ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED DATE OPENED PAGE OF 28-Aug-14 1 of 2
4. ISSUING OFFICE Name and title of Certifying Official (Type) I CERTIFY that I have opened, read, and Christina Sale, Contract Specialist
USACE, BALTIMORE DISTRICT recorded on this abstract all offers Signature Date Signed 10 SOUTH HOWARD STREET, ROOM 7000 received in response to this solicitation.
BALTIMORE, MD 21201 Contracting Officer: JOHN J. MCBRIDE
5. PROJECT TITLE
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F.)
A. HIRED LABOR
B. REASONABLE CONTRACT B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) (Without Profit)
6. NUMBER OF AMENDMENTS ISSUED X C. REASONABLE CONTRACT C. Amendments Acknowledged C. Amendments Acknowledged 2 (Two) (Including Profit)
7A. 7B. 7C. D. E. F. E. F. E. F.
ITEM DESCRIPTION OF OFFERED ITEM EST. UNIT UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED No. QUANTITY PRICE AMOUNT IGE PRICE AMOUNT PRICE AMOUNT
All costs in connection with removing existing and providing a new oil/water separator and associated piping and storage tanks at the Minefield Test Pad complete as shown on the drawings and specified.
1 JOB $824,128.00 $584,000.00 $877,745.00
TOTAL BASE BID AMOUNT
1 JOB $824,128.00 $584,000.00 $877,745.00
All costs in connection with removing existing and providing a new oil/water separator and associated piping and storage tanks at Test Pad 12 complete as shown on the drawings and specified.
1 JOB $686,208.00 $500,000.00 $798,325.00
All costs in connection with removing existing and providing a new oil/water separator and associated piping and storage tanks at Test Pad 18 complete as shown on the drawings and specified.
1 JOB $604,827.00 $400,000.00 $765,195.00
TOTAL BID AMOUNT
(TOTAL BASE BID and OPTIONAL BID AMOUNTS)
1 JOB $2,115,163.00 $1,484,000.00 $2,441,265.00
NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. Prescribed by GSA-FAR(48 CER)53.236-1 OPTIONAL FORM 1419 (11-88)
YES
BID BOND 20% BID BOND 20%
D&B Construction, Inc.
2706 Lodge Farm Rd.
Baltimore, MD 21219-1314
YES
No. 2
East Coast Utility Contractors, LTD
P.O. BOX 3572
Williamsburg, VA 23187-3572
25-Jul-14W912DR-14-B-0016
REPLACE OIL WATER SEPARATORS, ABERDEEN PROVING GROUND, MD
100% TOTAL SMALL BUSINESS SET-ASIDE
No. 1
9. OFFERS
1. SOLICITATION NUMBER PAGE OF
ABSTRACT OF OFFERS W912DR-14-B-0016 2 OF 2
CONSTRUCTION INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on CONTINUATION SHEET a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.
2. PROJECT TITLE
B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount)
3. CONTRACT ITEMS C. AMENDMENT ACKNOWLEDGED C. AMENDMENT ACKNOWLEDGED C. AMENDMENT ACKNOWLEDGED C. AMENDMENT ACKNOWLEDGED 7A. B. C. D.
ITEM DESCRIPTION OF OFFERED ITEMS ESTIMATED UNIT E. UNIT F. ESTIMATED E. UNIT F. ESTIMATED E. UNIT F. ESTIMATED E. UNIT F. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
All costs in connection with removing existing and providing a new oil/water separator and associated piping and storage tanks at the Minefield Test Pad complete as shown on the drawings and specified. 1 JOB $1,467,600.00 $1,018,000.00
TOTAL BASE BID AMOUNT $1,467,600.00 $1,018,000.00
All costs in connection with removing existing and providing a new oil/water separator and associated piping and storage tanks at Test Pad 12 complete as shown on the drawings and specified. 1 JOB $1,358,600.00 $450,000.00
All costs in connection with removing existing and providing a new oil/water separator and associated piping and storage tanks at Test Pad 18 complete as shown on the drawings and specified. 1 JOB $1,322,900.00 $420,000.00
TOTAL BID AMOUNT
(TOTAL BASE BID and OPTIONAL BID AMOUNTS) $4,149,100.00 $1,888,000.00
NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. Prescribed by GSA-FAR(48 CER)53.23OPTIONAL FORM 1419 (11-88)
OFFERS (Continued)
100% TOTAL SMALL BUSINESS SET-ASIDE
REPLACE OIL WATER SEPARATOR, ABERDEEN PROVING GROUND, MD
BID BOND 20%
YES YES
No. 6No. 3 No. 4
Corinthian Contractors, Inc.
8510 Westphalia Road Upper Marlboro, MD 20772
Edifice-Schlosser JV, LLC 4328 Farragut Street Hyattsville, MD 20781
BID BOND 20%
No. 5
| 1 |
| D-1_Abstract of Bids Cont(PG2).pdf |
| 2 |
| 2014-08-28T15:10:03-0400 | |
| SALE.ELLIE.CHRISTINA.1228681985 |