Text version

W912CN18R0018

SEE ADDENDUM

(No Collect Calls)

W912CN18R0018 13-Mar-2018

b. TELEPHONE NUMBER

808.656.1029

8. OFFER DUE DATE/LOCAL TIME

10:00 AM 27 Mar 2018

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA X ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W912CN9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

WARREN M. SABUGO

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

EXPEDITIONARY CONTRACTING COMMAND

413TH CSB, RCO-HAWAII,

742 SANTOS DUMONT AVENUE

BLDG 108, 3RD FLOOR (WAAF)

SCHOFIELD BARRACKS HI 96857-5026

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE W90KJU 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

US ARMY 402ND AFSB

SANDRA FONTENOT (REESE)

1904 HIGGINS RD EAST RANGE

MGT. BRANCH, BLDG. 6039

SCHOFIELD BARRACKS HI 96857

TEL: 808-656-3076 FAX:

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$38,500,000

NAICS:

562119

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF65

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

Section SF 1449 - CONTINUATION SHEET

SUBMISSION OF OFFERS

SUBMISSION OF OFFERS

Offers will be accepted through any of the following options:

1. FedBizOpps; or

2. Email: warren.m.sabugo.civ@mail.mil and ronnie.t.sakata.civ@mail.mil

(Offers must be received to both email addresses In Box no later than date and time specified in block 8);

Offeror must be registered in the SAM database to be considered for award. Registration is free and can be completed on-line at http://www.sam.gov/

PERFORMANCE WORK STATEMENT

PERFORMANCE WORK STATEMENT

MAINTENANCE/REPAIR WORK FOR PARTS WASHERS EQUIPMENT

ISLAND OF OAHU, HAWAII

1. DESCRIPTION OF SERVICES. The Contractor shall provide all management, transportation, labor, materials, supplies, and tools to perform maintenance and repair work for four (4) government owned parts washer equipment (Model: Graymills Drum-Mount Solvent Parts Washer DMS 236) installed at East Range buildings 6017 (1EA), 6018 (1EA) & 6065 (2EA), on Schofield Barracks, Hawaii. Services are to include testing/recycling/disposal of non-hazardous petroleum oil and lubricant products (POL) and solvent. The Contractor shall work in accordance with Occupational Safety and Health Act (OSHA) Standards, current Federal, State, County laws, regulations, and commercial standards.

1.1. SUPPLIES, MATERIALS AND EQUIPMENT TO BE PROVIDED

BY THE CONTRACTOR

Unless otherwise specified herein, the contractor shall furnish all supplies, material and equipment necessary for the performance of work under this contract. The contractor shall utilize products and materials made from bio based materials (e.g. bio based degreasers and bio based toilet bowl cleaner) to the maximum extent practical without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. The EPA's Comprehensive Procurement Guidelines and product list can be found at http://www.epa.gov/epawaste/conserve/tools/cpg/index.htm.

Upon request of the COR, the contractor shall submit a list indicating the name of the manufacturer, the brand name, and the intended use of each of the materials used in the performance of its work. The Contactor shall not use any materials, chemicals, or compound which the COR determines would be unsuitable for the intended purpose or harmful to the surfaces to which applied or, as might be the case for such items as paper or soap products, unsatisfactory for use by occupants.

For bio based content products evaluation, all non-chemical products proposed for use under this contract must conform to the Department of Agriculture (USDA) Designated Bio based Products List (DBPL) whenever practicable.

1.1.1. Parts Washers Equipment Maintenance & Repair. The Contractor shall service/repair parts washers and replace the solvent once every four (4) months for various buildings. The contractor shall use P-D-680 Type III or better cleaning solution, Flashpoint 146 or greater. Solvent shall meet guidelines for Performance Specification Degreasing Solvent for Types II, III or IV and guidelines for Solvent Cleaning Power by U.S. Anny Soil Test Method as stated in Technical Exhibit # 1: Performance Specification Degreasing Solvent.

1.1.2. Consumable Solvent and Filters. Replace filters as required. The Contractor shall dispose used solvent and recycle for reuse.

1.1.3. Maintenance Service Work Schedule. The Contractor shall submit to the COR a maintenance service work schedule within five (5) working days before the month of scheduled maintenance that indicates the day and approximate time of service for Parts Washers. The

Government reserves the right to request for work schedule modifications to ensure accessibility of products

1.2. Special Conditions.

1.2.1. Disposal/Recycle Plan. The Contractor shall submit a disposal/recycle plan for the used solvent products and other materials 10 days after award, subject to Government approval. The disposal/recycle plans shall reflect all required State and Federal permits, licenses, reports and final disposition of materials. The plan shall be adhered to for all disposals and recycling of products during the contract performance period.

1.3. Business Relations. The Contractor shall partner with the Government to resolve all issues and conflicts within two (2) working days from the day of occurrence.

2. Non-Personal Services. The Government shall neither supervise contractor employees nor control the method by which the contractor performs the required tasks.

Under no circumstances shall the Government assign tasks to, or prepare work schedules for, individual contractor employees. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor believes that any actions constitute, or are perceived to constitute personal services, it shall be the contractor's responsibility to notify the Procuring Contracting Officer (PCO) immediately.

3. PERFORMANCE REQUIRED SUMMARY. The Contractor service requirement is summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objectives PWS Para

Performance Threshold

Service/Repair for Parts Washers

1.1.1 Service parts washers and replace the

solvent every four (4) month.

Maintenance Service Work Schedule

1.1.3. The Contractor shall submit to the COR a

maintenance service work schedule within five (5) working days on the month of scheduled maintenance.

Business Relations 1.3. Contractor shall partner with the Government to resolve all issues and conflicts within two (2) working days from the day of occurrence.

4. GOVERNMENT FURNISHED PROPERTY. Parts Washers will be provided by the government.

4.1. GOVERNMENT FURNISHED UTILITIES. The Government will furnish water and electricity from existing fixtures and outlets at no cost to the Contractor. The Contractor shall conserve electricity and water. No other labor, equipment, supplies, materials, or transportation will be furnished by the Government, unless stated otherwise in the contract document.

5. GENERAL INFORMATION.

5.1. Quality Control. The Contractor shall maintain and submit to the COR within 5 working days from start of contract a quality control program to ensure services are performed in accordance with commonly accepted commercial practices.

5.2. Performance Assessment. The Government will periodically evaluate the Contractor's performance in accordance with the Performance Assessment Plan.

5.3. Hours of Operation. Accomplish all work Monday through Friday, 7:30 a.m. to 4:00 p.m.

excluding Federal holidays. Approval from the COR is required to work other than normal working hours.

5.4. Essential Knowledge, Skills and Training. Contractor and Contractor Employees for this effort must be able to read, write, understand and articulate English fluently and in a professional manner. English shall be the only language used with regard to this contract for written correspondence, discussions and other business transactions.

5.5. Identification of Contractor Employees.

5.5.1. Installation Access Pass (IAP). See Installation Specific Requirements

5.5.2. AT/OPSEC. Level 1 Antiterrorism (AT) Standards. See Installation Specific Requirements.

5.5.3. Provide each employee with identification (ID) badge made of nonmetallic material, easily readable and including employee's name, contractor's name, functional area of assignment, with recent color photograph of the employee.

5.5.4. All contractor personnel shall wear the ID badge at all times when performing work under this contract at a Government site, including while attending Government meetings that may take place outside the Government facility. Contractor employee shall wear the ID badge in a conspicuous place on the front of exterior clothing above the waist except when safety or health reasons prohibit such placement.

5.5.5. All Contractor vehicles shall be identifiable with a sign bearing the company's name

5.5.6. Anti-Terrorism Compliance. IWATCH Training, 1) IWATCH within the Army is a nation-wide modern version of a neighborhood watch program focused on the threat of terrorist activity. It is an antiterrorism awareness program that the contractors' workforce, while on Army installations, must all be familiar with to promote and enhance reporting suspicious activity or behavior. The program has two elements:

"passive" and "active". The passive element is an individual's situational awareness of his or her surroundings. The active element of iWATCH involves individuals taking action to report suspicious behavior or activities to law enforcement for more investigation. 2) Contractor personnel, to include subcontractors, performing on or within an Army controlled facility, area or on an Army installation are required to brief and train their persom1el on the !Watch program for that area, facility or installation. Training standards will be provided by the COR within 5 calendar days of contract award. Contractor personnel are train within 5 days of award or within 5 days of a hiring action. Contractors are to report training to the COR within 7 days of contract award or a hiring action.

6. CONTRACT MANPOWER REPORTING (CMR) REQUIREMENT.

6.1. "The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Logistics Readiness Center via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/, and then click on "Department of the Anny CMRA" or the icon of the DoD organization that is receiving or benefitting from the contracted services.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk by clicking on "Send an email" which is located under the Help Resources ribbon on the right side of the login page of the applicable Service/Component's CMR website".

7. TECHNICAL EXHIBITS (TE):

Technical Exhibit# 1: Performance Specification Degreasing Solvent

TECHNICAL EXHIBIT #1

External attachment - Performance Specification Degreasing Solvent

INSTALLATION SPECIFIC REQUIREM

Installation Specific Requirements

1. GENERAL ENVIRONMENTAL STANDARDS

(a) While performing work on any US Army Garrison, Hawaii (USAG-HI) installation, the Contractor shall comply with Executive Orders 13423 “Strengthening Federal Environmental, Energy, and Transportation Management” signed by the President on 24 Jan 2007 and 13514, “Federal Leadership in Environmental, Energy, and Economic Performance” signed by the President on 8 Oct 2009 requiring the acquisition of environmentally preferable goods and services, use of sustainable environmental practices, purchase of bio based, energy efficient and recycled content products. More specifically, the Contractor shall strive to improve upon their sustainability performance by taking actions to:

(1) Reduce energy consumption

(2) Reduce greenhouse gas emissions

(3) Conserve and protect water resources

(4) Eliminate waste, recycle, and prevent pollution

(5) Adopt sustainable technologies

(6) Procure environmentally preferable materials, products and services

(7) Maintain sustainable buildings

(8) Strengthen livability of the local community

(9) Inform and involve personnel in the achievement of these goals

(b) The Contractor shall comply with the Government directives, permit conditions, installation policies and plans as administered by the Government. The Contractor shall be held liable to pay for any environmental fines resulting from its operations, waste generated or other operational environmental requirements. As applicable, the Contractor shall obtain environmental permits required for wastewater pretreatment, underground tanks, hazardous waste identification numbers, air pollution permit for temporary sources, storm water permits or other pertinent environmental permits.

(c) The Contractor shall review and comply with applicable policies, program documents and regulatory requirements as stipulated under each environmental program media below.

(1) Environmental program documents include, but are not limited to; the Installation Hazardous Waste Management Plan – USAG-HI Regulation 200-4, Asbestos Management Plan, Lead-based Paint Management Plan, Installation Spill Prevention, Control, and Countermeasures (SPCC) Plan, Integrated Natural Resources Management Plan, Integrated Cultural Resources Management Plan, Pollution Prevention Plan, and the Storm Water Pollution Prevention Plan available at the DPW Environmental Division. Environmental program documents can be downloaded from the installation sustainability and environmental management website at:

http://www.garrison.hawaii.army.mil/sustainability/Environmental.aspx.

(2) Installation policies include, but are not limited to; the Environmental Compliance and Protection Program Policy Memorandum USAG-HI-4; Environmental Policy Memorandum USAG-HI-10; Authorized Use List Policy Memorandum USAG-HI-19, Waste Reduction and Recycling Policy Memorandum USAG-HI-25; Open Burn Policy Memorandum USAG-HI-51; Generator Control Policy Memorandum USAG-HI-55; Illicit Discharge Detection and Elimination Policy Memorandum USAG-HI-59; and the Joint USARPAC and IMCOM-Pacific Energy Conservation Policy Guidance. Installation Policy Memorandums are available for download at:

http://www.garrison.hawaii.army.mil/command/documents.htm

(3) The Contractor is also encouraged to view the online A to Z sustainability and environmental management guide for instructions on managing common environmental issues. The A to Z sustainability and environmental management guide is available at: http://www.garrison.hawaii.army.mil/sustainability/AtoZ.aspx.

(d) The Contractor shall at all times keep the work area, including storage areas used, free from accumulations of waste material or rubbish and prior to completion of the work remove any rubbish from the premises and all tools, scaffolding, equipment and materials not the property of the Government. Upon completion of the work, the Contractor shall leave the work and premises in a clean, neat and workmanlike condition satisfactory to the Contracting Officer. If debris is not disposed of properly or the site is not left clean, the Government will clean the site at the expense of the Contractor. The Contractor shall also be held liable for damages done to the environment as a result of disposal and/or cleanup.

(e) The Contractor may be subject to unannounced Environmental Compliance Inspections by the DPW Environmental Division.

(f) Environmental and Safety Noncompliance Fees. The Contractor shall be solely responsible for remedying all Federal, State and local environmental and safety violations or noncompliance and any payment of fines, penalties and fees levied as a result of the violations or noncompliance. The Government reserves the right to withhold payment in the amount of the fines, penalties and fees levied if not paid by the Contractor.

2. EMERGENCY PLANNING COMMUNITY RIGHT TO KNOW ACT (EPCRA) HAZARDOUS

SUBSTANCES (HS)

(a) Contractors using EPCRA HS in the performance of any work while on USAG-HI installations are responsible for complying with the provisions of EPCRA regulations and submitting applicable reports (TIER II/TRI) to Federal and State regulatory agencies as applicable.

(b) Copies of reports for substances used in connection with work performed on USAG-HI installations shall be provided to the DPW Environmental Division, Attention: EPCRA Program Manager, STOP 253, 3rd Floor, 948 Santos Dumont Ave., Wheeler Army Airfield, phone (808) 656-2878.

(c) Chemicals regulated under EPCRA HS are defined in EPA document EPA 550-B-98-017, Title III List of List, Consolidated List of Chemicals Subject to the Emergency Planning and Community Right to Know Act and Section 112(r) of the Clean Air Act Amended.

(d) The Contractor is responsible for knowing which chemicals it uses or transports that are contained on the list.

For convenience, the Contractor may review a copy of the EPA document at the Directorate of Public Works (DPW) Environmental Division. The document can also be downloaded from the U.S. Environmental Protection Agency (EPA) at: http://www.epa.gov/oppt/pubs/genpub.htm.

(e) The Contractor shall maintain copies of Material Safety Data Sheets (MSDS’s) of all chemicals used in the performance of any work while on USAG-HI installations. MSDSs must be readily available at the site location where the work is being performed.

(f) The Contractor may request the list and locations of EPCRA HS currently utilized on USAG-HI installations by contacting the DPW Environmental Division EPCRA Program Manager. The Contractor must provide name, company, contract number, date the contract was awarded and provide a description of the contract. A database of locations of chemicals will then be forwarded upon review and approval of request. Contractors working on USAG- HI installations are encouraged to review this database, which will provide information where potentially hazardous chemicals are stored.

(g) All spills of substances containing EPCRA HS shall be immediately reported to the Directorate of Public Works Spill Response line at (808) 656-1111 and the USAG-HI, Public Affairs Office at (808) 656-3160 or (808) 542-9489 (after hours). The Contracting Officer shall be notified during the first business hour immediately after. All waste generated from EPCRA HS being utilized shall be immediately reported to the DPW Environmental Office, phone:

(808) 656-2878.

(h) All Contractors utilizing substances containing EPCRA HS shall perform the following prior to contract start.

(1) Review the Installation Spill Prevention, Control, and Countermeasures (SPCC) Plan and the Installation Hazardous Waste Management Plan – USAG-HI Regulation 200-4 available at the DPW Environmental Division or from the installation sustainability and environmental management website at:

http://www.garrison.hawaii.army.mil/sustainability/Environmental.aspx. Upon review, the Contractor or designated responsible employee shall sign a certification statement that they have reviewed and understand the contents of these documents.

(2) Provide a listing and MSDS copies of oil and Hazardous Substance (HS) products projected to be utilized in the performance of any work while on USAG-HI installations to the DPW Environmental Division. The estimated average and maximum quantities of each material anticipated to be on-site at any given time shall also be provided to the DPW Environmental Division EPCRA Program Manager, STOP 253, 3rd Floor, 948 Santos Dumont Ave., Wheeler Army Airfield, phone (808) 656-2878 and to building 6040 East Range for material to be bar-coded. The Contractor shall ensure the product listing is current and updated as frequently as necessary and/or at a minimum, on an annual basis by 1 January of each year.

(3) Provide the name, office phone number, and cellular phone number of a company spill response point of contact. The point of contact shall be trained in spill response.

(4) Provide a copy of an agreement with a hazardous materials spill response company in the event of a spill.

(5) Provide copies of employees training certificates on environmental and spill response training.

(6) Appoint a primary and alternate Environmental Compliance Officer in writing.

(7) Develop a notification procedure in the event of a spill to include phone numbers of response personnel, support agencies, National Response Center, State Hazard Evaluation Emergency Response Office and Civil Defense.

(8) Accomplish all spill notifications as required by the U.S. Environmental Protection Agency and State of Hawaii to the Hazard Evaluation Emergency Response Office, Local Emergency Response Commission and National Response Center. Copies of written spill notifications shall be provided to the DPW Environmental Division.

(9) All spills caused by the Contractor shall be cleaned up under supervision of the Contractor and a qualified hazardous materials spill response company, at no cost to the Government, in accordance with all applicable laws and regulations and to the satisfaction of the DPW Environmental Division.

(10) The Contractor shall pay for disposal cost of all contaminated materials to include but not limited to soil, sorbent materials, disposable equipment and other materials contaminated by the spill. Ensure all disposals are in accordance with all applicable laws and regulations at authorized disposal facilities.

3. SPILLS OF PETROLEUM/OIL/LUBRICANTS OR HAZARDOUS MATERIALS/HAZARDOUS

WASTE

(a) The Contractor shall prepare and maintain a site-specific spill plan, including notification procedures for spills/releases. The spill plan shall include phone numbers of response personnel, support agencies, National Response Center, State Hazard Evaluation Emergency Response Office and Civil Defense. The Contractor shall provide a copy of the spill plan to DPW Environmental Division upon request.

(b) The Contractor shall provide immediate response to stop, contain, and clean-up all spills of oil and other hazardous substances that result from its performance under this contract.

(c) The Contractor shall report all spills immediately to the DPW Spill Response line at (808) 656-1111 in accordance with the Installation SPCC Plan. Additionally, the Contractor shall notify the COR of the incident during normal business hours or the first business hour following the incident.

(d) The Contractor shall accomplish all spill notifications and written spill reports as required by the U.S.

Environmental Protection Agency, State of Hawaii Hazardous Evaluation Response Office, Local Emergency Planning Commission and National Response Center, in accordance with applicable laws and regulations.

(e) The Contractor shall provide a copy of spill notifications and written reports to the DPW Environmental Division.

(f) All spills caused by the Contractor shall be cleaned up under the supervision of the Contractor and/or a qualified hazardous waste/materials spill response company, at no cost to the Government, in accordance with all applicable laws and regulations and to the satisfaction of the DPW Environmental Division. If cleanup is not accomplished in a timely fashion, or to the satisfaction of the DPW Environmental Division, the Government will assist with the final cleanup, and the Contractor shall provide appropriate reimbursement of cleanup costs.

(g) The Contractor shall pay for all clean up, management, and disposal cost of all contaminated materials to include but not limited to soil, sorbent materials, disposable equipment and other materials contaminated by the spill. The Contractor shall ensure waste disposal is accomplished in accordance with all applicable laws and regulations and at authorized/permitted treatment and disposal facilities.

(h) The Contractor shall pay any fines or penalty charges associated with a citation issued by federal, state or local officials as a result of the accident.

(i) Contractors handling bulk fuel shall be trained to do so, and mobile fuel operations shall be approved by the DPW Environmental Division.

(j) Off-Post Spills. The Contractor shall be responsible for and pay for cleanup of off-post spills in accordance with directions received from appropriate local authorities (e.g., Honolulu Fire Department, State Civil Defense, etc.).

Off-post spills in connection with work performed under this contract shall also be reported to the DPW Spill Response line at (808) 656-1111 and to the COR.

(k) Discovery of other than Contractor-caused spills. The Contractor shall report any spills of hazardous materials to the DPW Spill Response line at (808) 656-1111 and to the COR upon discovery.

4. HAZARDOUS WASTE (HW) AND NON-REGULATED WASTE (NRW)

(a) The Contractor shall comply with the Environmental Compliance and Protection Program Policy Memorandum

USAG-HI-4.

(b) The Contractor shall determine, based on generation of hazardous waste(s) resulting from their operation/activities their respective hazardous waste generator status. The Contractor is responsible to manage HW and NRW generated on-site from inception to disposal in accordance with all applicable, federal, state, and local regulations. All costs associated with disposal shall be borne by the Contractor.

5. RECYCLING PROGRAM

(a) The Contractor shall comply with USAG-HI Policy Memorandum 25, Waste Reduction and Recycling, requiring diversion of solid waste to the fullest possible. More information can be found on the installation sustainability and environmental management website at:

http://www.garrison.hawaii.army.mil/sustainability/Recycling.aspx

(b) The Contractor shall identify a recycling POC to DPW Environmental Division to include name, phone number and email address.

(c) The Contractor shall report quantities of refuse disposed and recycled to DPW Environmental Division as part of the work performed under this contract as applicable.

6. NATURAL AND CULTURAL RESOURCES PROGRAM

(a) The Contractor shall comply with USAG-HI Range Standard Operating Procedures (SOPs). All personnel who use the ranges must complete a mandatory pre-brief covering issues associated with Natural and Cultural Resources.

(b) The Contractor shall be cognizant of the potential environmental impact and liability their actions could have, if specified procedures are not followed on Army lands. The Contractor shall be aware that USAG-HI manages more than 100 threatened and endangered species including plants, snails, birds, bats, insects and their critical habitat and over 1,300 prehistoric archaeological sites, including temple structures, stone markers, fishing shrines, habitation sites, caves, rock shelters, mounds, burial platforms, earth ovens, stone walls and enclosures, agricultural terraces, irrigation canals, petroglyphs and trails.

(c) The Contractor shall take every precaution to prevent starting wildfires at training areas and must put them out if they do occur. The Contractor shall report all wildfires to range control immediately at (808) 655-1434.

(d) The Contractor shall be familiar with the policy and restrictions regarding the types of ammunition that can be used under the different Burn Indices (BI) and on the different ranges.

(e) The Contractor shall comply with the non-smoking policy at training areas and only allow smoking in designated areas.

(f) The Contractor shall comply with the range best management practices to prevent the spread of invasive plant species from one training area to another by always washing vehicles, gears and equipment before starting new training activities.

(g) The Contractor shall stay out of areas marked with Seibert Stakes. Seibert stakes are placed along roads and within vegetated areas to advise personnel of unsafe or hazardous range or training conditions and/or environmentally sensitive off-limit areas.

(h) The Contractor shall refer to the installation sustainability and environmental management website at:

http://www.garrison.hawaii.army.mil/sustainability/NaturalResources.aspx and http://www.garrison.hawaii.army.mil/sustainability/CulturalResources.aspx for additional information.

7. NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)

As applicable, and upon request by the Government, the Contractor shall comply with the NEPA process, notify the DPW Environmental Division and complete a Record of Environmental Consideration (REC) for actions such as, but not limited to:

(1) Actions that could impact historic structures, cultural and natural resources

(2) Minor renovation or new construction

(3) Actions that introduce new training vehicles, maneuvers, and weapons

(4) Replacing or removing floor tiles, ceiling tiles, sound proofing material, lighting fixtures, carpet, serving line equipment, natural gas unit

(5) Installing interior doors, windows, partitions, security cameras, rerouting ductwork

8. SUSTAINABLE ENVIRONMENTAL MANAGEMENT (SEM) SYSTEM

(a) The Contractor shall be familiar with and comply with the installation’s Environmental Policy Memorandum USAG-HI-10 and all 18 components of the Installation SEM system manual in conformance with the ISO 14001 standard. The SEM system manual is available for download at:

http://www.garrison.hawaii.army.mil/sustainability/SEM.aspx

(b) In accordance with OPORD IMPC-HI-ZA 02-09, the Contractor shall train all personnel in SEM awareness provided by DPW Environmental Division upon contract award. Refer to the installation Sustainable and Environmental Management website at http://www.garrison.hawaii.army.mil/sustainability/Training.aspx for information about the online training logging and access procedure.

(c) The Contractor shall support, as applicable, USAG-HI in achieving the reduction and environmental improvement goals identified in the installation Strategic and Sustainability Plan, as well as Executive Order 13514.

The Contractor shall strive to accomplish these goals by implementing and promoting green practices to help reduce their environmental footprint, fostering an ethic that takes the Army beyond environmental compliance to sustainability.

(d) The Contractor shall appoint a SEM point of contact to DPW Environmental Division to include name, phone number and email address upon request by the Government.

9. SELF-HELP PROJECTS

(a) While performing work and/or occupying facilities on any US Army Garrison, Hawaii (USAG-HI) installation, the Contractor shall consult with the DPW Environmental Division before beginning any self-help project for guidelines on how to comply with historical property requirements and for verification of potential asbestos, lead-based paint and other environmental health hazards associated with the proposed self-help project.

(b) You can read more about asbestos and lead-based paint at:

http://www.garrison.hawaii.army.mil/sustainability/AsbestosLead.aspx

10. ENERGY AND WATER CONSERVATION

(a) Upon request by the Government, the Contractor shall appoint a Unit Energy Conservation Officer (UECO) and Building Energy Monitor (BEM) and fully participate in the Garrison's energy and water conservation program.

(b) The appointed BEM and UECO must attend the training class provided by the DPW Engineering Branch.

(c) The appointed UECOs and BEMs are responsible for ensuring energy-saving measures are being enforced in each building and to provide regular reports to DPW Engineering Branch showing how well the Contractor is doing at conserving energy.

(d) More information can be found on the installation sustainability and environmental management website at:

http://www.garrison.hawaii.army.mil/sustainability/Energy.aspx

11. AMC-LEVEL PROTEST PROGRAM

(a) If you have complaints about this procurement, it is preferable that you first attempt to resolve those concerns with the responsible Contracting Officer. However, you can also protest to Headquarters, AMC.

(b) The HQ, AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO.

(c) The AMC protest decision goal is to resolve protests within 20 working days from filing. To be timely, protests must be filed within the periods specified in FAR 33.103. Send protests (other than protests to the Contracting Officer) to:

Headquarters U.S. Army Materiel Command Office of Command Counsel 4400 Martin Road Rm: A6SE040.001 Redstone Arsenal, AL 35898-5000 Fax: (256)450-8840

(d) The AMC-level protest procedures are found at: http://www.amc.army.mil/amc/commandcounsel.html. If Internet access is not available, contact the Contracting Officer or HQ, AMC, to obtain the AMC-Level Protest Procedures.

12. REQUIRED INSURANCE

(a) The Contractor shall procure and maintain during the entire period of its performance under this contract the following minimum insurance:

AMOUNT

TYPE PER PERSON PER ACCIDENT PROPERTY

Comprehensive General Liability: $500,000 Comprehensive Automobile Liability $200,000 $500,000 $20,000

Workmen’s Compensation and Liability Insurance: As prescribed or required by law, with minimum employer liability limit of $100,000 for accidental bodily injury or death, or for occupational disease.

(b) Prior to the commencement of work, the Contractor shall furnish to the Contracting Officer a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the Government in such insurance shall not be effective for such period as may be prescribed by the laws of the State in which this contract is to be performed and in no event less than thirty (30) days after written notice thereof to the Contracting Officer.

(c) The Contractor agrees to insert the substance of this clause, including this paragraph (c) in all subcontracts hereunder.

(d) It is the Contractor’s responsibility to ensure the following changes are incorporated into their submitted Certificate of Insurance:

1. The contract number must appear in the body of the Certificate of Insurance.

2. The certificate holder name shall read:

Army Materiel Command Regional Contracting Office, Hawaii 413th CSB

The certificate shall be provided to the following address

413th Contracting Support Brigade Regional Contracting Office, Hawaii Contracting Operations Division 742 Santos Dumont Avenue Bldg.108, 3rd Floor (Wheeler Army Airfield) Schofield Barracks, HI 96857

(e) For all Contractors using the ACORD form dated earlier than October 2009, the Certificate of Insurance cancellation statement shall be revised as follows: Delete the words “endeavor to” and “but failure to do so shall impose no obligation or liability of any kind upon the insurer, its agents or representatives.” The Certificate of Insurance cancellation statement shall then read: “Should any of the above described policies be cancelled before the expiration date thereof, the issuing insurer shall mail 30 days written notice to the certificate holder named to the left.”

13. ACCESS TO ARMY INSTALLATIONS – PERSONNEL AND VEHICLES

(a) Commercial businesses shall possess and present a Contractor Installation Access Pass (IAP) to gain entry at any access control point (ACP). IAPs are processed by the Installation Access Pass Office, Building 6508, Leilehua Golf Course.

(b) In order to obtain a Contractor IAP, the Contracting Officer’s Representative (COR) must submit a signed and approved IAP application along with a personnel information sheet to the Installation Access Office. Printed proof of social security numbers are required to be presented with all substantiating documents to the IAP Office. After the office has processed the paperwork (typically two days), Contractor employees may pick up passes at the office.

Contractor employees shall bring some form of identification with proof of his or her social security number.

(c) Vendors and Contractors with commercial vehicles who do business on Army installations on a regular basis can receive extended passes for individual and fleet vehicles, for periods stipulated by the COR/sponsor, by registering their vehicles at the IAP Office. Company “Multiple Operator” memorandums shall be presented to IAP personnel upon requesting a vehicle IAP.

(d) The Contractor shall provide to the COR the names and social security numbers of individuals requiring access in performance of the contract no later than 14 days prior to start of performance. The Army Organization or Directorate for whom the Contractor is working is responsible for processing the paperwork to obtain passes.

(e) The Contractor is responsible for assuring personnel required to access any installation in performance of the contract obtain the required identification. Costs for employees to travel to the Government location shall be borne by the Contractor. Failure to obtain the required identification will not relieve the Contractor from contract performance. The Contractor shall be responsible for the return of identification cards upon expiration of the contract or when an employee is no longer performing work under the contract.

(f) The Contractor shall provide a list of the names of all employees and subcontractor employees who will access any Army facility in the performance of this contract. The Contractor shall provide written documentation used to verify employees and subcontractor’s employees compliance with FAR 52.222-54, Employment Eligibility Verification (clause that requires Contractor to do background check.) The Contractor shall provide written proof from the Immigration and Naturalization Service that all employees listed are approved for employment within the U.S.

(g) At any time Contractor employees are operating Contractor-owned vehicles on an Army Installation, they shall have in their possession a letter signed by a corporate officer authorizing the individual to drive the vehicle.

(h) The Contracting Officer and the Provost Marshal office shall be notified of any change in vehicles within three business days of the change.

(i) Lost vehicle passes shall be reported immediately in order to obtain new passes. All vehicle passes issued shall be returned to the Installation Access Office upon completion of the contract, termination of an employee or discontinued use of the registered vehicles.

(j) Failure to follow the procedures outlined above may result in delays in entering Army Installations. The Government is not responsible for any adverse impact on the Contractor or its operation as a result of delays due to the failure to register vehicles.

(k) Contractors operating vehicles on an Army post shall not use cell phones unless used with a hands-free device.

This applies to ALL personnel driving privately-owned and Government vehicles on Army installations and housing areas. Failure to comply will result in the loss of on-post driving privileges:

First offense – 14 days Second offense – 30 days Third offense – 180 days

If caught driving while privileges are suspended, privileges may be further suspended for a 5-year period.

(l) The Provost Marshall has the authority to change the above procedures without notice. Contractors shall adhere to any change in security procedures.

14. DOD ANTITERRORISM (AT) AND OPERATIONAL SECURITY (OPSEC) STANDARDS

(a) Pursuant to Department of Defense Instruction Number 2000, “DoD Antiterrorism (AT) Standards,” dated October 2, 2006, each Contractor employee requiring access to a Federally-controlled installation, facility and/or Federally-controlled information system(s) shall complete Level I AT Awareness Training on an annual basis and receive a certificate of completion.

Detailed information on each of these items are stated below. Applicable items to this contract action are indicated below:

[X] 1. AT level I Training (general) [X] 2. Access and general protection policy and procedures [ ] 2a. For contractor requiring Common Access Card (CAC) [X] 2b. For contractor not eligible for CAC, but requires access to DoD facility or installation [ ] 3. AT Awareness training for US based contractor personnel traveling overseas [X] 4. iWatch training [ ] 5. Army Training Certificate Tracking System (ATCTS) registration for contractor [ ] 6. For contracts that require a formal OPSEC program [X] 7. Requirement for OPSEC training [ ] 8. Information assurance/information technology training [ ] 9. Information assurance/information technology certification [ ] 10. Contractor Authorized to Accompany the Force clause [ ] 11. Contract requiring performance or delivery in a foreign county [ ] 12. Handling/Access to Classified information [X] 13. Threat Awareness Reporting Program

1. AT Level I training. Required for Contractor employees with an area of performance within an Army controlled installation, facility or area. All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 7 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee, to the COR or to the Contracting Officer if a COR is not assigned, within five calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil

2. Access and general protection/security policy and procedures. Required for Contractor employees with an area of performance within an Army controlled installation, facility, or area. The Contractor and all associated sub-contractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services or Security Office. The Contractor workforce shall comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contract or Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.

2a. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contract or Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

2b. For contractors that do not require CAC, but require access to a DoD facility or installation. The Contractor and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

3. AT Awareness Training for Contractor Personnel Traveling Overseas. Required for U.S. based Contractor employees and associated sub-contractor employees to make available and to receive Government provided area of responsibility (AOR) specific AT awareness training as directed by AR 525-13. Specific AOR training content is directed by the combatant commander with the unit ATO being the local point of contact.

4. iWATCH Training. Required for Contractor employees with an area of performance within an Army controlled installation, facility or area. The Contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. See also paragraph 25, iWatch Training.

5. Army Training Certification Tracking System (ATCTS) registration. Required for Contractor employees who require access to Government information systems. All Contractor employees with access to a Government Information System (IS) shall be registered in the ATCTS (Army Training Certification Tracking System) at commencement of services, and shall successfully complete the DoD Information Assurance Awareness training prior to access to the IS and then annually thereafter.

6. For contracts that require a formal OPSEC program. The Contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan within 90 calendar days of contract award, to be reviewed and approved by the responsible Government OPSEC officer. This plan shall include a process to identify critical information, where it is located, who is responsible for it, how to protect it and why it needs to be protected. The Contractor shall implement OPSEC measures as ordered by the commander. In addition, the Contractor shall have an identified certified Level II OPSEC coordinator per AR 530-1.

7. For contracts that require OPSEC Training. Per AR 530-1 Operations Security, Contractor employees shall complete Level I OPSEC Awareness training. New employees shall be trained within 30 calendar days of their reporting for duty and annually thereafter.

8. For information assurance (IA)/information technology (IT) training.

This is the start of the file's text. The full file is on GovTribe.