POPLAR ISLAND LATERAL EXPANSION CONTRACT 2, TALBOT COUNTY, MD
Solicitation number
W912DR-17-B-0007
Issued by

About this file

Solicitation Amendment 0001: W912DR-17-B-0007-0001 answers all RFIs received via ProjNet. This amendment also extends the response date and time to 17 AUG 2017 at 11:00AM EST.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to herby provide the official responses to all ProjNet submitted Request for Information (RFIs). The hour and date specified for receipt of sealed bid has also been extended to 17 Aug 2017 at 11:00 AM EST. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 7

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR-17-B-0007

X 9B. DATED (SEE ITEM 11)

11-Jul-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

03-Aug-2017

CODE

USACE, BALTIMORE DISTRICT

10 S. HOWARD ST

ROOM 7000

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR-17-B-0007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 10-Aug-2017 11:00 AM to 17-Aug-2017 11:00 AM.

(End of Summary of Changes)

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Bid Inquiry Contractor Report All Inquiries

Project: Poplar Island Lateral Expansion Contract 2 Review: Poplar Island Lateral Expansion Contract 2 (00001) (sorted by CommentID ) Displaying 19 inquiries.

Id Discipline Sheet Detail Spec 7072805 Geotechnical 31 05 19 - GEOTEXTILE Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

PLEASE PROVIDE THE NAME OF THE MANUFACTURERS FOR THE APPROVED GEOTEXTILE FABRIC BEING

USED ON THE ONGOING PHASE ONE EXPANSION PROJECT

On: Jul 20 2017.

Government Response. . We cannot provide the name of a manufacturer due to creating an unfair advantage. We are using the same spec for the contract currently under construction. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7072828 General 01 32 01.00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

WHAT TIMEFRAME WOULD BE A REASONABLE EXPECTATION FOR BIDDERS TO USE IN DETERMINING

SCHEDULING THE START OF THIS PHASE OF CONSTRUCTION.

On: Jul 20 2017.

Government Response. . If all the contractor's paperwork is submitted in a timely manner, NTP could be early October. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074601 Contracting Section 00010 Page 9 of 42 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

There is a 24% minority and 7% female goal listed in the solicitation document. Are these mandatory? If not what good faith efforts documentation is required?

On: Jul 21 2017.

Government Response. . Yes these goals are mandatory. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074610 Civil C-101 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

More detail is required on the existing stone stockpile shown on C-101. What size stone is in the stockpile? Is the stone submerged? Is it accessible by floating equipment? What are the general dimensions of the stockpile? How would the contractor access and remove stone from this stockpile?

On: Jul 21 2017.

Government Response. . Q1: What size stone is in the stockpile?

A1: 26,000 TON of 350LB stone.

Q2: Is the stone submerged?

A2: No.

Q3: Is it accessible by floating equipment?

A3: The Government does not dictate contractor means and methods.

Q4: What are the general dimensions of the stockpile?

A4: The approximate area of the stockpile is 4 acres.

Page 3 of 7ProjNet: Logged In User

8/2/2017https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll...

Q5: How would the contractor access and remove stone from this stockpile?

A5: The Government does not dictate contractor means and methods. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074613 Civil G1003 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

What volume of sand will be available for this contract within Cell 1D, Cell 7, and Cell 4C?

On: Jul 21 2017.

Government Response. . Approximate values of recoverable sand are:

Cell 1D: 420,000 CY Cell 4C: 245,000 CY Cell 7: 325,000 CY On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074652 Civil Time of Year Restrictions Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

In the event terns or other ground nesting birds such as banks swallows make nests in the sand stockpiles is the contractor liable for the potential sand hauling days lost while the birds are inhabiting the stockpiles and the stockpiles are inaccessible?

On: Jul 21 2017.

Government Response. . In the event that terns or other ground nesting birds makes nests in the sand stockpiles, or on dikes being actively constructed, the contractor is liable for the potential days lost in the construction schedule. USACE will work to alleviate and mitigate bird nesting in the construction zone in support of construction activities as much as possible, but cannot make any guarantees that bird nesting will not inhibit construction. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074658 Civil Time of Year Restriction Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Will the Time of Year Restrictions apply to the removal of the break waters?

On: Jul 21 2017.

Government Response. . Yes, all time of year restrictions apply to the excavation and construction of the breakwaters. However, excavation by typical earth moving equipment to create the openings in the breakwaters is not considered mechanical dredging. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074664 Civil G1007 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Is it mandatory to follow the construction sequence consecutively from A to C or would alternate sequences be considered?

On: Jul 21 2017.

Government Response. . Yes, the sequence shown on G1007 is mandatory. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074671 Civil G1007, B Note 3 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

How shall the toe dike being 200 feet advanced of embayment dike fill be achieved or measured since they are two separate alignments?

Page 4 of 7ProjNet: Logged In User

On: Jul 21 2017.

Government Response. . The Construction Representatives on site will field measure the 200 feet advancement of the perimeter toe dike to ensure that the embayment dike is not being constructed ahead of the perimeter toe dike. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074676 Civil C9304 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Should the road way slope be draining to the open water or the future cell, given the other sections show draining away from the open water?

On: Jul 21 2017.

Government Response. . From station 35+52.95 to 38+53.82, the road way slopes to drain to the open water. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074679 Civil Section 01 11 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Will the Corp send the contract drawing CAD files if requested by prospective bidders?

On: Jul 21 2017.

Government Response. . No, the Corps will not provide CAD files to prospective bidders. On: Aug 02 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074683 Civil Section 01 33 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Given the large number of soil laboratory test and required 72-hour turnaround for results to the Corp, will the Corp provide a list of Crop approved labs capable of performing the requested test?

On: Jul 21 2017.

Government Response. . No, the Corps will not provide a list of Corps approved labs. However, the contractor may use the following link to find a suitable lab.

https://media.defense.gov/2017/Jul/17/2001778567/-1/-1/1/170714_CEERD-GMC_VALIDATEDLABS%20.PDF On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7074690 Civil Solicitation Bid Items Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Is the quantity of geotextile fabric listed for bid item 0005 the neat square yard coverage, or does the quantity include the additional fabric required to achieve the overlaps mandated in the specifications?

On: Jul 21 2017.

Government Response. . The quantity of geotextile fabric listed for bid item 0005 is the net square yardage, and does not include overlaps, being that sewn seems can also be used. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7082807 Specifications 35 31 19 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The Bedding stone gradation In Section 35 31 19, 2.1.3 calls for AASHTO #2. For the Lateral Expansion Contract 1, this was changed in Amendment 3 to AASHTO #1. Will AASHTO #1 be accepted as a replacement for the bedding stone for contract 2 as well?

Page 5 of 7 ProjNet: Logged In User

On: Jul 27 2017.

Government Response. . Concur, AASHTO #1 would be accepted as an alternative material. On: Aug 02 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7082810 Specifications 35 31 19 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The Minus 12" rock fill found in Section 35 31 19, 2.1.3 has a band for the percent passing by weight through a 6" sieve of 35% to 60%. There were concerns at the current project with the large sized rocks allowed by the gradation spec. Can the 6" range be changed to 50 to 100% instead of 35 to 60%?

On: Jul 27 2017.

Government Response. . Yes, the 6" range can be changed to 50 to 100% instead of 35 to 60%. On:

Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7082816 Specifications 35 31 19 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Does Section 35 31 19, 2.1.4 "Size and Shape of Stone" apply to just the armor stone, or all sizes listed in 2.1.3? In Contract 1 the size and shape requirement was only on the armor stone. If this specification is required for all sizes (Minus 12", Bedding, Quarry Run, etc), there will be a problem finding any quarry that can produce material that will comply with this requirement.

On: Jul 27 2017.

Government Response. . Yes, the "size and shape of stone" specifications apply to all stone materials. If the Contractor would prefer that certain stone sizes be excluded from this, they may make those requests specifically, and each will be evaluated. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7082881 Geotechnical Stone 1500 and 2500 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

In regards to the total project days related to production of the required rip rap materials and primarily the Armor Stone product. The ability to meet the supply schedule and seasonality impacts from a source standpoint will be very difficult. Is there a possibility of an extension?

On: Jul 27 2017.

Government Response. . Current conditions permit 600 calendar days as a reasonable construction duration. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7082905 Specifications 01 22 00.00 10-Measurement & Payment Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

1.6.4.5 Payment notes those items that refer to stone in place on existing to be salvaged & either stockpiled or placed on the new dike. Please provide what amount of the material it is anticipated will be stockpiled. Have the bid quantities for new material to be supplied been adjusted to reflect the anticipated quantity of material to be salvaged & reused?

On: Jul 27 2017.

Government Response. . Yes, the bid quantities for new material to be supplied have been adjusted to reflect anticipated quantity of material to be salvage and reused. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7082937 General Solicitation

Page 6 of 7ProjNet: Logged In User

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

This is to request that the proposed contract duration be extended to 900 days for the following reasons (1)The phase 1 expansion contract allowed 400 days duration for a much less scope of work. The access for revetment construction in Phase 2 is along the constructed dikes and only a certain number of crews can effectively work on the dikes at one time.

(2)There are two stone quarries on the Bay that have water based facilities. They would not be able to provide the production required for the specified quantity of material in 600 days.

On: Jul 27 2017.

Government Response. . Current conditions permit 600 calendar days as a reasonable construction duration. On: Aug 02 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

Report Complete

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Patent 11/892,984 ProjNet property of ERDC since 2004.

Page 7 of 7ProjNet: Logged In User