- Replace Generator and Switchgear B504 & B506, Tinker Air Force Base, Oklahoma Federal contract opportunity
- Solicitation number
- W912BV-16-R-0137
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Appendix_E-B506_Electric_Report.xlsx | XLSX spreadsheet | |
| W912BV-16-R-0137_Amendment_6_extend_due_date.pdf | ||
| W912BV-16-R-0137-0005.pdf | ||
| Appendix_D-910722.pdf | ||
| Appendix_D-820014.pdf | ||
| Appendix_D-DACA56-84-C-0050.pdf | ||
| Appendix_D-890004.pdf | ||
| Appendix_D-DACA63-73-C-0179.pdf | ||
| Appendix_C-2016_TAFB_ELECTRICAL_STANDARD.pdf | ||
| W912BV-16-R-0137-0004.pdf | ||
| SIGN_IN_SHEET_DLA_Generators_20_Oct_16_Site_Visit.pdf | ||
| W912BV-16-R-0137-0003.pdf | ||
| Appendix_B-_DLA_Tinker_Electrical_Power_System_Assessment.pdf | ||
| W912BV-16-R-0137-0002.pdf | ||
| W912BV-16-R-0137-0001.pdf | ||
| W912BV-16-R-0137.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
DLA Replace Generator & Switchgear B504 & B506, Tinker AFB, OK.
1. This amendment revises Section 00 22 11.
2 Appendix E is incorporated into this solicitation for informational purposes. Appendix E will provide the electrical consumption data in kWh (average demand/load) for B506 and bidders are to size the new generators for 20% more than the average demand.
CE Energy also suggests using the June consumption data while sizing the generators.
See pg 2 for continuation of block 14
1. CONTRACT ID CODE PAGE OF PAGES
1 15
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BV-16-R-0137
X 9B. DATED (SEE ITEM 11)
30 Sep 2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
4 Jan 2017
CODE
CONTRACTING DIV
USACE, TULSA 1645 S 101 E AVE
TULSA OK 74128-4609
W912BV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
X
X 1
W912BV-16-R-0143
Amendment 0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Continuation of block 14:
3. The proposal due date and time IS EXTENDED to 2 PM CST, 20 January 2017.
4. POC for this amendment is Pun Chittchang, punnie.chittchang@usace.army.mil, 918-669-7544.
5. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED BY THIS AMENDMENT
*AM7 00 22 11 - 1*
SECTION 00 22 11
PROPOSAL PREPARATION AND EVALUATION CRITERIA
1.0 PART I -- PROPOSAL INSTRUCTIONS
1. 1 PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS
a. REQUIREMENT FOR SEPARATE PRICE AND TECHNICAL PROPOSALS.
(1) Each Offeror must submit both a Price Proposal and a Technical Proposal. The Price Proposal and the Technical Proposal must be submitted as separate volumes. Ensure that the outside of each separate volume is clearly marked to indicate its contents; and the identity of the offeror. Additionally, clearly identify the “original” price proposal and the “original” technical proposal on the outside cover.
(2) Both the Price Proposal and the Technical Proposal must be received by the closing date and time set for receipt of proposals.
(3) No dollar amounts from the Price Proposal are to be included in the Technical Proposal.
(4) All information intended to be evaluated as part of the Technical Proposal must be submitted as part of the Technical Proposal. Do not merely cross-reference similar material in the Price Proposal, or vice versa. Also, do not include links to websites in lieu of incorporating information into your proposal.
(5) Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the offer may be determined "unacceptable" and thus ineligible for award. Should the offeror have any questions related to specific terms and conditions, these should be resolved prior to submission of the offer.
b. DISCUSSIONS. The Government does not intend to enter into discussions with offerors prior to making an award. Offerors are encouraged to present their best technical proposal and prices in their initial proposal submission. However, in accordance with FAR Part 15.306, should discussions become necessary, the Government reserves the right to hold them. If this occurs, a competitive range will be determined and offerors notified. The competitive range may be limited for purposes of efficiency in accordance with (IAW) FAR Part 15.306(c)(2).
c. COST OR PRICING DATA. Offerors are not required to submit Cost or Pricing Data with their offers.
d. GENERAL INSTRUCTIONS.
(1) Submit only the electronic files specifically authorized and/or required elsewhere in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc. All pages should be numbered.
(2) Proposal materials shall be submitted via AMRDEC SAFE website https://safe.armdec.army.mil/safe/ , or via email, containing the proposal in PDF file format using Adobe Acrobat software. Proposals shall be tabbed and labeled in a manner to afford easy identification from a Table of Contents. Each page shall be identified with the appropriate page number centered at the bottom of the page. Sheet size of the proposal contents shall be 8-1/2 inches x 11 inches where sheets are prepared specifically for this proposal, unless another paper size is specifically authorized elsewhere in this section for a particular submission. Do not use alternative paper sizes (e.g., 11” x 14” or 11” x 17” sheets) unless specifically authorized in this section for a particular submission. Do not use a font size smaller than 10, an unusual font style such as script, or condensed print for any submission. All page margins must be at least 1 inch wide, but may include headers and footers.
*AM7 00 22 11 - 2*
(3) Provide read-only PDF file format using Adobe Acrobat software containing the technical volume as well as a read-only PDF format using Adobe Acrobat software containing the price volume.
(4) “Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror’s technical proposal. Offerors that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offerors—Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data”.
(5) For submissions with page limitations, the pages will be counted as follows: One side of the paper is one page; information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, fold-out pages (11" x 14" or 11" x 17") will count as one page. Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are not included in the page limitation.
(6) Proposal revisions shall be submitted as page replacements with revised text readily identifiable, e.g., bold face print or underlining. The source of the revision, e.g., Error, Omission, or Clarification, or amendment shall be included and be annotated for each revision. Proposal replacement pages shall be numbered, shall be clearly marked “REVISED”, shall show the date of revision, shall be submitted in appropriate number of copies (e.g., if two (2) copies of the original page was required, then two (2) copies of the revised page will also be required). A revised copy of the entire proposal in .pdf format shall be provided.
e. SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL
(1) Number of Sets of the Price Proposal. Submit an ORIGINAL set of the Price Proposal.
(2) Size Restrictions and Page Limits. Use only 8 ½” x 11” pages. There are no page limits set for the price proposal. However, limit your response to information required by this solicitation. Excess information will not be considered in the Government’s evaluation.
(3) Format and Contents of the Price Proposal and List of Tabs. The Price Proposal shall be appropriately labeled as such and shall be organized as indicated in the following chart. Note: If the Offeror is not required to submit any information under a listed Tab in accordance with the instructions below, that tab can be omitted.
However, do not renumber the subsequent tabs.
TAB CONTENTS OF THE PRICE PROPOSAL
#1 The Proposal Cover Sheet
#2 Signed Letter Responding to RFP and Acknowledgement of Amendments
#3 Section 00 11 00, Pricing (CLIN) Schedule
#4 Bid Guarantee (Bid Bond)
#5 Representations and Certifications
(4) Detailed Submission Instructions for the Price Proposal
TAB 1: The proposal cover sheet is required by FAR 52.215-1(2) (c) (i)-(v) and must be submitted by all offerors. This provision, titled “Instructions to Offerors—Competitive Acquisition,” and the format for the proposal cover sheet as shown here:
*AM7 00 22 11 - 3*
TAB 2: The Letter provided to respond to this Request for Proposal is to be completed by all Offerors and duly executed with an original signature by an official authorized to bind the company in accordance with FAR 4.102. All amendments must be acknowledged by all Offerors in accordance with the instructions on the Standard Form 30, Amendment of Solicitation.
TAB 3: Section 001100, CLIN Schedule is to be completed in its entirety by all Offerors. See Section 001100 with attached notes, for further instructions.
TAB 4: Provide a fully executed Bid Bond as required by FAR Clause 52.228-1, Bid Guarantee.
TAB 5: All Offerors must have electronically completed the annual representations and certifications on the “Online Representations and Certifications Application” (ORCA) website or respond with the completed representations/certifications found in the solicitation. The Offerors are responsible for ensuring that these on-line Representations and Certifications are updated as necessary to reflect changes, but at least annually to ensure that they are kept current, accurate and complete. Additionally, the Offeror must also complete and return the “Representations, Certifications, and Other Statements of Offerors” included in the solicitation. If the Offeror is a Joint Venture, all participants must separately complete both the ORCA Representations and Certifications.
e. SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL
(1) Number of Sets of the Technical Proposal. Submit the ORIGINAL and ONE additional set of the written Technical Proposal.
(2) Format and Contents of the Technical Proposal and List of Tabs. The original and all copies of the technical proposal will be appropriately labeled as such. Each set shall be organized using the tabs specified in the following chart.
PROPOSAL COVER SHEET
1. Solicitation Number:
2. The name, address, and telephone and facsimile numbers of the Offeror (and electronic address if available):
3. Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this solicitation:
4. Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
5. Tax Identification number of Offeror.
*AM7 00 22 11 - 4*
*AM7 TAILOR THESE FACTORS TO THE SPECIFIC PROJECT*
TAB CONTENTS OF THE TECHNICAL
PROPOSAL
Factor #1 EXPERIENCE
Factor #2 PERSONNEL
Factor #3 PAST PERFORMANCE
(3) Page Limitations. The following page limitations are established for each factor described above:
(a) Factor #1, Experience – Limited to 5 pages (a maximum of 5 forms)
(b) Factor #2, Personnel – Limited to 1 page for each resume provided
(c) Factor #3, Past Performance – *AM7 Limited to 20 Pages*
Tables of content, proposal cover letters, and tabs between proposal information do not count toward any page limitations in the proposal.
(4) Detailed Submission Requirements for the Technical Proposal. The following is a detailed description of the information to be submitted under each TAB.
(i) TAB 1: FACTOR 1, EXPERIENCE: Demonstrate the experience of the offeror and/or proposed team, including sub-contractors, on projects same/similar to that described in the solicitation for same/similar construction services. If using subcontractors as part of the proposed team to demonstrate experience, describe the role they will play in this project and the percentage of work they will perform.
The Contractor shall complete a minimum of three (3), but no more than five (5), “Experience Information” forms, attached at the end of this section, in response to this factor. All blocks must be filled in and all data should be accurate, current, and complete. All projects submitted must be at least 50% complete and completed within the last 5 years. At least two (2) of the projects provided must be valued at over $3,000,000.
If any of the information required is not included in the form then the contractor will be considered non-responsive and evaluated as unacceptable.
(SEE EXPERIENCE INFORMATION FORM IN ATTACHMENT 1)
(ii) TAB 2: FACTOR 2, PERSONNEL: The offeror must provide resume data for the following key personnel: *AM7 Electrical Engineer (DoR),* Project Manager, Safety Officer, Quality Control Manager, Site Superintendent, as applicable to this requirement. *AM7 See Section 01 45 00.00 10 QUALITY CONTROL for the Project Manager, Quality Control Manager (CQC System Manager), and Site Superintendent requirements; 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS for the SSHO. The Electrical Engineer shall be a registered professional engineer with a minimum of 5 years professional experience as an electrical engineer.*
Resume information to be provided shall be limited to no more than one (1) page per person and shall include the following information as a minimum:
*AM7 00 22 11 - 5*
(a) Name and title
(b) Project assignment
(c) Name of firm with which associated
(d) Years experience with this firm and with other firms
(e) Education degree(s), year, specialization, if applicable
(f) Active professional registration, year first registered, if applicable
(g) Other experience and qualifications relevant to same/similar work required under this contract
(iii) TAB 3: FACTOR 3, PAST PERFORMANCE: For the projects listed under Factor 1 – Experience, the Government will query the Contractor Performance Assessment Reporting System (to include ACASS, CCASS, and CPARS) to validate past performance ratings on Department of Defense contracts and any other past performance information the Government deems necessary to evaluate a contractor’s past performance. Firms without a history of past performance will be neutral rating.
For each project that does not have a ACASS, CCASS, or CPARS evaluation, Offerors shall forward a copy of the Past Performance Questionnaire (PPQ) included at Attachment 2 to the points of contact responsible for monitoring performance under such contracts. The Past Performance Questionnaire included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 2. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment 2) which will provide contract nd client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Contract Specialist identified in Part A, Paragraph 1 of Section 00 21 00, Instructions, Conditions, and Notices to Offerors via email prior to proposal closing date.
Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
The information contained in the questionnaires will be used to evaluate the offeror’s past performance. If any negative past performance information is received, the contractor will be given an opportunity to provide rebuttal. Each contractor shall provide at least three (3) past performance ratings. Any rating an offeror has in ACASS, CCASS, and CPARS for the projects listed under Factor 1 will count toward this requirement. The offeror is responsible for ensuring that the KO has received a minimum of three (3) questionnaires prior to that date/time or has provided written notification to the KO that they have current ratings in ACASS, CCASS, and CPARS. Entities that have no past customers shall notify the KO in writing, prior to the date and time established for the RFP closing, that they have had no previous clients and that the minimum number of questionnaires cannot be provided. It is the contractor’s responsibility to ensure that the reference documentation is provided, as the Government may not make additional requests for past performance information from the references. The evaluation form shall be provided to the Contract Specialist directly from the reference. Do not request past performance questionnaires on projects that have final ACASS, CCASS, or CPARS evaluations. If a past performance questionnaire is received on a project where a final ACASS, CCASS, or CPARS evaluation exists, the ACASS, CCASS, or CPARS evaluation will serve as the official rating of record for evaluation purposes.
The Government may contact references provided as part of Factor 1 – Experience, for information regarding the offeror’s past performance on the project and for the purposes of assessing and verifying the scope of the work performed. Offerors should provide accurate, current, and complete contact information for references provided in the project descriptions.
The Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity
*AM7 00 22 11 - 6*
Information System (FAPIIS), Electronic Subcontract Reporting System (ESRS), and any other sources not provided by the offeror.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
2.1 PART II. EVALUATION OF OFFEROR PROPOSALS
2.2 SOURCE SELECTION USING THE LOW-PRICED, TECHNICALLY ACCEPTABLE PROCESS.
An evaluation for acceptability will be performed on the low price proposal in accordance with FAR 15.101-2(b)(3).
The proposal that provides the lowest price and is otherwise technically acceptable in all factors will be selected for award. To be considered technically acceptable, no technical factor in the proposal may be determined to be unacceptable. The failure of a proposal to meet any of the requirements will result in a technically unacceptable rating and preclude award.
2.3 BASIS OF AWARD. Award will be made on the basis of the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-cost factors. Tradeoffs are not permitted. Proposals will be evaluated for acceptability but not ranked using non-cost/price factors.
If awarded a contract, the Offeror shall construct the project in accordance with the plans and specifications contained in the RFP.
2.4 EVALUATION OF THE PRICE PROPOSALS
a. Price will be evaluated and considered but will not be scored or combined with other aspects of the proposal evaluation. The proposed prices will be analyzed for reasonableness. They may also be analyzed to determine whether they are realistic for the work to be performed, reflect a clear understanding of the requirements, and are consistent with the information provided by the Offeror. Additionally, all offers will be analyzed for unbalanced pricing in accordance with FAR 15.404-1(g) and may be rejected if it is determined that the lack of balance poses an unacceptable risk to the Government.
b. The otherwise technically-acceptable, lowest-priced offeror may be required to confirm its price on either a CLIN, element, or total price basis, and/or provide additional information in support of their price, prior to contract award at the Government’s request and discretion.
2.5 EVALUATION OF THE TECHNICAL PROPOSAL. Each Technical Proposal will be evaluated based on the following evaluation criteria:
a. FACTOR 1: EXPERIENCE: The Government will review the project experience of the offeror, including subcontractors, on projects provided in response to Factor 1. Offerors must meet all of the following minimum acceptability standards to receive a “ACCEPTABLE” on this factor:
(1) Proposed team must have at least three (3) projects that are same/similar to that of the work found in this solicitation; AND
(2) At least two (2) of the projects submitted must be valued at over $3,000,000, and they must have been at least 50% complete within the last 5 years.
Failure to demonstrate the minimally acceptability standards under this factor will result in a “UNACCEPTABLE” rating and possible elimination from further consideration for contract award.
b. FACTOR 2: PERSONNEL: The Government will review the resumes provided in response to Factor
2. Offerors must demonstrate all of the following minimum acceptability standards to receive a “ACCEPTABLE” on this factor.
*AM7 00 22 11 - 7*
The offeror must demonstrate in all resumes that the key personnel proposed have:
(1) A minimum of 5 years of specialized experience in their field; AND
(2) Experience on projects same/similar to the work in this solicitation working in the position they are assigned to under this contract.
Failure to demonstrate the minimally acceptability standards under this factor will result in a “UNACCEPTABLE” rating and possible elimination from further consideration for contract award.
c. FACTOR 3: PAST PERFORMANCE: The Government will review all CPARS, ACASS, CCASS evaluations regardless of project and past performance questionnaires for projects submitted under Factor 1. The Government may contact points of contacts listed on the “Experience Information” forms submitted under Factor
1. Offerors must demonstrate the following minimum acceptability standards:
All past or current references must have overall ratings of satisfactory or above.
FAR 15.101-2(b)(1) requires if the KO determines that a small business' past performance is not acceptable, the matter is referred to the SBA for a COC determination.
Failure to demonstrate the minimally acceptable criteria under this factor will result in an “Unacceptable” rating and elimination from further consideration for contract award. In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305(a)(2)(iv)). Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability. “unknown” shall be considered “acceptable”.
2.6 GENERAL TECHNICAL CRITERIA
a. Material omission(s) may cause the technical proposal to be rejected as unacceptable.
b. Proposals which are generic, vague, or lacking in detail may be considered unacceptable. The offeror’s failure to include information that the Government has indicated should be included may result in the proposal being found deficient if inadequate detail is provided.
c. The Government cannot make award based on a deficient offer. Therefore, receipt of an
“UNACCEPTABLE” determination of acceptability for any factor will make the offer ineligible for award, unless the Government elects to enter into discussions with that Offeror and all deficiencies are remedied in a revised proposal. Note: It is the Government’s intent to award without discussions.
*AM7 00 22 11 - 8*
ATTACHMENT 1
EXPERIENCE INFORMATION
(To be completed by Contractor)
1. Contractor:
Name:
Address:
2. Contract /Task Order(TO) /Purchase Order (PO) Number:
3. Contract/TO/PO Dollar Value:
4. Contract/TO /PO Status: Active Complete
Completion Date (w/ extensions):
5. Project Title:
Location:
6. Project Description-- to include the role of the contractor on the project and specific responsibilities of the contractor in performance of the effort:
7. Project Owner or Project Manager for the Client – provide:
Name:
Address:
Telephone Number and E-mail:
ATTACHMENT 2
NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0) CONTRACT INFORMATION (Contractor to complete Blocks 1-4)
1. Contractor Information Firm Name: CAGE Code:
Address: DUNs Number:
Phone Number:
Email Address:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:
If subcontractor, who was the prime (Name/Phone #):
3. Contract Information Contract Number:
Delivery/Task Order Number (if applicable):
Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):
Contract Title:
Contract Location:
Award Date (mm/dd/yy):
Contract Completion Date (mm/dd/yy):
Actual Completion Date (mm/dd/yy):
Explain Differences:
Original Contract Price (Award Amount):
Final Contract Price (to include all modifications, if applicable):
Explain Differences:
4. Project Description:
Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)
CLIENT INFORMATION (Client to complete Blocks 5-8)
5. Client Information Name:
Title:
Phone Number:
Email Address:
6. Describe the client’s role in the project:
7. Date Questionnaire was completed (mm/dd/yy):
8. Client’s Signature:
NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS.
CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM.
RATING DEFINITION NOTE
(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract.
There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable No information or did not apply to your contract Rating will be neither positive nor negative.
ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE
TO BE COMPLETED BY CLIENT
PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.
1. QUALITY:
a) Quality of technical data/report preparation efforts E VG S M U N
b) Ability to meet quality standards specified for technical performance E VG S M U N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance E VG S M U N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E VG S M U N
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract E VG S M U N
3. CUSTOMER SATISFACTION:
a) To what extent were the end users satisfied with the project? E VG S M U N
b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;
responsiveness to administrative reports, businesslike and communication)
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer? E VG S M U N
d) Overall customer satisfaction E VG S M U N
4. MANAGEMENT/ PERSONNEL/LABOR
a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force? E VG S M U N
b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N
c) Government Property Control E VG S M U N
d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N
e) Utilization of Small Business concerns E VG S M U N
f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes E VG S M U N
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program) E VG S M U N
5. COST/FINANCIAL MANAGEMENT
a) Ability to meet the terms and conditions within the contractually agreed E VG S M U N price(s)?
b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client E VG S M U N
c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section. Yes No
e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
Yes No
f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below. Yes No
6. SAFETY/SECURITY
a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes:
following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)
b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N
7. GENERAL
a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N
c) Would you hire or work with this firm again? (If no, please explain below) Yes No
d) In summary, provide an overall rating for the work performed by this contractor. E VG S M U N
Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):
(End of Summary of Changes)
| SECTION 00 22 11 |
| e. SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL |
| e. SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL |
| *AM7 TAILOR THESE FACTORS TO THE SPECIFIC PROJECT* |
| $3,000,000. |
| 2.1 PART II. EVALUATION OF OFFEROR PROPOSALS |
| 2.4 EVALUATION OF THE PRICE PROPOSALS |
| 2.6 GENERAL TECHNICAL CRITERIA |
| ATTACHMENT 1 |
| ATTACHMENT 2 |
| Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluati... |