 34 34 1 0 0 1 0 0 4264
39+75.000 1 0 0 0 1 42 38 38 1 0 0 1 0 0 4227
40+00.000 1 0 0 0 1 33 34 34 1 0 0 1 0 0 4192
40+25.000 1 0 0 0 1 23 26 26 1 0 0 1 0 0 4166
40+50.000 1 1 1 1 1 15 18 18 1 0 0 1 0 0 4150
40+75.000 1 2 1 1 1 7 10 10 1 0 0 1 0 0 4141
41+00.000 1 17 8 8 1 1 4 4 1 0 0 1 0 0 4145
41+25.000 1 20 17 17 1 0 0 0 1 0 0 1 0 0 4162
41+50.000 1 19 18 18 1 0 0 0 1 0 0 1 0 0 4180
41+75.000 1 14 16 16 1 0 0 0 1 0 0 1 0 0 4195
42+00.000 1 18 15 15 1 0 0 0 1 0 0 1 0 0 4210
42+25.000 1 17 16 16 1 3 1 1 1 0 0 1 0 0 4225
42+50.000 1 17 16 16 1 7 4 4 1 0 0 1 0 0 4236
42+75.000 1 13 14 14 1 11 8 8 1 0 0 1 0 0 4242
43+00.000 1 15 13 13 1 8 9 9 1 0 0 1 0 0 4247
43+25.000 1 17 15 15 1 3 5 5 1 0 0 1 0 0 4256
43+50.000 1 13 14 14 1 4 3 3 1 0 0 1 0 0 4267
43+75.000 1 9 10 10 1 10 6 6 1 0 0 1 0 0 4271
44+00.000 1 12 10 10 1 7 8 8 1 0 0 1 0 0 4273
44+25.000 1 14 12 12 1 13 9 9 1 0 0 1 0 0 4276
44+50.000 1 17 14 14 1 4 8 8 1 0 0 1 0 0 4282
44+75.000 1 14 14 14 1 2 3 3 1 0 0 1 0 0 4293
45+00.000 1 29 20 20 1 0 1 1 1 0 0 1 0 0 4312
45+25.000 1 18 22 22 1 0 0 0 1 0 0 1 0 0 4334
45+50.000 1 19 16 16 1 0 0 0 1 0 0 1 0 0 4350
45+75.000 1 12 13 13 1 0 0 0 1 0 0 1 0 0 4364
46+00.000 1 25 16 16 1 0 0 0 1 0 0 1 0 0 4379
46+25.000 1 28 23 23 1 0 0 0 1 0 0 1 0 0 4402
46+50.000 1 12 18 18 1 0 0 0 1 0 0 1 0 0 4420
46+75.000 1 4 8 8 1 1 0 0 1 0 0 1 0 0 4428
47+00.000 1 25 14 14 1 0 0 0 1 0 0 1 0 0 4442
Zone C
5207 5207 766 766 0 0 0 0Grand Total:
Alignment Name:
Baseline
Station Mass
Factor Area Volume Adjusted Factor Area Volume Adjusted Factor Volume Adjusted Factor Volume Adjusted Ordinate
Zone D
3+00.000 1 0 0 0 1 0 0 0 1 0 0 1 0 0 0
3+25.000 1 0 0 0 1 0 0 0 1 0 0 1 0 0 0
3+50.000 1 0 0 0 1 6 3 3 1 0 0 1 0 0 -3
3+75.000 1 3 1 1 1 9 7 7 1 0 0 1 0 0 -8
4+00.000 1 1 2 2 1 20 13 13 1 0 0 1 0 0 -20
4+25.000 1 0 0 0 1 18 18 18 1 0 0 1 0 0 -38
4+50.000 1 0 0 0 1 32 23 23 1 0 0 1 0 0 -61
4+75.000 1 0 0 0 1 33 30 30 1 0 0 1 0 0 -91
5+00.000 1 0 0 0 1 30 29 29 1 0 0 1 0 0 -120
5+25.000 1 0 0 0 1 16 22 22 1 0 0 1 0 0 -142
5+50.000 1 0 0 0 1 7 11 11 1 0 0 1 0 0 -152
5+75.000 1 0 0 0 1 1 4 4 1 0 0 1 0 0 -156
6+00.000 1 14 7 7 1 0 1 1 1 0 0 1 0 0 -150
6+25.000 1 0 6 6 1 0 0 0 1 0 0 1 0 0 -144
6+50.000 1 0 0 0 1 1 0 0 1 0 0 1 0 0 -144
6+75.000 1 0 0 0 1 1 1 1 1 0 0 1 0 0 -145
7+00.000 1 3 1 1 1 1 1 1 1 0 0 1 0 0 -144
7+25.000 1 2 2 2 1 6 3 3 1 0 0 1 0 0 -145
7+50.000 1 2 2 2 1 5 5 5 1 0 0 1 0 0 -148
7+75.000 1 3 3 3 1 1 3 3 1 0 0 1 0 0 -148
8+00.000 1 3 3 3 1 1 1 1 1 0 0 1 0 0 -146
8+25.000 1 2 2 2 1 2 1 1 1 0 0 1 0 0 -145
8+50.000 1 1 2 2 1 1 1 1 1 0 0 1 0 0 -144
8+75.000 1 2 1 1 1 1 1 1 1 0 0 1 0 0 -144
9+00.000 1 0 1 1 1 0 0 0 1 0 0 1 0 0 -144
9+25.000 1 0 0 0 1 7 3 3 1 0 0 1 0 0 -147
9+50.000 1 2 1 1 1 5 5 5 1 0 0 1 0 0 -151
9+75.000 1 2 2 2 1 4 4 4 1 0 0 1 0 0 -153
10+00.000 1 0 1 1 1 7 5 5 1 0 0 1 0 0 -158
10+25.000 1 0 0 0 1 8 7 7 1 0 0 1 0 0 -165
10+50.000 1 0 0 0 1 7 7 7 1 0 0 1 0 0 -171
10+75.000 1 1 1 1 1 15 10 10 1 0 0 1 0 0 -181
11+00.000 1 0 0 0 1 19 16 16 1 0 0 1 0 0 -196
11+25.000 1 1 0 0 1 12 14 14 1 0 0 1 0 0 -210
11+50.000 1 1 1 1 1 15 13 13 1 0 0 1 0 0 -222
11+75.000 1 0 0 0 1 16 14 14 1 0 0 1 0 0 -236
12+00.000 1 2 1 1 1 7 11 11 1 0 0 1 0 0 -246
12+25.000 1 0 1 1 1 10 8 8 1 0 0 1 0 0 -253
12+50.000 1 6 3 3 1 1 5 5 1 0 0 1 0 0 -256
12+75.000 1 7 6 6 1 1 1 1 1 0 0 1 0 0 -251
13+00.000 1 2 4 4 1 2 1 1 1 0 0 1 0 0 -248
13+25.000 1 5 3 3 1 1 1 1 1 0 0 1 0 0 -245
13+50.000 1 7 5 5 1 1 1 1 1 0 0 1 0 0 -241
13+75.000 1 6 6 6 1 1 1 1 1 0 0 1 0 0 -236
14+00.000 1 12 9 9 1 0 1 1 1 0 0 1 0 0 -227
14+25.000 1 13 12 12 1 0 0 0 1 0 0 1 0 0 -216
14+50.000 1 4 8 8 1 0 0 0 1 0 0 1 0 0 -209
14+75.000 1 5 4 4 1 0 0 0 1 0 0 1 0 0 -205
15+00.000 1 0 2 2 1 0 0 0 1 0 0 1 0 0 -202
15+25.000 1 10 4 4 1 0 0 0 1 0 0 1 0 0 -198
15+50.000 1 9 8 8 1 0 0 0 1 0 0 1 0 0 -190
15+75.000 1 9 8 8 1 0 0 0 1 0 0 1 0 0 -182
16+00.000 1 8 8 8 1 0 0 0 1 0 0 1 0 0 -174
16+25.000 1 11 9 9 1 0 0 0 1 0 0 1 0 0 -165
16+50.000 1 19 14 14 1 0 0 0 1 0 0 1 0 0 -152
16+75.000 1 26 21 21 1 0 0 0 1 0 0 1 0 0 -132
17+00.000 1 32 27 27 1 0 0 0 1 0 0 1 0 0 -105
17+25.000 1 41 33 33 1 0 0 0 1 0 0 1 0 0 -72
17+50.000 1 22 29 29 1 0 0 0 1 0 0 1 0 0 -44
17+75.000 1 16 17 17 1 1 0 0 1 0 0 1 0 0 -27
18+00.000 1 13 13 13 1 1 1 1 1 0 0 1 0 0 -14
18+21.959 0
- - - - - - - - - - Fill - - - - - - - - - - - - - - - - - - Cut - - - - - - - - - - - - - - - - Fill - - - - - - - -
Note:
- - - - - - - - - - - - - - - - Station Quantities - - - - - - - - - - - - - - - - - Added Quantities (Aggregate Surface Course) -
- - - - - - - - - - Cut - - - - - - - - - -
End Area Volume Report Report Created: 3/11/2016
Time: 4:41pm
20 Right Bank Levee Centerline
All units in this report are in feet, square feet and cubic yards unless specified otherwise. Quantities are based on the volume differences between the existing surface and the design surface and not adjusted for swell or shrink. Quantities shown do not account for the volume to be lost to grubbing operations.
18+25.000 1 22 16 16 1 0 0 0 1 0 0 1 0 0 2
18+50.000 1 15 17 17 1 0 0 0 1 0 0 1 0 0 18
18+75.000 1 10 11 11 1 0 0 0 1 0 0 1 0 0 30
Zone D
Zone E
18+75.000 1 10 11 11 1 0 0 0 1 0 0 1 0 0 30
19+00.000 1 18 13 13 1 0 0 0 1 0 0 1 0 0 42
19+25.000 1 22 18 18 1 0 0 0 1 0 0 1 0 0 60
19+50.000 1 30 24 24 1 0 0 0 1 0 0 1 0 0 84
19+75.000 1 27 26 26 1 0 0 0 1 0 0 1 0 0 110
20+00.000 1 26 24 24 1 0 0 0 1 0 0 1 0 0 134
20+25.000 1 19 21 21 1 0 0 0 1 0 0 1 0 0 155
20+50.000 1 20 18 18 1 0 0 0 1 0 0 1 0 0 173
20+75.000 1 17 17 17 1 0 0 0 1 0 0 1 0 0 190
21+00.000 1 15 15 15 1 0 0 0 1 0 0 1 0 0 204
21+25.000 1 7 10 10 1 1 0 0 1 0 0 1 0 0 214
21+50.000 1 4 5 5 1 4 2 2 1 0 0 1 0 0 217
21+75.000 1 4 4 4 1 9 6 6 1 0 0 1 0 0 214
22+00.000 1 2 3 3 1 12 9 9 1 0 0 1 0 0 208
22+25.000 1 2 2 2 1 7 9 9 1 0 0 1 0 0 201
22+50.000 1 2 2 2 1 9 8 8 1 0 0 1 0 0 196
22+75.000 1 0 1 1 1 0 4 4 1 0 0 1 0 0 192
23+00.000 1 0 0 0 1 0 0 0 1 0 0 1 0 0 192
23+25.000 1 0 0 0 1 39 18 18 1 0 0 1 0 0 174
23+50.000 1 2 1 1 1 21 28 28 1 0 0 1 0 0 148
23+75.000 1 1 1 1 1 9 14 14 1 0 0 1 0 0 135
24+00.000 1 8 4 4 1 5 7 7 1 0 0 1 0 0 132
24+25.000 1 11 9 9 1 0 3 3 1 0 0 1 0 0 139
24+50.000 1 16 13 13 1 0 0 0 1 0 0 1 0 0 151
24+75.000 1 11 13 13 1 0 0 0 1 0 0 1 0 0 164
25+00.000 1 9 10 10 1 0 0 0 1 0 0 1 0 0 173
25+25.000 1 10 9 9 1 0 0 0 1 0 0 1 0 0 182
25+50.000 1 16 12 12 1 0 0 0 1 0 0 1 0 0 193
25+75.000 1 17 15 15 1 0 0 0 1 0 0 1 0 0 208
26+00.000 1 8 11 11 1 0 0 0 1 0 0 1 0 0 219
26+25.000 1 10 8 8 1 1 0 0 1 0 0 1 0 0 227
26+50.000 1 6 7 7 1 0 0 0 1 0 0 1 0 0 234
26+75.000 1 7 6 6 1 0 0 0 1 0 0 1 0 0 240
27+00.000 1 7 6 6 1 0 0 0 1 0 0 1 0 0 246
27+25.000 1 9 7 7 1 0 0 0 1 0 0 1 0 0 253
27+50.000 1 14 10 10 1 0 0 0 1 0 0 1 0 0 263
27+75.000 1 12 12 12 1 0 0 0 1 0 0 1 0 0 274
28+00.000 1 11 11 11 1 0 0 0 1 0 0 1 0 0 284
28+25.000 1 25 16 16 1 0 0 0 1 0 0 1 0 0 301
28+50.000 1 23 22 22 1 0 0 0 1 0 0 1 0 0 323
28+75.000 1 15 18 18 1 0 0 0 1 0 0 1 0 0 340
29+00.000 1 22 17 17 1 0 0 0 1 0 0 1 0 0 357
29+25.000 1 15 17 17 1 0 0 0 1 0 0 1 0 0 374
29+50.000 1 12 13 13 1 1 0 0 1 0 0 1 0 0 386
29+75.000 1 13 12 12 1 0 0 0 1 0 0 1 0 0 397
30+00.000 1 12 12 12 1 0 0 0 1 0 0 1 0 0 409
30+25.000 1 12 11 11 1 0 0 0 1 0 0 1 0 0 420
30+50.000 1 12 11 11 1 0 0 0 1 0 0 1 0 0 430
30+75.000 1 14 12 12 1 0 0 0 1 0 0 1 0 0 442
31+00.000 1 8 10 10 1 0 0 0 1 0 0 1 0 0 452
31+25.000 1 13 10 10 1 0 0 0 1 0 0 1 0 0 462
31+50.000 1 27 18 18 1 0 0 0 1 0 0 1 0 0 479
31+75.000 1 31 27 27 1 3 1 1 1 0 0 1 0 0 505
32+00.000 1 31 29 29 1 4 3 3 1 0 0 1 0 0 530
32+25.000 1 46 36 36 1 0 2 2 1 0 0 1 0 0 564
32+50.000 1 73 55 55 1 0 0 0 1 0 0 1 0 0 619
32+75.000 1 44 55 55 1 0 0 0 1 0 0 1 0 0 673
33+00.000 1 54 45 45 1 0 0 0 1 0 0 1 0 0 718
33+25.000 1 24 36 36 1 0 0 0 1 0 0 1 0 0 754
33+50.000 1 17 19 19 1 0 0 0 1 0 0 1 0 0 773
33+75.000 1 16 16 16 1 0 0 0 1 0 0 1 0 0 788
34+00.000 1 19 16 16 1 0 0 0 1 0 0 1 0 0 804
34+25.000 1 20 18 18 1 0 0 0 1 0 0 1 0 0 822
34+50.000 1 24 20 20 1 0 0 0 1 0 0 1 0 0 842
34+75.000 1 22 21 21 1 0 0 0 1 0 0 1 0 0 863
35+00.000 1 17 18 18 1 1 0 0 1 0 0 1 0 0 881
35+25.000 1 15 15 15 1 1 1 1 1 0 0 1 0 0 895
35+50.000 1 14 13 13 1 0 0 0 1 0 0 1 0 0 908
35+75.000 1 15 14 14 1 0 0 0 1 0 0 1 0 0 921
36+00.000 1 19 16 16 1 0 0 0 1 0 0 1 0 0 937
36+25.000 1 21…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .