W912DR-15-T-0072-0004.pdf
PDF 61 KB Posted
- Attached to
- Vessel Maintenance Federal contract opportunity
- Solicitation number
- W912DR-15-T-0072
About this file
Amendment
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912DR-15-T-0072-003.pdf | ||
| W912DR-15-T-0072-002.pdf | ||
| W912DR-15-T-0072-01.pdf | ||
| W912DR-15-T-0072.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912DR-15-T-0072
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to revise the bid schedule, and to extened the closing date of the solicitation from 04-June-2015 to 17-June-2015. Offerors MUST use revised BID Schedule included in this amendment or they w ill be considered non-responsive. All other terms and conditons w ill remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 11-Jun-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR-15-T-0072
X 9B. DATED (SEE ITEM 11)
22-Apr-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
11-Jun-2015
CODE
USACE BALTIMORE
10 S. HOWARD STREET
BALTIMORE MD 21201
W912DR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been modified:
BID SCHEDULE
2.4.3 Shipyard Work to be Performed (Cost Breakdown) BD-1
The following items are in no particular order of accomplishment.
Items Description Price of Services
0001AA
Haul, block and re-float barge.
0001AB
Scrape, sand and pressure wash the bottom and hull to completely remove marine growth and loose paint in preparation for painting.
0001AC Open all hatches and check all interior compartments for rusting, corrosion, electrolysis and damage. Report excessive occurrences.
0001AD Wire brush, sand or sand wash all exterior rust. $
0001AE Inspect/check the exterior for pitting, corrosion and electrolysis and damage. Report excessive occurrences.
Cleaning w/o major repairs
0001AF Apply two (2) coats of epoxy mastic and primer to bare spots inside and out (Ameron MILP-24 Gray / MILP 24B).
Inspection w/o damages
0001AG
Apply one (1) finish coat to manufacturer’s specification of matching color to all primed areas.
0001AH
Apply one (1) coat of gloss black acrylic epoxy paint from waterline to deck (Ameron 229T Gloss Black Acrylic Epoxy).
0001AJ Apply two (2) coat of red antifouling paint on hull bottom to waterline (Ameron
AT214-73).
0001AK
Repaint all numbers and lettering using gloss white acrylic epoxy paint (Ameron 229T Gloss White Acrylic Epoxy).
0001AL
Remove and replace all six (6), 18 inch round hatches and combings rings.
0001AM Sand blast deck, prime and apply two (2) coats of red paint to the deck. First coat to be without non-skid material and second coat to be with non-skid material (Ameron Amercoat 238).
0001AN Replace all Zinc anodes. Barge has a total of 12 anodes measuring 6 inches wide by 12 inches long.
0001AP
Purchase and install two (2) 24 inch cleat centered on either end of barge.
0001AQ
Sand, prime and paint areas of interior that paint was affected by welding of new hatches and cleats.
Total Estimated Cost
BID SCHEDULE
SHIPYARD MAINTENANCE DEBRIS VESSEL BD-5
15 January 2015
2.4.2 Shipyard Work to be Performed (Cost Breakdown) BD-5
The following items are in no particular order of accomplishment.
Items Description Price of Services 0002AA Haul, block and re-float vessel $
0002AB Scrape and pressure wash the bottom and hull to remove marine growth, wire brush or sand all bare spots.
0002AC Apply two (2) coats of antifouling red paint on hull bottom to waterline (Ameron AT214-73).
0002AD Sand the black hull, touch up bare spots with primer, and paint.
0002AE Apply one (1) coat of gloss black paint from waterline to deck to include splash guard on and around bow (Ameron 229T Gloss Black Acrylic Epoxy).
0002AF Repaint all numbers and lettering using gloss white paint (Ameron 229T Gloss White Acrylic Epoxy).
0002AG Remove stern counterweights, sandblast deck, lift well, bow splash guard and counterweights, repair rust spots, prime and paint deck with oxide red and apply nonskid (use coarse blasting grit NOT walnut shells) paint counterweights, splash guard, lift well and trim with Ameron 229T Gloss Black Acrylic Epoxy and reinstall weights.
0002AH Service lectrasan unit. Cycle valves and repair as needed.
0002AJ Remove and replace all metal grating on lift basket, sand blast entire lift, check all welds on lift and repair as needed, prep, prime and paint lift arms and basket with Ameron 229T Gloss Black Acrylic Epoxy.
0002AK Remove all pins and bushings on lift and replace with new ones, install new zerk grease fittings on all lift lubrication points.
0002AL Replace all hydraulic lines, connections and fittings on lift.
0002AM Drain and flush anti-freeze from main engines and keel coolers, replace with 50/50 mixture of new coolant.
0002AN Check keel cooler units for leaks or damage. $
0002AP Replace starboard engine coolant reservoir and lines
0002AQ Rebuild radar mast and raise stern light above height of exhaust stacks.
0002AR Repair life line stanchions and mounting brackets, sandblast prime, paint with Ameron 229T Gloss Black Acrylic Epoxy and reinstall.
Fabricate and install new life lines.
0002AS Reconfigure stern towing lights to raise them above the height of the life raft.
0002AT Replace existing shafts and cutlass bearings. Repack stuffing boxes.
0002AU Repair and balance props and reinstall $
0002AV Replace zinc anodes. $
0002AW Repair/ replace all hydraulic hoses and fittings under dash in wheelhouse. (Lift basket and steering)
0002AX Replace connection rod between rudder posts, properly reconnect the steering ram, replace hydraulic lines and fittings to steering ram, and repair rudder angle indicator.
0002AY Align main engines/ shafts to .003 run out. $
0002AZ Replace the high heat wrapping around engine exhaust pipes and mufflers in engine room.
Total Estimated Cost
NOTE: All line items must be priced to be considered for award. Otherwise it will be considered Non responsive to the RFQ.
Offerors MUST use Bid Schedule included in amendment 0004 or they will be considered non-responsive. All other terms and conditions will remain the same
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 04-Jun-2015 10:00 AM to 17-Jun-2015 10:00 AM.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .