SOLICITATION NO. W912EE-18-B-0015

DATE: 27 July 2018

SPECIFICATIONS

FOR

FC/MR&T, BIG SUNFLOWER RIVER BASIN, BIG

SUNFLOWER RIVER, WASHINGTON AND BOLIVAR

COUNTIES, MS, SEDIMENT REDUCTION

STRUCTURES, PHASE IV

THIS PROCUREMENT IS 100% WOMAN

OWNED SMALL BUSINESS SET-ASIDE

Building Strong

Serving the Army

Serving the Nation

VICKSBURG DISTRICT

4155 CLAY STREET

VICKSBURG, MS 39183-3435

INQUIRIES

REGARDING THIS SOLICITATION SHOULD

BE MADE TO THE FOLLOWING:

http://www.projnet.org/projnet

PLANS AND SPECIFICATIONS AVAILABLE ON THE FEDERAL

BUSINESS OPPORTUNITIES (FBO) WEB PAGE AT

http://www.fedbizopps.gov/.

http://www.projnet.org/projnet http://www.fedbizopps.gov/

W912EE-18-B-0015

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SOLICITATION, OFFER, AND AWARD (SF1442)

00010 BIDDING SCHEDULE

00100 INSTRUCTIONS TO BIDDERS

00600 REPRESENTATIONS AND CERTIFICATIONS

00700 CONTRACT CLAUSES

00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS

01 22 00.00 09 MEASUREMENT AND PAYMENT

01 33 00 SUBMITTAL PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 09 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 04.00 09 CONTRACTOR QUALITY CONTROL

01 45 05.00 09 MILESTONE COMPLIANCE REVIEW PROCEDURE (MCRP)

01 57 20.00 09 ENVIRONMENTAL PROTECTION

01 57 23.00 09 STORM WATER POLLUTION PREVENTION PLAN

DIVISION 05 - METALS

05 60 00.00 09 WELDING

DIVISION 13 - SPECIAL CONSTRUCTION

13 60 00.00 09 MISCELLANEOUS ITEMS

DIVISION 31 - EARTHWORK

31 06 00.00 09 ENGINEERING FABRIC

31 11 00.00 09 CLEARING AND GRUBBING

31 23 03.00 09 EXCAVATION, BACKFILL, FILL, AND CONTROL OF WATER

31 32 13.19 09 LIME TREATMENT

31 37 00.00 09 STONE PROTECTION FOR STRUCTURES

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 92 02.00 09 EROSION CONTROL

DIVISION 33 - UTILITIES

33 42 29.00 09 CORRUGATED METAL PIPE

-- End of Project Table of Contents –

PROJECT TABLE OF CONTENTS Page 1

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

W912EE18B0015

2. TYPE OF SOLICITATION 3. DATE ISSUED

27-Jul-2018

PAGE

X SEALED BID (IFB)

NEGOTIATED (RFP)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

W807PM81669102

6. PROJECT NO.

7. ISSUED BY CODE W912EE 8. ADDRESS OFFER TO (If Other Than Item 7) CODE

VICKSBURG CONTRACTING OFFICE

4155 CLAY ST

VICKSBURG, MS 39183-3435

SEE SPECIAL NOTICES TO BIDDERS

9. FOR INFORMATION

CALL:

A. NAME

AMY L. STARKS

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

601-631-5693

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

WASHINGTON AND BOLIVAR COUNTIES, MS

BIG SUNFLOWER SEDIMENT REDUCTION STRUCTURES PHASE IV

FC/MR&T, BIG SUNFLOWER RIVER BASIN

BIG SUNFLOWER RIVER

DESCRIPTION OF WORK: The work consists of furnishing all plant, labor, materials and equipment, constructing seven (7) riser pipe grade control structures in Washington and Bolivar Counties, Mississippi. Principal features of the work include clearing and grubbing, excavation, fill, backfill, embankment, miscellaneous items, control of water, engineering fabric, stone protection, corrugated metal pipe, erosion control, lime treatment, welding, concrete work, storm water pollution prevention and environmental protection.

The estimated value of the proposed work is between $1,000,000 and $5,000,000.

11. The Contractor shall begin performance within 10 calendar days and complete it within See section 00 80 00.00 09 1.1.1 calendar days after award, X notice to proceed. This performance period is X mandatory, negotiable. (See Section 00 80 00.00 09)

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12B. CALENDAR DAYS

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed Offers in original copy to perform work required are due at the place specified in Item 8, by 1430 (hour) local time 04 SEP 2018 . If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

SOLICITATION, OFFER, AND AWARD (Continued)

(Construction, Alteration, or Repair)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

TAX ID: See Item 14

CAGE CODE DUNS NUMBER:

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within _ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

20B. SIGNATURE 20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

SEE SCHEDULE

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

96X3112

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY CODE

VICKSBURG CONTRACTING OFFICE

4155 CLAY STREET

VICKSBURG, MS 39183-3435

US ARMY CORPS OF ENGRS FINANCE CENTER

5722 INTEGRITY DRIVE

MILLINGTON, TN 39054-5005

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this 29. AWARD ( Contractor is not required to sign this document.)

document and return _ copies to issuing office.) Contractor agrees Your offer on this solicitation, is hereby accepted as to the items listed. This award con-to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by refer-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print) summates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE 30C. DATE 31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

NSN 7540-01-155-3212 STANDARD FORM 1442 BACK (REV. 4-85)

Section 00100 - Bidding Schedule/Instructions to Bidders

BIDDING SCHEDULE

WASHINGTON AND BOLIVAR COUNTIES, MS

BIG SUNFLOWER SEDIMENT REDUCTION STRUCTURES PHASE IV

FC/MR&T, BIG SUNFLOWER RIVER BASIN

BIG SUNFLOWER RIVER

ITEM DESCRIPTION

EST

QTY U/M

UNIT

PRICE AMOUNT

0001 BS17-BP-20 1 JOB FOR $___________

0002 BS17-BP-23 1 JOB FOR $___________

0003 BS17-BP-23B 1 JOB FOR $___________

0004 BS17-BP-27 1 JOB FOR $___________

0005 BS17-BP-47 1 JOB FOR $___________

0006 BS17-BPC-55 1 JOB FOR $___________

0007 BS17-BPC-55B 1 JOB FOR $___________

TOTAL $___________

NOTES:

(a) THIS PROCUREMENT IS A WOMAN OWNED SMALL BUSINESS (WOSB) SET-ASIDE.

(b) All technical inquiries and questions relating to this solicitation are to be submitted via bidder Inquiry in ProjNet at http://www.projnet.org/projnet. See Section 00100 Paragraph 16 Entitled

“TECHNICAL INQUIRIES AND QUESTIONS”.

(c) Lack of registration in the SAM database will make a bidder ineligible for award. SEE CONTRACT CLAUSE 52.204-7 ENTITLED "System for Award Management”.

(d) Bidders shall furnish unit prices for all items listed on the schedule of bid items which require unit prices. If the bidder fails to insert a unit price in the appropriate blank for required items, but does furnish an extended total or an estimated amount for such items, the Government will deem his unit price to be the quotient obtained by dividing the extended estimated amount for that line item by the quantity. IF THE BIDDER OMITS BOTH

THE UNIT PRICE AND THE EXTENDED ESTIMATED AMOUNT FOR ANY ITEM, HIS BID WILL

BE DECLARED NONRESPONSIVE.

(e) All quantities shown on the BIDDING SCHEDULE are estimated quantities except when the unit of measure is shown as "job" (JB) or "each". For Federal Acquisition Regulations (FAR) and FAR supplement reference purposes, ‘job’ can be used in the place of ‘lump sum’.

(f) If a bid or modification to a bid based on unit price is submitted which provides for a “job” adjustment to the total estimated cost, the application of the “job” adjustment to the unit price in the schedule must be stated. If it is not stated, the bidder agrees that the “job” adjustment shall be applied on a pro rata basis to the unit price in the Bid Schedule.

(g) All extensions of the unit price shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the bid.

(h) Award will be made as a whole to the lowest responsive, responsible bidder as may be in the best interest of the Government.

(i) THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Program, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.

(j) VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS.

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/ Department of Veterans Affairs-VOW to Hire Heros Act http://benefits.va.gov/vow/ Army Wounded Warriors Program-http://wtc.army.mil/modules/employers/index.html U.S. Chamber of Commerce Foundation-Hiring Our Heros http://www.hiringourheroes.org/ Guide to Hiring Veterans-Reference Material http://www.whitehouse.gov/sites/default/files/docs/white_house_business_counc il_-_guide_to_hiring_veterans_0.pdf

1. INVITATION FOR BIDS (IFB) NO. W912EE-18-B-0015

FOR: FC/MR&T, BIG SUNFLOWER RIVER BASIN, BIG SUNFLOWER RIVER,

WASHINGTON AND BOLIVAR COUNTIES, MS, SEDIMENT REDUCTION

STRUCTURES, PHASE IV

TO OPEN: 04 September 2018, 1430 HOURS, LOCAL TIME AT PLACE OF

BID OPENING

BID OPENING MAY BE ATTENDED IN PERSON OR VIEWED ONLINE AT

http://www.mvk.usace.army.mil/BusinessWithUs/Contracting.aspx.

BIDDERS MUST PROVIDE FULL, ACCURATE AND COMPLETE INFORMATION AS

REQUIRED BY THIS SOLICIATION AND ITS ATTACHMENTS. THE PENALTY

FOR MAKING FALSE STATEMENTS IN BIDS IS PRESCRIBED IN 18 U.S.C.

1001. (FAR 52.214-4 APR 1984)

SEALED BIDS FOR THE WORK DESCRIBED HEREIN WILL BE RECEIVED UNTIL

DATE AND TIME OF BID OPENING.

2. THIS PROCUREMENT IS A 100% WOMAN OWNED SMALL BUSINESS (WOSB)

SET-ASIDE.

3. TECHNICAL ISSUES WILL BE MANAGED VIA PROJNET (SEE PARAGRAPH

15 BELOW).

4. YOUR ATTENTION IS DIRECTED TO SECTION 00100-BID

SCHEDULE/INSTRUCTIONS TO BIDDERS CLAUSE ENTITLED “SUBMISSION OF

BIDS”. IT IS THE BIDDER’S RESPONSIBILITY TO ENSURE THAT BIDS

SENT BY COMMERCIAL CARRIER ARE CLEARLY IDENTIFIED AS CONTAINING

A SEALED BID ON THE OUTERMOST ENVELOPE. THIS INCLUDES, BUT IS

NOT LIMITED TO, BIDS SENT VIA: FEDERAL EXPRESS, AIRBORNE

EXPRESS, EXPRESS COURIER SERVICES, INC., EXPRESS MAIL - U.S.

POSTAL SERVICE, UNITED PARCEL SERVICE AND PUROLATOR.

5. NOTE THE AFFIRMATIVE ACTION REQUIREMENT OF THE EQUAL

OPPORTUNITY CLAUSE WHICH MAY APPLY TO THE CONTRACT RESULTING

FROM THIS SOLICITATION.

6. NOTE THE AFFIRMATIVE ACTION REQUIREMENT OF THE CONTRACT

CLAUSE ENTITLED, “AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR

CONSTRUCTION”, WHICH WILL APPLY TO THE CONTRACT RESULTING FROM

THIS SOLICITATION.

7. SEE SECTION 00 80 00.00 09, SPECIAL CONTRACT REQUIREMENTS,

CLAUSE ENTITLED “COMMENCEMENT, PROSECUTION, AND COMPLETION OF

THE WORK (APR 1984)”.

8. SEE SECTION 01 00 00.00 09, GENERAL CONTRACT REQUIREMENTS

CLAUSE, ENTITLED, “PAYMENT INVOICES” WHICH WILL APPLY TO THE

CONTRACT RESULTING FROM THIS SOLICITATION. THE FEDERAL

ACQUISITION REGULATION REQUIRES THAT THE “REMIT TO” ADDRESS OF

THE INVOICE MATCH THE “REMIT TO” ADDRESS ON THE CONTRACT OR A

PROPER NOTICE OF ASSIGNMENT.

09. MAIL BIDS TO THE VICKSBURG DISTRICT HEADQUARTERS BUILDING,

4155 CLAY STREET, VICKSBURG, MISSISSIPPI 39183-3435. BIDS SENT

BY COMMERCIAL CARRIER SHALL BE CLEARLY MARKED ON THE OUTER

ENVELOPE AS CONTAINING A “SEALED BID”. BIDS MUST BE RECEIVED

PRIOR TO THE EXACT TIME SET FOR BID OPENING.

10. HAND CARRIED BIDS MUST BE DELIVERED TO THE VICKSBURG

DISTRICT HEADQUARTERS BUILDING, 4155 CLAY STREET, VICKSBURG,

MISSISSIPPI 39183-3435. ALL BIDS MUST BE RECEIVED PRIOR TO THE

EXACT TIME SET FOR BID OPENING. NOTE: BIDS DELIVERED LATER THAN

15 MINUTES PRIOR TO THE TIME SET FOR THE BID OPENING SHALL BE

DELIVERED DIRECTLY TO ROOM 103, BID OPENING ROOM.

11. BIDS WILL NOT BE ACCEPTED NOR SHALL BIDS BE WITHDRAWN

TELEGRAPHICALLY OR BY ELECTRONIC COMMERCE.

12. IN ACCORDANCE WITH THE PROVISIONS OF SUBPART 36.201

(EVALUATION OF CONTRACTOR PERFORMANCE) OF THE FEDERAL

ACQUISITION REGULATION (FAR), CONSTRUCTION CONTRACTOR’S

PERFORMANCE SHALL BE EVALUATED THROUGHOUT THE PERFORMANCE OF THE

CONTRACT. THE UNITED STATES ARMY CORPS OF ENGINEERS (USACE)

FOLLOWS THE PROCEDURES OUTLINED IN ENGINEERING REGULATION 415-1-

17 TO FULFILL THIS FAR REQUIREMENT. FOR CONSTRUCTION CONTRACTS

AWARDED AT OR ABOVE $100,000.00, THE USACE WILL EVALUATE

CONTRACTOR’S PERFORMANCE AND PREPARE A PERFORMANCE REPORT USING

THE CONSTRUCTION CONTRACTOR APPRAISAL SUPPORT SYSTEM (CCASS),

WHICH IS NOW A WEB-BASED SYSTEM. AFTER AN EVALUATION (INTERIM

OR FINAL) IS WRITTEN UP BY THE USACE, THE CONTRACTOR WILL HAVE

THE ABILITY TO ACCESS, REVIEW AND COMMENT ON THE EVALUATION FOR

A PERIOD OF 30 DAYS. ACCESSING AND USING CCASS REQUIRES

SPECIFIC SOFTWARE, CALLED PKI CERTIFICATION, WHICH IS INSTALLED

ON THE USER’S COMPUTER. THE CERTIFICATION IS A DEPARTMENT OF

DEFENSE REQUIREMENT AND WAS IMPLEMENTED TO PROVIDE SECURITY IN

ELECTRONIC TRANSACTIONS. THE CERTIFICATION SOFTWARE COULD COST

APPROXIMATELY $110 - $125 PER CERTIFICATE PER YEAR AND IS

PURCHASED FROM AN EXTERNAL CERTIFICATE AUTHORITIES (ECA) VENDOR.

CURRENT INFORMATION ABOUT THE PKI CERTIFICATION PROCESS AND FOR

CONTACTING VENDORS CAN BE FOUND ON THE WEB SITE:

http://www.cpars.navy.mil/. IF THE CONTRACTOR WISHES TO

PARTICIPATE IN THE PERFORMANCE EVALUATION PROCESS, ACCESS TO

CCASS AND PKI CERTIFICATION IS THE SOLE RESPONSIBILITY OF THE

CONTRACTOR.

13. ELECTRONIC FUNDS TRANSFER (EFT)

PURSUANT TO FAR 52.232-5 AND 52.232-33, ALL PAYMENTS UNDER THIS CONTRACT WILL BE MADE BY

ELECTRONIC FUNDS TRANSFER (EFT). CONTRACTORS ARE REQUIRED TO COMPLETE FORM:

UFC-DISB-4.

THE FORM AND COMPLETION INSTRUCTIONS MAY BE DOWNLOADED FROM THE U. S. ARMY CORPS

OF ENGINEERS FINANCE CENTER AT: HTTP://WWW.FC.USACE.ARMY.MIL (CLICK ON "DIRECTORATES"

AT THE TOP OF THE PAGE, THEN CLICK ON "DIRECTORATE OF ACCOUNTING OPERATIONS" AND

THEN “EFT DIRECT DEPOSIT FORM”)

THE “INSTALLATION EROC” FOR THE VICKSBURG CONSOLIDATED CONTRACTING OFFICE IS “B4."

14. TECHNICAL INQUIRIES AND QUESTIONS

ALL Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet (https://www.projnet.org) no later than 5 days prior to bid opening date in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team. All timely questions and approved answers will be made available through ProjNet. Approved answers to all timely questions will also be posted on the FedBizOps in the form of a report generated from ProjNet as soon as the comment/question entering period is over and all answers are all finalized.

THE SOLICITATION NUMBER IS: W912EE-18-B-0015

THE BIDDER INQUIRY KEY IS: J838IE-H57788

Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

THE CALL CENTER OPERATES WEEKDAYS FROM 8AM TO 5PM U.S. CENTRAL

TIME ZONE (CHICAGO). THE TELEPHONE NUMBER FOR THE CALL CENTER IS

800-428-HELP.

15. PRIOR TO BID OPENING, IN ACCORDANCE WITH FEDERAL

ACQUISITION REGULATION PART 14.303 (b) MODIFICATION OR

WITHDRAWAL OF BIDS, “A BID MAY BE WITHDRAWN IN PERSON BY A

BIDDER OR ITS AUTHORIZED REPRESENTATIVE IF, BEFORE THE EXACT

TIME SET FOR OPENING OF BIDS, THE IDENTITY OF THE PERSONS

REQUESTING WITHDRAWAL IS ESTABLISHED AND THAT PERSON SIGNS A

RECEIPT FOR THE BID."

THE FOLLOWING STEPS WILL BE REQUIRED BY THE VICKSBURG

CONTRACTING OFFICE:

1) CONTRACTOR MUST PRESENT A LETTER VERIFYING THEY ARE A

REPRESENTATIVE OF THE COMPANY.

2) CONTRACTOR MUST SHOW VALID PICTURE ID.

3) VICKSBURG DISTRICT CONTRACTING OFFICE WILL HAVE THE

REPRESENTATIVE SIGN A RECEIPT FOR BID.

GENERAL NOTICES

1. AUTHORITY & APPROPRIATION INFORMATION PROGRAM DATA

AUTHORITY: Flood Control Act of 1944, 1950, 1962 and 1965 APPROPRIATION: Consolidated Appropriations Act, 2018 PL 115-141

FUNDING CITATION: 96X3112

2. NEGOTIATIONS AFTER SEALED BIDDING.

The Government has the option to reject all bids received in response to the sealed bid advertisement and initiate negotiation. Negotiations will include soliciting offers from each responsible bidder that submits a bid in response to the Invitation for Bids. If, after bid opening, the Contracting Officer determines that negotiations are in the best interest of the Government, the following steps will be followed:

(a) An amendment to the sealed bid advertisement will be issued to each responsible bidder changing the Invitation for Bids Number to Request for Proposals Number. The amendment will also make any necessary changes to the scope of the work.

(b) A cover letter signed by the negotiator will accompany the amendment explaining the procedures to be followed during negotiations.

3. BID GUARANTEE, PERFORMANCE AND PAYMENT BONDS.

A bid guarantee is required with bid package and is to be executed on Standard Form SF24. Performance and payment bonds will be required after award. See Section 00700, Contract Clauses 52.228-1, BID GUARANTEE and 52.228-15, PERFORMANCE AND

PAYMENT BONDS -- CONSTRUCTION

4. AMENDMENTS PRIOR TO DATE SET FOR OPENING BIDS.

The right is reserved, as the interest of the Government may require, to revise or amend the specifications and/or drawings prior to the date set for opening bids. Such revisions or amendments, if any, will be announced by amendment or amendments to this Invitation for Bids. Copies of such amendments as may be issued will be furnished to all prospective bidders. If the revision or amendments are of a nature which require material changes in quantities or prices bid or both, the date set for opening bids may be postponed by such number of days as in the opinion of the District Engineer will enable bidders to revise their bids. In such case, the amendments will include an announcement of the new date for opening bids.

5. BUSINESS INTEGRITY.

The apparent successful bidder as a condition for award of any contract resulting from this solicitation may be required to execute a certificate related to Business Integrity.

6. CONDITIONS AFFECTING THE WORK.

Bidders should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, and the general and local conditions which can affect the work or the cost thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The Government will assume no responsibility for any understanding or representations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the Invitation for Bids, the specifications, or related documents.

7. BIDDER'S QUALIFICATIONS/Pre Award Survey.

A determination of contractor responsibility will be made. A determination of non-responsibility may be cause for the rejection of a prospective contractor's bid. In accordance with FAR 9.104-1 - General Standards, before a bid is considered for award, the bidder shall be requested by the Government to submit a statement regarding their previous experience in performing comparable work, their business and technical organization, financial resources, the plant available to be used in performing the work and/or other information necessary to make the determination of contractor responsibility.

8. SITE OF THE WORK.

Bidders are advised that for purpose of applicability of the Davis-Bacon Act and other contract labor standard provisions, "the site of the work" under the contract to be awarded pursuant to this Invitation may not be limited to the physical place(s) where the construction called for in the contract will remain when work on it has been completed. The "site of the work" may include other adjacent or nearby property used by the Contractor or Subcontractors during such construction. For example, fabrication plants, mobile factories, batch plants, borrow pits, job headquarters, tool yards, etc., will be considered part of the site of the work provided they are dedicated exclusively or nearly so to performance on the contract and are so located in proximity to the actual construction location that it would be reasonable to include them.

9. INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE, AND

BONDS.

a. Specifications, Invitation No. W912EE-18-B-0005, Bidding Schedule, Construction Contract Clauses, and Wage Determination Decisions No. MS180001 01/05/2018 MS1 of the Secretary of Labor, are parts of this Invitation.

b. (1) An offeror (bidder) electing to use individual sureties for either bid guarantees or performance and payment bonds must submit, concurrently with the bonds and required affidavits, a statement of both the business and personal names of the persons and/or brokerages firms through whom the bonds or the guarantees were obtained, together with the address and telephone number of the persons and/or brokerage firms.

(2) Offerors or bidders should note that some individual sureties and brokers of individual sureties have been debarred or suspended from offering themselves or others as sureties to the Government. Offerors or bidders are responsible for ascertaining the current status of their sureties and brokers.

(3) Failure to provide the required information or the submission of bid guarantees obtained from debarred or suspended sureties or brokers may cause rejection of the offer (bid).

10. DEFINITIONS

(a) The term "head of the agency" or "Secretary" as used herein means the Secretary of the Army; and the term "his duly authorized representative" means the Chief of Engineers, Department of the Army, or an individual or board designated by him.

(b) "Contracting Officer" means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the Contracting Officer acting within the limits of their authority as delegated by the Contracting Officer.

(c) The agency board of contract appeals having jurisdiction over all appeals from final decisions of the Contracting Officer under the Contract Disputes Act of l978 is the Armed Services Board of Contract Appeals, addressed as follows: Recorder, Armed Services Board of Contract Appeals, Skyline 6, 7th Floor, 5109 Leesburg Pike, Falls Church, Virginia 22041-3208.

(d) "Small business concern" means a concern including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria and size standards in 13 CFR 121.

(1) Size Standards for Construction and Special Trades.

(a) Construction. A concern is small if its average annual receipts for its preceding 3 fiscal years did not exceed $36.5 million.

(b) Dredging. A concern is small if (1) its average annual receipts for its preceding 3 fiscal years did not exceed $27.5 million, and (2) at least 40 percent of the yardage in the contract's plans and specifications is dredged with equipment owned by the concern or obtained from another small business dredging concern.

CLAUSES INCORPORATED BY REFERENCE

52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.236-7 Permits and Responsibilities NOV 1991

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a FIRM FIXED PRICE contract resulting from this solicitation.

(End of provision)

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY (FEB 1999).

a. The Offeror's attention is called to the Equal Opportunity and the

Affirmative Action Compliance Requirements for Construction clauses of this solicitation.

b. The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade all construction work in the covered area, are as follows:

Economic Area

Goals for Minority Participation for Each Trade

Goals for Female Participation for Each Trade

Memphis, Tennessee Non-SMSA (Non-Standard Metropolitan Statistical Area) Counties

26.5%

6.9

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

c. As used in this Notice, and in any contract resulting from this

Solicitation, the “covered area” is: Memphis, Tennessee, Non-SMSA Counties, which includes Sunflower, Tallahatchie, Bolivar, and Coahoma Counties, Mississippi.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

USACE, VICKSBURG DISTRICT

CONTRACTING OFFICER

CEMVK-CT-C

4155 CLAY STREET

VICKSBURG, MS 39180

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting: (8:00 a.m. to 4:45 p.m., Monday through Friday CST) by contacting:

Mr. Jason Overstreet Project Engineer Greenwood Area Office 100 Moore Street Greenwood, MS 38930-4512

(662) 453-5531

GAO@usace.army.mil.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil/

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any (48 CFR Chapter) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

WAGE RATES

Attachments(s):

General Decision Number: MS180001 01/05/2018 MS1

Superseded General Decision Number: MS20170001

State: Mississippi

Construction Type: Heavy Flood Control

Counties: Mississippi Statewide.

*RIVER, HARBOR AND FLOOD CONTROL PROJECTS FOR CONSTRUCTION OF

ALL RIVER, HARBOR AND FLOOD CONTROL WORK ON THE MISSISSIPPI

RIVER AND TRIBUTARIES -(EXCLUDING ANY CONTRACTS FOR ANY PHASE

OF CONSTRUCTION OF A LOCK AND DAM) MISSISSIPPI - EXCEPT THE

METROPOLITAN AREAS OF GREENVILLE, NATCHEZ AND VICKSBURG

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.

Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2018

* SUMS1991-004 12/18/1991

Rates Fringes

CARPENTER........................$ 7.25

Laborers:

AIR TOOL OPERATOR...........$ 7.25

CHAIN SAW OPERATOR OR FILER.$ 7.25

REVETMENT & DIKES...........$ 7.25

UNSKILLED...................$ 7.25

Power equipment operators:

ASPHALT PLANT DRYER

OPERATOR, ASPHALT

DISTRIBUTOR, ASPHALT

ROLLER, BULLDOZER (ROUGH,

INCLUDING DISC, PLOW, OR

ROLLER), MOTOR PATROL

(HAUL ROADS), TRENCHING

MACHINE (18" & UNDER),

SELF-PROPELLED ROLLER

(EXCEPT ASPHALT, END DUMP

EQUIPMENT (OFF HIGHWAY),

MIXER (CONCRETE UP TO 21

CU. FT.), BOTTOM DUMP

EUCLIDS (& LIKE EQUIPMENT)..$ 7.25 .05

BULLDOZER (FINISHER, PUSH

CAT & ON BARGES), MOTOR

PATROL FINISHER, SCRAPER &

LIKE EQUIPMENT, FRONT END

LOADER, BACKHOE (TRACTOR

MOUNTED) ASPHALT FINISHER

OR SPREADING MACHINE, WELL

POINT SYSTEM OPERATOR,

SELF PROPELLED LOADER

(CONVEYOR TYPE).............$ 7.25 .05

FIREMAN (HEAVY

CONSTRUCTION), PILEDRIVER,

LEADSMAN, WINCHMAN..........$ 7.25 .05

OILER, PUMP, GREASER,

TRACTOR (FARM TYPE

INCLUDING DISC, PLOW OR

ROLLER).....................$ 7.25 .05

PILEDRIVER OPERTOR,

MECHANIC (HEAVY

EQUIPMENT), CRANES,

DERRICKS, DRAGLINES,

WELDER, POWER SHOVELS &

BACKHOES, MIXER (CONCRETE,

21 CU. FT. & OVER),

ASPHALT PLANT OPERATOR,

TRENCHING MACHINE (OVER

18")........................$ 7.75 .05

Truck drivers:

1 1/2 TONS OR LESS..........$ 7.25

OVER 1 1/2 TONS.............$ 7.25

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

Section 00600 - Representations & Certifications

52.204-3 Taxpayer Identification OCT 1998 52.225-25 Prohibition on Contracting with Entities Engaging in Certain

Activities or Transactions Relating to Iran-- Representation and Certifications.

OCT 2015

52.204-5 WOMEN-OWNED BUSINESS (OTHER THAN SMALL BUSINESS) (OCT 2014)

(a) Definition. Women-owned business concern, as used in this provision, means a concern that is at least 51 percent owned by one or more women; or in the case of any publicly owned business, at least 51 percent of its stock is owned by one or more women; and whose management and daily business operations are controlled by one or more women.

(b) Representation. [Complete only if the offeror is a women-owned business concern and has not represented itself as a small business concern in paragraph (c)(1) of FAR 52.219-1, Small Business Program Representations, of this solicitation.] The offeror represents that it ( ___ ) is a women-owned business concern.

52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2016)

(a) Definitions. As used in this provision--

Electronic Funds Transfer (EFT) indicator means a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for Award Management records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.

Registered in the System for Award Management (SAM) database means that--

(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14) into the SAM database;

(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in the SAM database;

(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and

(4) The Government has marked the record ``Active''.

Unique entity identifier means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.

(b)(1) By submission of an offer, the Offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ``Unique Entity Identifier'' followed by the unique entity identifier that identifies the Offeror's name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in the SAM database.

(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:

(1) Company legal business name.

(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(3) Company physical street address, city, state, and Zip Code.

(4) Company mailing address, city, state and Zip Code (if separate from physical).

(5) Company telephone number.

(6) Date the company was started.

(7) Number of employees at your location.

(8) Chief executive officer/key manager.

(9) Line of business (industry).

(10) Company headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) Offerors may obtain information on registration at https://www.acquisition.gov.

(End of clause)

52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.

(2) The small business size standard is $36,500,000.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

( ) Paragraph (d) applies.

( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v)…