W912DR-15-R-0005_Amendment_0001.pdf
PDF 22 KB Posted
- Attached to
- Campus Feeders SATOC
- Solicitation number
- W912DR-15-R-0005
About this file
The purpose of the attached amendment to the solicitation is to provide responses to Requests for Information (RFI).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912DR-15-R-0005-02.pdf | ||
| W912DR-15-R-0005__Campus_Feeders_Phase_1_Solicitation.pdf | ||
| W912DR-15-R-0005_Campus_Feeders_Project__Phase_1_Solicitation.pdf | ||
| Contractor_Format_for_RFIs.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The above referenced solicitation is hereby amended to incorporate the follow ing: - Answ ers to Requests for Information (RFIs) The date and time of proposal closing has not been extended.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Apr-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR-15-R-0005
X 9B. DATED (SEE ITEM 11)
15-Apr-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Apr-2015
CODE
US ARMY CORPS OF ENGINEERS BALTIMORE DIS
10 SOUTH HOWARD STREET
BALTIMORE MD 21201-2536
W912DR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DR-15-R-0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been added by full text:
AMENDMENT 1 RFI Q&AS
Q: Is this a Draft Solicitation?
A: No, DRAFT watermark failed to remove upon release.
Q: Will a Facility Security Clearance be required from the awarded contractor?
A: No.
Q: Reference Attachment B, “Contractor’s Past Experience.” The form requests cost information for “Project” and “Subcontractor.” For a project performed by the prime contractor, is the form requesting “Subcontractor” cost be the total subcontracted amount; or, is the “Subcontractor” cost information to be provided for subcontractors providing past experience?
A: Form is requesting the total subcontracted amount of the prime’s original contract.
Q: Solicitation included Attachment A “Questionnaire Pertaining to Foreign Interest.” Please advise on the following questions:
Q1. At what stage of the procurement process, Phase 1 or Phase 2, should this document be completed?
A1. Document shall be completed in Phase 1.
Q2. If questionnaire is required for Phase 1, please specify if information should be submitted to the Government prior to Phase 1 submission or if information may be included in Binder 2: Solicitation Information.
A2. Binder 2: TAB H- Questionnaire Pertaining to Foreign Interest.
Q3. Please specify the team members who are required to complete document.
A3. The principal responsible for signing the contract will be required to complete the document. For a Joint Venture, all parties signing the Joint Venture agreement.
Q: 5.1 Factor 1 Past Performance of Relevant Projects. Will the Government consider modifying project completion requirement from 100% construction completion to 95% construction completion?
A: No-the factor remains as originally written.
Q: 5.2 Factor 2 Work Plan, 5.2.5 Safety. Government requested EMR and DART rates if available, however did not specify for what years to provide. Please clarify how many years information is required for.
A: -5 years for the Experience Modification Rating (EMR).
-200,000 hours for the Days Away, Restrictions and Transfers (DART) rate.
Q: Paragraph 1 of Section 5.1 FACTOR 1: PERFORMANCE OF RELEVANT PROJECTS states: “Projects submitted must demonstrate past performance by the 100% construction completion of similar projects within six years from the date of issuance of this solicitation.” Please confirm if the below criteria satisfies 100% construction completion
- Installation and construction of the facility is complete
- Commissioning and close-out is currently in progress A: Yes, as long as beneficial occupancy has taken place.
Q: Paragraph 2 of Section 5.1 FACTOR 1: PERFORMANC OF RELEVANT PROJECTS states: “The Offeror shall provide formal performance evaluation if available.” Please confirm it is acceptable to provide an interim formal performance evaluation if a final formal performance evaluation has not yet been completed and filed.
A: Yes.
(End of Summary of Changes)
W912DR-15-R-0005