Amendment_0001.pdf
PDF 707 KB Posted
- Solicitation number
- W912EF-14-B-0005
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Results.pdf | ||
| Amendment_0002.pdf | ||
| Plans_14-B-0005_Amend-0001.pdf | ||
| Site_Visit_Attendees.pdf | ||
| Bidder_Inquiry_Information.pdf | ||
| W912EF-14-B-0005.pdf | ||
| Site_Visit_Information.pdf | ||
| Plans_14-B-0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W68SBV33249743
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
TITLE: Low er Granite Permanent Closures: Fish Screen Slots and Wagner Horns
The purpose of this amendment is to make the changes indicated in the Summary of Changes.
The bid opening date is hereby changed from 29 April 2014 at 2:00 p.m. to 6 May 2014 at 2:00 p.m.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-Apr-2014
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-14-B-0005
X 9B. DATED (SEE ITEM 11)
28-Mar-2014
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Apr-2014
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
JANI C. LONG
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF-14-B-0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. Revised the following Specifications:
• SECTION 01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS
o Revised paragraph 1.6.1 General o Revised paragraph 1.6.3 Fish Screen Slot Permanent Closure Documentation o Revised paragraph 1.6.4 Remotely Operated Vehicle (ROV) Requirements o Added paragraph 1.8 WATER TEMPERATURE o Revised paragraph 1.9 WATER SURFACE ELEVATION IN FISH SCREEN SLOTS
DURING CONSTRUCTION
o Revised paragraph 1.10 FINAL WATER SURFACE ELEVATION IN FISH SCREEN
SLOTS
o Added paragraph 1.20.1 Installation Supervisor o Deleted paragraph 1.21 INSTALLATION SUPERVISOR o Some paragraphs renumbered.
• SECTION 01 14 00.10 28 PROJECT SITE RESTRICTIONS
o Revised paragraph 1.4.2 Government's Work Schedule o Deleted paragraph 1.5 OTHER CONTRACTS o Renumbered paragraph 1.5.1 Roadway Closure and Delays (changed to paragraph
1.5).
• SECTION 01 22 00.00 28 MEASUREMENT AND PAYMENT
o Revised paragraph 1.3 ITEM 0002 FISH SCREEN SLOT CONCRETE CLOSURE
CONSTRUCTION
o Revised paragraph 1.8 ITEM 0007 ADJUST FSS PERMANENT CLOSURE LEG
LENGTH
o Revised paragraph 1.9 ITEM 0008 FURNISH SKILLED IRONWORKER LABOR o Revised paragraph 1.9.1 ITEM 0008a Related Construction Material Cost o Revised paragraph 1.10 ITEM 0009 ADDITIONAL DIVING SERVICES
• SECTION 01 32 01.10 28 PROJECT SCHEDULE
o Revised paragraph 3.4 PROJECT SCHEDULE SUBMISSIONS o Revised paragraph 3.4.1 Initial Project Schedule Submission
• SECTION 01 33 00 SUBMITTAL PROCEDURES
o Revised Submittal Register
• SECTION 01 35 10.00 28 DIVING
o Revised paragraph 1.2.2 Anticipated Environment o Revised paragraph 1.3 DIVE OPERATION NOTIFICATION o Revised paragraph 2.1 UNDERWATER VIDEO o Deleted paragraph 2.1.1 General
• SECTION 01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS
o Revised paragraph 1.2 SUBMITTALS o Revised paragraph 1.4.1 Construction Activities on the Intake Deck o Revised paragraph 1.5 OVERHEAD POWER TRANSMISSION LINES o Revised paragraph 1.6 UNIT OUTAGES o Added paragraph 1.6.1 Early Unit Availability Requests o Revised paragraph 1.7 INTAKE GATE INSTALLATION PRIOR TO DIVING o Revised paragraph 1.8.2 Fish Screen Slot Grating o Revised paragraph 1.8.3 Temporary Handrailing o Revised paragraph 1.9 EXTENDED SUBMERGED BAR SCREENS (ESBS's) o Revised paragraph 1.11 FISH RESCUE, AND REMOVAL FROM FISH SCREEN
SLOTS
o Revised paragraph 1.12 WORK PRIOR TO DIVING o Revised paragraph 1.16 GOVERNMENT ROADWAYS AND DECK ACCESS
RESTRICTIONS
o Added paragraph 1.16.1 Storage and Staging Plan o Revised paragraph 1.18.2 Deck Access and Roadway Coordination Requirements o Some paragraph renumbering.
• SECTION 01 57 20.10 28 ENVIRONMENT PROTECTION
o Revised paragraph 1.3 SUBMITTALS o Deleted paragraph 1.5 CONTRACTOR'S ENVIRONMENTAL MANAGER and related paragraphs.
o Deleted paragraph 1.6 ENVIRONMENTAL DEMONSTRATION AND TRAINING and related paragraphs.
o Revised paragraph 1.10 CONSTRUCTION WATER DISPOSAL o Revised paragraph 1.10.1 Water Treatment and Disposal o Added paragraph 1.10.1.1 Settling Tank System o Added paragraph 1.10.1.2 Land Application Disposal o Deleted paragraph 1.10.2 Construction Water o Added paragraph 1.11 DISPOSAL OF FISH SCREEN SLOT WATER AFTER
TREMIE PLACEMENT
o Added paragraph 1.12 CONSTRUCTION WATER o Some paragraph renumbering.
• SECTION 03 11 13.00 28 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
o Revised paragraph 3.3.1 Formwork Supporting Weight of Concrete
• SECTION 03 30 00.00 28 CAST-IN-PLACE CONCRETE
o Revised paragraph 1.1 REFERENCES o Revised paragraph 2.6 CLOSURE GROUT, and Table o Revised paragraph 2.7 NONSHRINK GROUT o Revised paragraph 3.2.1 General Requirements o Revised paragraph 3.5.3 Cold Weather Placing Requirements o Renamed paragraph 3.7.1 from “Waterstops” to “Guide Bar Seep Plates”.
o Revised paragraph 3.7.1 Guide Bar Seep Plates o Revised paragraph 3.8 CLOSURE GROUTING o Revised paragraph 3.9 TESTING AND INSPECTION FOR CQC
• SECTION 05 12 00.00 28 STRUCTURAL STEEL
o Revised paragraph 1.6.3.2 Fish Slot Screen Inspection
2. Revised the following Drawings:
(See inside brackets on drawing for details)
• G-001, G-003, G-101, G-301, G-302, SD401, SC402, SC403, SC501, SC502, and
SC504.
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 29-Apr-2014 02:00 PM to 06-May-2014 02:00 PM.
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been modified:
BID SCHEDULE
Walla Walla District Corps of Engineers
Lower Granite Permanent Closures: Fish Screen Slots and Wagner Horns
100% Small Business Set-Aside
The estimated magnitude of construction will be between $1,000,000 and $5,000,000
ITEM
DESCRIPTION
QUANTITY
U/M
U/P
AMOUNT
BASE ITEMS
0001 Fish Screen Slot Screen Removal 1 JOB XXXXX $________
0002 Fish Screen Slot Concrete Closure Construction 1 JOB XXXXX $________
0003 Wagner Horn Screen Removal 1 JOB XXXXX $________
0004 Wagner Horn Concrete Closure Construction 1 JOB XXXXX $________
0005 Wagner Horn Closure Installation 1 JOB XXXXX $________
0006 Fish Screen Slot Closure Installation 1 JOB XXXXX $________
0007 Adjust FSS Permanent Closure Leg Length Estimated 6 TASK $_______ $________
0008 Furnish Skilled Ironworker Labor NTE 50 HR $_______ $________
0008aa Related Construction Material Cost NTE $5,000 Dollar XXXXX $5,000
0009 Additional Dive Services NTE 60 HR $_______ $________
SCHEDULE TOTAL $__________
IMPORTANT See Section 01 22 00.00 28; MEASUREMENT AND PAYMENT; Paragraph; Retainage of Payment, for withholding of payment for final deliverables.
Estimated quantities are provided for in CLIN 0007. See Section 00700, FAR Clause 52.211-18, Variation in Estimated Quantity.
Contract Line Item #0008, 0008aa, and 0009 are Time & Materials/Labor Hour line items. The extended amount for these items are the established ceiling price. Without a modification pursuant to FAR Clause 52.243-3, Changes -- Time-and-Materials or Labor-Hours (Sep 2000), the Contractor exceeds the ceiling at its own risk.
SECTION 00700 - CONTRACT CLAUSES
The following have been added by reference:
52.211-18 Variation in Estimated Quantity APR 1984 52.232-7 Payments Under Time-And-Materials And Labor Hour
Contracts
AUG 2012
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the dates listed below.
Contractor shall complete work during the scheduled unit outages. Scheduled Contractor turbine unit access dates are listed below (see Specifications Section 01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS, paragraph UNIT OUTAGES for additional information). Units are listed by letter since sequence of unit outages may change.
Unit A – 6 August 2014 thru 12 September 2014 Unit B – 13 September 2014 thru 14 October 2014 Unit C – 15 October 2014 thru 13 November 2014 Unit D – 14 November 2014 thru 17 December 2014 Unit E – 18 December 2014 thru 21 January 2015 Unit F – 22 January 2015 thru 23 February 2015
(1) The Contractor shall complete all work for the Fish Screen Slot and Wagner Horn closures by not later than 23 February 2015.
(2) The Contractor shall complete final cleanup and demobilization by not later than 15 calendar days after completion of work in (1) above.
(3) The Contractor shall complete final submission of working “as-built” contract drawings and final approved versions of Contractor prepared drawings (see SECTION 01 78 00.00 28) by not later than 30 calendar days after completion of work in (1) above.
(4) WORK RESTRICTION: Contractor must complete all work on one Unit before initiating work on the next.
(End of clause)
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Drawing Number
Sheet Number
Title
Revision Number
Date
LOWER GRANITE LOCK AND DAM
PERMANENT CLOSURES: FISH SCREEN SLOT AND
WAGNER HORN
GENERAL
GDG-1-0-1/578 G-001 COVER SHEET, - MAPS AND SITE PLAN A 4/2/2014
GDG-1-0-1/588 G-002 DRAWING INDEX - AND ABBREVIATIONS
GDG-1-13-1/55 G-003 GENERAL AND STRUCTURAL - NOTES A 4/8/2014
GDG-1-13-1/56 G-101 CONTRACTOR STORAGE AND STAGING AREAS
PLAN A 4/14/2014
GDG-1-13-1/57 G-102 KEY PLANS
GDG-1-13-1/58 G-301 TYPICAL UNIT - SECTIONAL ELEVATION A 4/14/2014
GDG-1-13-1/59 G-302 FISH SCREEN SLOT CLOSURE - POTENTIAL
INSTALLATION SEQUENCE A 4/14/2014
GDG-1-13-1/60 G-303 WAGNER HORN CLOSURE - POTENTIAL
INSTALLATION SEQUENCE
STRUCTURAL
GDF-1-13-
10/120 SD401 EXISTING FISH SCREENS - SALVAGE PLANS AND
SECTIONS - SHEET 1 A 4/7/2014
GDF-1-13-
1O/121 SD402 EXISTING FISH SCREENS - SALVAGE PLANS AND
SECTIONS - SHEET 2
GDF-1-13-
10/122 SC401 TYPICAL SCREEN CONVERSION - PLAN AND
SECTION
GDF-1-13-
10/123 SC402 WAGNER HORN CLOSURE - PLAN, ELEVATION
AND DETAILS A 4/7/2014
GDF-1-13-
10/124 SC403 WAGNER HORN CLOSURE - SECTIONS AND
DETAILS A 4/7/2014
GDF-1-13-
10/125 SC404 WAGNER HORN CLOSURE - POTENTIAL CABLE
PROTECTION - DETAILS
GDF-1-13-
10/126 SC501 FISH SCREEN SLOT CLOSURE - SECTIONS AND
DETAILS - SHEET 1 A 4/14/2014
GDF-1-13-
10/127 SC502 FISH SCREEN SLOT CLOSURE - SECTIONS AND
DETAILS - SHEET 2 A 4/7/2014
GDF-1-13-
10/128 SC503 FISH SCREEN SLOT CLOSURE - SECTIONS AND
DETAILS - SHEET 3
GDF-1-13-
10/129 SC504 FISH SCREEN SLOT CLOSURE - SECTIONS AND
DETAILS - SHEET 4 A 4/7/2014
GDF-1-13-
10/130 SC505 FISH SCREEN SLOT CLOSURE - TREMIE CLOSURE
POUR - SECTIONS AND DETAILS
FOR INFORMATION ONLY (FIO)
The Government does not warrant the accuracy of the FIO drawings. The Government recommends that the Contractor verify the accuracy of FIO drawings.
GDG-1-0-1/309 I-001 WAGNER HORN CLOSURES - GENERAL PLAN AND
SECTION
GDF-1-13-10/39 I-002 FISH SCREEN SLOT CLOSURE - FRAMING PLAN,
ELEVATION AND SECTION
GDF-1-13-10/40 I-003 FISH SCREEN SLOT CLOSURE - SECTIONS AND
DETAILS
GDF-1-13-10/41 I-004 WAGNER HORN CLOSURES - ELEVATION AND
GDF-1-13-10/42 I-005 WAGNER HORN CLOSURES - SECTIONS AND
DETAILS
GDF-1-13-10/43 I-006 FISH SCREEN SLOT AND - WAGNER HORN
CLOSURES - LIFTING BEAM SHEET 1
GDF-1-13-10/44 I-007 FISH SCREEN SLOT AND - WAGNER HORN
CLOSURES - LIFTING BEAM SHEET 2
GDF-1-13-10/45 I-008 FISH SCREEN SLOT AND - WAGNER HORN
CLOSURES - LIFTING BEAM SH. 3
GDF-1-13-10/46 I-009 FISH SCREEN SLOT AND - WAGNER HORN
CLOSURES - LIFTING BEAM SH. 4
GDP-1-4-2/1 I-010 GENERATOR BAY-CONCRETE OUTLINE -
TRANSVERSE SECTION - BAYS 1, 2 & 3
GDP-1-4-2/2 I-011 GENERATOR BAY-CONCRETE OUTLINE -
TRANSVERSE SECTION - BAYS 4, 5 & 6
GDP-1-4-2/38 I-012 GENERATOR BAY-CONCRETE OUTLINE - INTAKE
DECK EL. 751 - SHEET 1
GDP-1-4-2/38A I-013 GENERATOR BAY-CONCRETE OUTLINE - INTAKE
DECK EL. 751 - SHEET 1A
GDP-1-4-2/40 I-014 GENERATOR BAY-CONCRETE OUTLINE - INTAKE
TRANSVERSE SECTION
GDP-1-4-2/42A I-015 GENERATOR BAY-CONCRETE OUTLINE - FISH
SCREEN BLOCKOUTS - UNITS 1 THRU 6
GDP-1-4-2/78 I-016
GENERATOR BAYS-REINFORCEMENT - INTAKE
ROOF OF WATERWAY - AND SERVICE GALLERY-
SHEET 1
LGD-1-4-4/3 I-017 POWERHOUSE - MISCELLANEOUS METAL -
FRAMES AND COVERS-SHEET 3
GDP-1-5-0/18 I-018 POWERHOUSE - MISCELLANEOUS METAL -
FRAMES AND COVERS-SHEET 8
GDP-1-5-0/23A I-019 MISCELLANEOUS METAL - FRAMES AND COVERS-
SHEET 14
1210-1 I-020 WAGNER HORN CLOSURE
1210-2 I-021 SLOT CLOSURE
1210-3 I-022 DETAILS
1210-4 I-023 DETAILS
1210-5 I-024 LIFTING BEAM
1210-6 I-025 DETAILS
1210-7 I-026 MISC. PARTS
1210-8 I-027 MISC. PARTS
1210-9 I-028 DETAILS
GDP-1.34-0-0/4 I-029 LOWER GRANITE PROJECT - TRANSVERSE
GDP-1-6-1A5/3 I-030 POWERHOUSE - HIGH VOLTAGE EQUIPMENT -
PLAN
GDP-1-6-1A5/4 I-031 POWERHOUSE - HIGH VOLTAGE EQUIPMENT -
SECTIONS
(End of drawing list)
(End of clause)
Contract drawings created on CADD will be available in electronic form for use by the Contractor. No For Information Only drawings are available on CADD. The Contractor assumes all risks associated in using electronic CADD drawings. The contract drawings shall govern if there are any discrepancies between the electronic copy and the contract drawing. The Contractor shall promptly notify the Contracting Officer of any discrepancies. The Government will not be responsible to correct the electronic CADD drawing. If contract modifications are issued, the associated electronic CADD drawings will not be available to the Contractor. Electronic copies of CADD drawings are only available in Bentley MicroStation format. The Government will provide the files on CD ROM. If the Contractor requires different media, such as floppy disks, the Contractor shall be responsible for all conversions required for their use and associated conversion inaccuracies.
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 1995)—UAI
(a) This clause does not apply to terminations. See 52.249-5000, Basis for Settlement of Proposals and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region VIII. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the small purchase threshold, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
(End of Special Contract Requirements)
(End of Summary of Changes)
Lower Granite Perm. Closures: Fish Screen Slot and Wagner HornW912EF-14-B-0005 Amend-0001
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DEFINITIONS
1.4 FIELD VERIFICATION OF SITE CONDITIONS
1.5 FIELD VERIFICATION OF EXISTING FISH SCREEN SLOT (FSS) and FSS
SCREEN DIMENSIONS
1.6 FIELD VERIFICATION OF INSTALLED FISH SCREEN SLOT AND WAGNER HORN
CLOSURES
1.6.1 General
1.6.2 Wagner Horn Permanent Closure Documentation
1.6.3 Fish Screen Slot Permanent Closure Documentation
1.6.4 Remotely Operated Vehicle (ROV) Requirements
1.7 ADJUST FSS PERMANENT CLOSURE LEG LENGTH
1.8 WATER TEMPERATURE
1.9 WATER SURFACE ELEVATION IN FISH SCREEN SLOTS DURING CONSTRUCTION
1.10 FINAL WATER SURFACE ELEVATION IN FISH SCREEN SLOTS
1.11 REGULAR CLEANUP AND DEBRIS DISPOSAL
1.12 EQUIPMENT LIST
1.13 TESTING OF EQUIPMENT
1.14 DISPOSITION OF REMOVED EQUIPMENT
1.15 FIRE CONTROL
1.16 RIGGING AND LIFTING DEVICES
1.17 FISH SCREEN SLOT SCREEN - LIFTING BEAM
1.18 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.19 PRE-WORK AND POST WORK SURVEYS
1.20 PROJECT SUPERINTENDENT
1.20.1 Installation Supervisor
1.21 KEY PERSONNEL SUBSTITUTION
1.22 POST AWARD MEETINGS
1.22.1 Pre-Work Meeting
1.22.2 Pre-Construction Meeting
1.22.2.1 Minutes
1.22.2.2 Demobilizing And Remobilizing
1.23 WEEKLY PRODUCTION MEETINGS
1.23.1 Minutes
1.24 ADDITIONAL MEETINGS
1.25 PARTNERING
1.25.1 General
1.25.2 Partnering Meetings
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
SECTION 01 11 01.00 28
G4EDHCMP
Line
G4EDHCMP
Line
G4EDHCMP
Line
G4EDHCMP
Line
ATTACHMENTS:
Weekly Meeting Agenda Template
-- End of Section Table of Contents --
SECTION 01 11 01.00 28
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. When used, a designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Equipment List; I C
Pre-Work Survey Photos And Report; I C
Project Superintendent; I C
SD-02 Shop Drawings
Field Verification of Existing Fish Screen Slot (FSS) and FSS Screen Dimensions; I C
SD-07 Certificates
Installation Supervisor; G C
Key Personnel Substitution; G C
SD-11 Closeout Submittals
Post-Work Survey Photos And Report; I C
1.3 DEFINITIONS
a. Qualified Person.
As defined in EM 385-1-1; "DEFINITIONS", unless otherwise specified.
1.4 FIELD VERIFICATION OF SITE CONDITIONS
As-built drawings may not accurately represent existing field conditions.
The Contractor shall field verify all elevations, dimensions, and coordinates of existing features indicated on the contract drawings, that impact required execution of construction and installation of new features. Any deviations shall be reported to the Contracting Officer within 24 hours of discovery and updated as per Section 01 78 00.00 28, CLOSEOUT SUBMITTALS, paragraph MAINTAIN WORKING AS-BUILT CONTRACT DRAWINGS
AND FIO DRAWINGS.
1.5 FIELD VERIFICATION OF EXISTING FISH SCREEN SLOT (FSS) and FSS SCREEN
DIMENSIONS
a. Each FSS screen shall be identified by the Unit and Slot number it originated from, and be returned to the same slot after modification.
Contractor shall carefully document FSS screen and slot dimensions in order to ensure accurate placement of permanent FSS closures. Refer to Sheet SD401 for additional information on measurements and final configuration.
b. Contractor shall make adjustments to the modified FSS screen leg lengths, as required, for the downstream side of the permanent closure to align with the downstream side of the FSS opening. After modification, the as-constructed screen leg dimension for Dimension 3 shall equal Dimension 1 plus 1.5 inches, with a tolerance of +/- 0.5 inches. The following measurements shall be recorded and submitted within 48 hours of taking measurements. Measurements shall be taken for each FSS screen leg and/or FSS guide slot, as applicable.
1. Total length of each FSS screen structure prior to modification (Dimension 2). Measure both sides after removing screen structure from the Fish Screen Slot.
2. Length of bottom screen leg to lower edge of angled plate (Dimension 3) prior to modification. Measure both sides after removing screen structure from the Fish Screen Slot.
3. Length of removed portion of FSS screen legs (Dimension 4).
4. Length of FSS guide slot from bottom of seat pocket to intake roof corner (Dimension 1). Measure both sides of slot after Fish Screen has been removed from the Fish Screen Slot.
5. Length of each modified FSS screen leg prior to installation of permanent closure (New Dimension 3). Measure prior to returning permanent closure to Fish Screen Slot.
c. Measurements of existing conditions must be submitted to the Contracting Officer a minimum of one Government work day prior to modifying applicable FSS screens. Field verification of measurements must be witnessed by a Government representative prior to returning modified permanent closures to the Fish Screen Slots.
1.6 FIELD VERIFICATION OF INSTALLED FISH SCREEN SLOT AND WAGNER HORN
CLOSURES
1.6.1 General
Underwater Video shall be used as documentation of closure installation.
Video submittals must show all edges of each Wagner Horn closure and/or Fish Screen Slot closure, as required. It must be possible to determine if In addition, video must show all Fish Screen Slot and Wagner Horn closures are installed as required in the Plans and Specifications. All video must be witnessed by a Government representative. See Section 01 35 10.00 28 DIVING, paragraph UNDERWATER VIDEO for video submittal requirements.
1.6.2 Wagner Horn Permanent Closure Documentation
Document the following features of the Wagner Horn Closures after completion of installation:
a. Face of Wagner Horn closure in the turbine intake is finished as shown and specified. See Section 05 12 00.00 28 STRUCTURAL STEEL, paragraph "Wagner Horn Inspection" for additional information.
b. Confirm grout does not extend down below roof of intake. All surfaces of intake roof, impacted by work on this contract, shall be ground smooth with no protruding surfaces that could be harmful to fish.
c. Access top of Wagner Horn Permanent Closure through Wagner Horn opening in the Fish Screen Slot. Verify gap between Permanent Closure and existing Corrugate Metal Pipe is completely filled with grout.
Confirm grout, at a minimum, is flush with top of Permanent Closure.
1.6.3 Fish Screen Slot Permanent Closure Documentation
Document the following features of the Fish Screen Slot Permanent closures as outline below:
a. After lowering modified Fish Screen Slot Closure into the Fish Screen Slot and prior to installing Joint Fillers, grout, or other final closure preparation, video the Fish Screen Slot closures from the turbine intake side. Video submittals must showdocument edges of each Fish Screen Slot closure across the downstream interface between the Fish Screen Slot closure and the intake roof, as well as the leg guide pockets along each side of the guide slots. It must be possible to determine ifIn addition, video must show the Fish Screen Slot closures are completely lowered and seated in the Fish Screen Slots. Fish Screen Slot Closures must be completely lowered in the Fish Screen Slots, with no portion of the legs protruding beyond the face of the guide pocket, prior to commencing final closure preparation. See Section 05 12 00.00 28 STRUCTURAL STEEL, paragraph "Fish Slot Screen Inspection" for additional information. Final closure preparation shall not proceed until the above conditions are met.
b. Placement of backer rod material around entire closure perimeter as shown and specified.
c. Grout placement and confirmation grout is flush, at a minimum, with top of permanent Fish Screen Slot closure plug.
SECTION 01 11 01.00 28
G4EDHCMP
Line
d. Rebar installed as shown and specified.
e. Tremie concrete placed as shown and specified, and minimum concrete thickness is met.
f. Grout and/or concrete does not extend down beyond roof of intake.
All surfaces of intake roof, impacted by work on this contract, are ground smooth with no protruding surfaces that could be harmful to fish.
1.6.4 Remotely Operated Vehicle (ROV) Requirements
There is no diver access to the turbine intake if fish screen slot (FSS) screens or permanent closures are installed in the Fish Screen slots. When Fish Screen Slots are blocked, inspection of items in the intake must be accomplished by an ROV deployed down the intake bulkhead slot (see FIO Sheet I-010 for location). It has been confirmed by the Government that a VideoRay PRO 3XE will fit through the available space and can access this area. This information is provided solely for the Contractor's use in selecting an ROV of appropriate size for inspection of the work.
1.7 ADJUST FSS PERMANENT CLOSURE LEG LENGTH
a. Fish Screen Slot (FSS) Permanent Closures may require leg length adjustment after initial placement of closures in the FSS and prior to proceeding with final closure preparation (placement of backer rod material, grout, etc.). If, after initial video inspection of FSS Permanent Closure placement in the slot, the Contracting Officer determines additional leg length adjustment is required prior to final closure preparation, the Contractor shall do the following:
1. Remove Permanent Closure from the FSS.
2. Adjust leg lengths of Permanent Closure using prefabricated shims, as required. See Contract drawings for additional information on shims.
3. Return FSS Permanent Closure to the Fish Screen Slot.
4. Perform video inspection as specified in paragraph "Fish Screen Slot Permanent Closure Documentation"
b. This work will be performed only as directed and required by the Contracting Officer or approved representative. All FSS Permanent Closure Leg Length adjustments will be directed and observed by the Contracting Officer or approved representative. There shall be no change to the contract schedule associated with this work.
1.8 WATER TEMPERATURE
Temperature probes in the forebay record water temperatures to 30 meter depth. Historical data shows water temperatures at 30 meters dropping below 40 degrees Fahrenheit beginning mid to late December and running through the beginning of March, on average. Average minimum recorded temperatures during this time reach about 36 degrees F.
1.9 WATER SURFACE ELEVATION IN FISH SCREEN SLOTS DURING CONSTRUCTION
The Contractor shall not lower the Water Surface Elevation in the Fish
SECTION 01 11 01.00 28
G4EDHCMP
Line
Screens Slots to facilitate construction of the permanent closures. Water Surface Elevation in the Fish Screens Slots must not exceed ten feet above the forebay elevation.
1.10 FINAL WATER SURFACE ELEVATION IN FISH SCREEN SLOTS
Water surface elevation in all Fish Screen Slots must be within 0.5 feet of Elevation 736.0 fmsl upon project completion. Any water removed from the Fish Screen Slots must be treated as specified in Section 01 57 20.10 28 ENVIRONMENT PROTECTION, paragraphs "Water Treatment and Disposal" and/or DISPOSAL OF FISH SCREEN SLOT WATER AFTER TREMIE PLACEMENT, as applicable.
1.11 REGULAR CLEANUP AND DEBRIS DISPOSAL
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials shall become the property of the Contractor and shall be removed from the job site daily in accordance with Federal, State, and local regulations. The Contractor shall furnish waste containers, all waste containers provided by the contractor shall be emptied daily.
1.12 EQUIPMENT LIST
The Contractor shall furnish a complete list of all equipment to be used on the project 30 days prior to commencement of on-site work. The Contractor shall submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.13 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it shall be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks shall be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1.
Equipment shall be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
1.14 DISPOSITION OF REMOVED EQUIPMENT
Unless otherwise specified in other sections of the specifications, all existing equipment removed and not reinstalled shall become the property of the Contractor, removed from the Project site, and disposed of in a legal manner. Materials that cannot be removed daily may be temporarily stored on-site at an approved area. Salvaged materials shall not be sold on the project site.
1.15 FIRE CONTROL
Each piece of internal combustion engine driven equipment used at the work site shall be equipped with a fire extinguisher in accordance with recommendation NFPA as appropriate. The minimum approved rating of extinguishers shall not be less than 5-B:C.
SECTION 01 11 01.00 28
G4EDHCMP
Line
1.16 RIGGING AND LIFTING DEVICES
The Contractor shall be responsible for furnishing all rigging, spreader bars, lifting devices, etc. for use with the cranes. All rigging, lifting devices, etc. must meet requirements of EM 385-1-1.
1.17 FISH SCREEN SLOT SCREEN - LIFTING BEAM
a. The existing Fish Screen Slot Screen lifting beam will be available for Contractor use on this project, as applicable. See FIO drawings for beam information. At completion of this work, the lifting beam shall become the property of the Contractor, removed from the Project site, and disposed of in a legal manner.
b. The lifting beam was designed for installing existing Fish Screen Slot Screens. It has not been load tested or used since screens were originally installed. The Government will provide the lifting beam "as-is", with no guarantees on operation of latching mechanism, or other features. Contractor may use at their own risk. If damaged, the lifting beam will not be repaired by the Government.
1.18 PROTECTION AND RESTORATION OF EXISTING FACILITIES
The Contractor shall take precautions to prevent damage to existing facilities while performing work under this contract. Upon completion of the work, all the existing facilities not included as a portion of the work shall be left in a condition better than or equal to the condition existing at time of contract award. Costs for maintenance, repair and restoration of any facilities shall be considered as incidental to and included in the contract price.
1.19 PRE-WORK AND POST WORK SURVEYS
The Contractor shall conduct a pre-work survey prior to start of on-site work, and a post-work survey during project closeout, of the Government facilities at the proposed work areas. Surveys shall be conducted with the Contracting Officer Representative. The results of the surveys shall be documented by digital photographs and descriptive narrative reports. A color copy of the survey photographs and narrative reports shall be submitted to the Contracting Officer within 5 days after survey has been completed.
1.20 PROJECT SUPERINTENDENT
At all times during performance of this contract and until the work is completed and accepted the Contractor shall assign and have on the worksite a competent superintendent as per FAR Clause 52.236-6 "Superintendence by the Contractor". Submit Superintendent name and contact information prior to start of on-site construction.
1.20.1 Installation Supervisor
A representative of the Contractor who is technically qualified to supervise the removal of existing Fish Screen Slot and Wagner Horn screen components, as well as installation of Fish Screen Slot and Wagner Horn closures. The Project Superintendent may serve as the Installation Supervisor provided they meet requirements of this paragraph. The Installation Supervisor, or pre-approved substitute, shall be present at
SECTION 01 11 01.00 28
the work site at all times when screens are being removed or closures installed. The representative shall be available at all times and shall be experienced in work similar in nature to that required by this project.
The representative shall report immediately in writing to the Contracting Officer any work not in accordance with project requirements or any special conditions which may result in an unsatisfactory job. The representative shall have supervised work similar in scope and nature of at least 2 projects within the past 5 years. Installation supervisor's resume shall be submitted to the Contracting Officer.
1.21 INSTALLATION SUPERVISOR
A representative of the Contractor who is technically qualified to supervise the removal of existing Fish Screen Slot and Wagner Horn screen components, as well as installation of Fish Screen Slot and Wagner Horn closures. The Installation Supervisor, or pre-approved substitute, shall be present at the work site at all times when screens are being removed or closures installed. The representative shall be available at all times and shall be experienced in work similar in nature to that required by this project. The representative shall report immediately in writing to the Contracting Officer any work not in accordance with project requirements or any special conditions which may result in an unsatisfactory job. The representative shall have supervised work similar in scope and nature of at least 2 projects within the past 5 years. Installation supervisor's resume shall be submitted to the Contracting Officer.
1.21 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (Project Superintendent, Installation Supervisor, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer. Personnel shall possess the qualifications that meet or exceed those stated in the specifications for the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement.
1.22 POST AWARD MEETINGS
1.22.1 Pre-Work Meeting
Within 15 days after receipt of Notice to Proceed, the Contractor shall attend a Pre-Work meeting. Senior Level members of the Contractor's staff involved with this contract shall participate in this meeting to discuss the overall contract requirements. The Government will lead this meeting and take the meeting minutes.
1.22.2 Pre-Construction Meeting
The Project Superintendent shall coordinate with the Contracting Officer and establish the date of the Pre-Construction Meeting. The meeting will be held at the project site at least one (1) week prior to mobilizing to the job site. The Project Superintendent shall lead the Pre-Construction Meeting discussing the Contractor's plan on executing the work at the project site, schedule, required clearances and timeframe for them, and plan for implementing safety and quality control. The Government will have key members from the Project staff to discuss environmental and clearance issues. Key members of the contractor staff shall attend this meeting including the Quality Control (QC) System Manager, Site Safety and Health Officer (SSHO) and any other members determined by the Government to be
SECTION 01 11 01.00 28
required.
1.22.2.1 Minutes
The Project Superintendent shall be responsible for taking the meeting minutes and shall send them electronically within 48 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.22.2.2 Demobilizing And Remobilizing
Anytime the Contractor demobilizes from the site and remobilizes at a later date, another Pre-Construction meeting shall be held and shall follow the requirements listed above.
1.23 WEEKLY PRODUCTION MEETINGS
During all onsite construction work the Project Superintendent shall lead a weekly production meeting using the attached "Weekly Meeting Agenda Template " to brief the Government on the status of the project. All elements listed in the agenda shall be thoroughly discussed. For example, the Project Superintendent shall provide the Government a three (3) week "look-ahead" that describes all the planned construction activities, onsite and offsite, over the next three (3) weeks. These activities shall align to the overall construction schedule submitted under SECTION 01 32 01.10 28 PROJECT SCHEDULE, and if the three (3) week "look-ahead" differs from the construction schedule, the construction schedule shall be updated to include these changes by the next scheduled update. Key members of the Contractor's staff shall attend this meeting, including the Quality Control System Manager, who is responsible for discussing QC aspects of the work as outlined under SECTION 01 45 04.00 28 CONTRACTOR QUALITY CONTROL and SSHO.
The Government reserves the right to require any person from the Contractor's staff, such as the Project Manager, Engineer, scheduler, etc., or key subcontractor personnel to attend this meeting, if Government feels their participation is required.
1.23.1 Minutes
The Project Superintendent shall be responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.24 ADDITIONAL MEETINGS
The Contractor shall record the minutes of all meetings, including all conference calls, that occur between the Contractor and Government, unless otherwise specified. Minutes shall be sent electronically within 24 hours of the meeting to the Contracting Officer for concurrence. E-mail subject line shall include project name and meeting topic.
1.25 PARTNERING
1.25.1 General
The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors by informally partnering this contract. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance and intended to achieve completion within budget, on schedule, and in accordance with plans and specifications. This partnership would be bilateral in makeup and participation will be totally voluntary. If Partnering is pursued, meetings would be held as identified in the following paragraph.
1.25.2 Partnering Meetings
Within 30 days of receipt of Notice to Proceed, the initial partnering meeting will be scheduled. The Contractor's key personnel will attend a face-to-face partnering meeting (typically one day in duration) together with key Government personnel, to discuss project goals and communication.
Follow-up meetings will be held periodically, as required, throughout the duration of the contract, as agreed to by the Contractor and the Government.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
This page intentionally left blank
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 PROJECT SECURITY
1.2.1 Vehicle Access
1.2.2 Identification of Employees
1.2.3 Delivery of Equipment
1.3 FACILITY OCCUPANCY CLOSURE
1.4 WORK SCHEDULES
1.4.1 Contractor's Work Schedule
1.4.2 Government's Work Schedule
1.5 ROADWAY CLOSURE DELAYS
1.6 BOAT RESTRICTED ZONE POLICY (BRZ)
1.7 USE OF WALLA WALLA DISTRICT PARKS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
ATTACHMENTS:
Security Badge Form
Boat Restricted Zone (BRZ) Policy
-- End of Section Table of Contents --
SECTION 01 14 00.10 28
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 PROJECT SECURITY
The Project site is a secured area and access onto the Project is restricted. The security measures affect all of the Contractor's vehicles and personnel. There will be delays when entering Projects due to locked gates, vehicle inspections, and personnel checks. Inspections and checks may include inspection of tool boxes, brief cases, lunch boxes, and other containers.
1.2.1 Vehicle Access
Only Contractor's work vehicles and equipment that are essential to the conduct of the work will be allowed in any work areas. No privately owned vehicles (POV's) will be allowed. All Contractor vehicles shall display suitable permanent or temporary identification. All Contractor vehicles that pass through locked gates will be subject to being searched.
1.2.2 Identification of Employees
a. The Government (Project personnel) will provide the Contractor's personnel with identification badges as they arrive on site. For each employee, the Contractor shall complete the Security Badge Form (attached to the end of this SECTION), and send the employee's picture and last 4 digits of the employee's social security number to the Contracting Officer's Representative and Quality Assurance Representative. Include each employee's full name with middle initial. The information must be received at least 30 calendar days before the employee arrives at the site to give project personnel time to make up the badge. The Contractor shall be responsible for furnishing initial identification for each employee, and upon issuance of official badges, for requiring each employee engaged on the work to display identification at all times. All prescribed identification shall immediately be delivered to the Quality Assurance Representative for cancellation upon the release of the employee or project completion. If required by the Contracting Officer, employees will be photographed by the Government. Employees who fail to submit to photographing will not be allowed on the project site.
SECTION 01 14 00.10 28
b. Every Contractor employee (prime or subcontractor) shall have a hard hat meeting the requirements of EM 385-1-1. Hardhats shall display the Prime Contractor name, subcontractor name, and the employee's name.
Contractor employee hardhats shall not be white with red markings. It shall be the responsibility of the Project Superintendent to enforce this requirement.
1.2.3 Delivery of Equipment
Contractor is responsible for delivery and receipt of all materials and equipment. Government personnel will not be available to assist contractor in these activities. To the maximum extent possible, deliveries shall arrive on the same side of the river as the Contractor's work area.
Delivery vehicles will be allowed to cross the river over the dam only with Government approval. Delivery vehicles arriving on the opposite side of the river as the work area shall be unloaded outside the locked gate, equipment shall be loaded onto Contractor's vehicles, and Contractor's vehicles will then be allowed to cross the dam to the work area.
1.3 FACILITY OCCUPANCY CLOSURE
Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer.
1.4 WORK SCHEDULES
1.4.1 Contractor's Work Schedule
At the Pre-Work Meeting, furnish a schedule of number of working days per week, shifts per day, and hours per shift for contract work. The Contractor shall furnish notification of any change of schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site. This notification shall be provided a minimum of 48 hours prior to any schedule change to allow suitable scheduling of Government personnel and inspection. Exception to this requirement may be allowed in case of schedule change due to emergency conditions.
1.4.2 Government's Work Schedule
The maintenance crews at the dam work from 6:30 a.m. to 5:00 p.m., Monday through Thursday. Crews and staff do not work on weekends and Federal holidays. If a Federal holiday falls on a Friday, the crews and staff do not work on the preceeding Thursday. A powerhouse operator is at the site 24 hours a day, 7 days a week, including Federal holidays but is not available to assist the Contractor.
If the Contractor requires Government support or assistance outside of normal work hours, the Contractor must make a formal written request to the Contracting Officersubmit request to the COR at least onetwo weeks prior to the date that support/assistance is needed, to allow for coordination. The Government will review this request, but there is no guarantee that Government support or assistance can be provided.
1.5 OTHER CONTRACTS
The Government may award other contracts for additional work to be performed in the vicinity of this work. The work area and restrictions and
SECTION 01 14 00.10 28
G4EDHCMP
Line limitations caused by the work to be performed by others shall be considered by the Contractor in scheduling work to be performed. No allowance will be made for damage or extra compensation because of the required cooperation.
1.5.1 Roadway Closure Delays
It is possible that other contract work may close the roadways near the dam to all vehicles in order to accomplish work requirements.