W912DS18B0019-0002_Revised.pdf

PDF 657 KB Posted

Attached to
KC-46A Addition/Alteration to Bldg. 3209 for Fuselage Trainer Federal contract opportunity
Solicitation number
W912DS18B0019
Issued by
Department of the Army Corps of Engineers Engineering District New York

About this file

Purpose of revision: correct numbering error in Block 2 on Page 1 of SF 30 (changed from 0003 to 0002). No other changes made.

View the file

Other files for this federal contract opportunity

Other files attached to KC-46A Addition/Alteration to Bldg. 3209 for Fuselage Trainer, newest first.
File Type Posted
Bid_Abstract-W912DS18B0019.pdf PDF
W912DS18B0019-0003.pdf PDF
Amendment_0003_-_KC46_Fuselage_Trainer_-_Plans.pdf PDF
Amendment_0003_-_KC46_Fuselage_Trainer_-_Specs.pdf PDF
Amendment_0002_-_FuT_Specs.pdf PDF
Amendment_0002_-_FuT_Plans.pdf PDF
W912DS18B0019-0002.pdf PDF
W912DS18B0019-0001.pdf PDF
Site_Visit_Sign-In_4_SEP_18_(Fus_Trainer,_Fuel_Hydrants,_Fac_for_Mx).pdf PDF
Package_3_-_KC46_Fuselage_Trainer_-_SID.pdf PDF
W912DS18B0019.pdf PDF
Package_4-_KC46_Fuselage_Trainer_-_FFE.pdf PDF
Package_1_-_KC46_Fuselage_Trainer_-_Plans.pdf PDF
Appendix_B_-_Geotechnical_Report.pdf PDF
Appendix_A_-_Bldg_3209_As-Builds.pdf PDF
Package_2_-_KC46_Fuselage_Trainer_-_Specifications.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1) Revise and reissue the bid schedule.

2) Answ er questions to prospective bidders for informational purposes only.

3) Revise draw ings and specifications, as outlined below .

Bid due date remains 24 September 2018 at 3:00pm EST.

NOTE: Offeror must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 8

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Sep-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS18B0019

X 9B. DATED (SEE ITEM 11)

24-Aug-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Sep-2018

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS18B0019

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

AMENDMENT 0002

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

Construction of Fuselage Trainer, 1

FFP

Construction of FY18 B3209 Fuselage Trainer, JBMDL: All work (includes all plant, labor, and material) for the renovations within B3209 as described in the plans and specifications except for work included in items below.

FOB: Destination

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job

Construction of Fuselage Trainer, 2

FFP

Construction of FY18 B3209 Fuselage Trainer, JBMDL: All work (includes all plant, labor, and material) for the construction of the covered storage, inclusive of site work outside the five-foot line of the building perimeter.

FOB: Destination

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0003 1 Job

Construction of Fuselage Trainer, 3

FFP

Construction of FY18 B3209 Fuselage Trainer, JBMDL: All work for the Final Record Drawing Submission (See Section 00 73 00). Pre-priced at $30,000.00 and this price shown may not be changed.

FOB: Destination

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0004 1 Job OPTION Construction of Fuselage Trainer, Opt. 1

FFP

Construction of FY18 B3209 Fuselage Trainer, JBMDL: Purchase, deliver, and install Furnishings and Appliances, per CID & FF&E packages.

FOB: Destination

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0005 1 Job OPTION Construction of Fuselage Trainer, Opt. 2

FFP

Construction of FY18 B3209 Fuselage Trainer, JBMDL: All work, (includes all plant, labor, and material) for the installation of the infill wall as described on drawings and specifications (A202 & Section 08 34 16).

FOB: Destination

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0006 1 Job OPTION Construction of Fuselage Trainer, Opt. 3

FFP

Construction of FY18 B3209 Fuselage Trainer, JBMDL: All work, (includes all plant, labor, and material) for procurement and delivery of caster ball deck as described in section 11 13 10.15 and shown on drawings.

FOB: Destination

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0007 1 Job OPTION Construction of Fuselage Trainer, Opt. 4

FFP

Construction of FY18 B3209 Fuselage Trainer, JBMDL: All work, (includes all plant, labor, and material) for procurement and delivery of breathing air compressor, air dryer and breathing air purifier as noted on drawings P-102, P-600 and specifications 22 15 14.00 40. Air distribution piping and fittings are not included in this option.

FOB: Destination

NET AMT

TOTAL

TOTAL BASE BID PRICE FOR LINE ITEMS 0001- 0003:

TOTAL OPTIONAL BID CLIN 0004 TO CLIN 0007:

TOTAL BASE BID + OPTIONAL ITEMS PRICE FOR LINE ITEMS 0001- 0007:

NOTES:

1. Bidders are required to bid on all the Base Bid and all the Optional Bid Items or their bids will be rejected.

2. Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions or attachments made by the bidder himself, thereto, may render the bid non-responsive and be cause for its rejection.

3. Line item 0003 is pre-priced at 30,000.00 and this price shown may not be changed. See Section 00 73 00 for Final Record Drawing definition and requirement.

4. The Basis of Evaluation will be the lowest responsive, responsible bid based on the Total Amount for the Base Bid Items plus the Optional Bid Items (Line Items 0001 thru 0007).

5. Option #1-3: At any time prior to 360 calendar days after issuance of notice to proceed (NTP), the Government at its option, may direct the Contractor, by written order, to perform the work and/or services provided under these Options. Execution of any of these options prior to 210 calendar days after issuance of NTP will not alter the project completion date of the contract. Execution of any of the options after 210 calendar days of NTP will extend the project completion by 150 calendar days.

6. Option #4: At any time prior to 270 calendar days after issuance of notice to proceed (NTP), the Government at its option, may direct the Contractor, by written order, to perform the work and/or services provided under these Options. Execution of this option will not alter the project completion date of the contract.

7. The Bid Acceptance Period is as stated on Standard Form 1442.

8. Submit technical inquiries and questions relating to this solicitation via Bidder Inquiry in ProjNet at (https://www.projnet.org) at least 10 calendar days prior to the date established in the IFB for receipt of bids. The Government reserves the right to decline addressing questions received less than 10 calendar days prior to receipt of bids. If a bidder believes that the requirements in this Invitation for Bid contain an error, omission, or are otherwise unsound; immediately notify the Contract Specialist in writing with supporting rationale.

To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access.

A prospective vendor who submits a comment or question will receive answers in an amendment. All timely questions and approved answers will be made available in amendments and posted to:

www.FBO.gov

Bidder Inquiry Key: FAIG4J-7URIFD

Specific Instructions for Initial ProjNet Bid Inquiry Access:

1. From the ProjNet home page, click on Quick Add on the upper right side of the screen.

2. Identify the Agency as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. E‐mail. Enter the e‐mail address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your Secret Answer and click Login. Once this is completed, you are logged into the System.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been added by full text:

AMENDMENT 0002

TO OFFORERS

The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED but NOT REISSUED:

- None

2. The following DRAWINGS have been REVISED and REISSUED:

- Drawing S-120

- Drawing S-200

- Drawing S-311

- Drawing S-312

- Drawing S-401

- Drawing A-101

- Drawing A-102

- Drawing A-104

- Drawing A-105

- Drawing P-101

- Drawing P-102

- Drawing P-600

- Drawing P-901

3. The following DRAWINGS have been ADDED:

- None

4. The following DRAWINGS have been DELETED:

- None

SPECIFICATIONS

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

- Section 01 45 35 Special Inspections

- Section 25 05 11 Cybersecurity for Facility-Related Control Systems

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

- Section 32 16 13 Concrete Sidewalks and Curbs and Gutters

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

- 00 01 00 – Solicitation Bid Schedule

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

- Section 01 11 00 Summary of Work – add the following to paragraph 1.2.1, point 2.

“c. Jersey Barriers to be used as construction perimeter and may be left in place after completion of construction.”

- Section 05 12 00 Structural Steel – add the following to end of paragraph 2.2.1 Structural Steel “Hot-Dip Galvanized per ASTM A123 where indicated.” Also add the following to end of paragraph 2.3 Bolts, Nuts, and Washers “Hot-Dip Galvanized per ASTM A123 where indicated.”

- Section 08 71 00 Door Hardware – add the following to paragraph 3.6 Hardware Sets “Provide hardware for aluminum doors under this section. Deliver Hardware templates and hardware, except field applied hardware, to the aluminum door and frame manufacturer for use in fabricating doors and frames.”

- Section 10 22 15 Interior Chain Link Fences and Gates – add paragraph 2.4 to part 2 which shall state the following “2.4 Privacy Screen A UV protected vinyl fence privacy screen fabric shall be installed that is made of high quality solid vinyl (PVC) with reinforced black binding for secure fitting and brass grommets every 24”. The screen shall provide maximum privacy and blockage.

MAXFlex 400 Series Solid Vinyl Privacy Fence Screen or equal to product can be installed to meet privacy requirements. The color to be selected in coordination with the COR and Users.”

OFFEROR’S QUESTIONS AND GOVERNMENT REPLY:

Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.

QUESTION 1:

In regard to chain link fence with privacy screen:

1. Please provide detail or spec of privacy screen.

2. Please provide detail of fence post attachment to existing slab.

3. Height of fence is called to be 12' on dwg. A-101 and 10' on dwg. A-102. Please clarify.

GOVERNMENT RESPONSE:

Details of the privacy screen has been added to spec section 10 22 15 Interior Chain Link Fences and Gates. The fence shall be 10’ high. For post installation please refer to specifications section 10 22 15 for details.

QUESTION 2:

Drawing M-802 is in the set but not listed in the index to drawings.

GOVERNMENT RESPONSE:

M-802 has been added to the drawing index.

(End of Summary of Changes)