A.07.14_Question_ _Answers_(Misc).docx
DOCX document 12 KB Posted
- Attached to
- Three Sided Information Panel at Perry Lake
- Solicitation number
- W912DQ-16-R-1012
About this file
Responses to Questions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Map_of_Boat_Ramps_2.pdf | ||
| Map_of_Boat_Ramps_1.pdf | ||
| A.07.23_Picture_6.pdf | ||
| A.07.23_Picture_3.pdf | ||
| A.07.23_Picture_5.pdf | ||
| A.07.23_Experience_Form.pdf | ||
| A.0.7.23_Solicitation(Draft_Removed).pdf | ||
| A.07.23_Picture_4.pdf | ||
| A.07.23_Picture_2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question and Answer For The Three Sided Information Panel
Can you please tell me the length of the walkways for the ADA ramp sidewalk and the concrete fill requirement?
It looks like there will only be two sites that will require an actual sidewalk, the rest will just be the pads. We are estimating between 35 and 40 ft. of sidewalk will need to be poured between those two locations. The other sites have existing sidewalks that the pad can be tied into. As far as depth is concerned we feel a 4 inch sidewalk and pad would be sufficient. There is no special requirement for the concrete fill.