Amendment 3 - Specification Changes and Answers to Questions

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US ARMY ENGINEER DISTRICT, PHILADELPHIA

POC ROBERT W. HUTCHEON

100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Changes to Specifications

Changes to Clauses

Answ ers to questions.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Oct-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU-16-B-0022

X 9B. DATED (SEE ITEM 11)

12-Aug-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Oct-2016

CODE

US ARMY ENGINEER DISTRICT, PHILADELPHIA

CONTRACTING DIVISION

WANAMAKER BUILDING

100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

W912BU 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912BU

FACILITY CODECODE

EMAIL:TEL:

W912BU-16-B-0022

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been added by reference:

52.232-16 Alt I Progress Payments (Apr 2012) - Alternate I MAR 2000

The following have been deleted:

52.214-21 Descriptive Literature APR 2002 52.232-15 Progress Payments Not Included APR 1984

(End of Summary of Changes)

Amendment No. 0003

IFB W912BU-16-B-0022

14. DESCRIPTION OF AMENDMENT (continued)

a. REQUESTS FOR INFORMATION (RFI) WITH RESPONSES: RFI’s with responses, annotated Amendment No. 0003, are attached to this amendment.

b. BIDDING SCHEDULE: Please delete page 00 10 00-3 in its entirety and substitute the revised page 00 10 00-3, annotated Amendment No. 0003, attached hereto.

c. SECTION 00 21 00 INSTRUCTIONS: Please delete this section in its entirety and substitute the revised Section 00 21 00, annotated Amendment No. 0003, attached hereto.

c. SECTION 00 73 00 SPECIAL CLAUSES: Please delete page 00 73 00-2 in its entirety and substitute the revised page 00 73 00-2, annotated Amendment No. 0003, attached hereto.

d. SECTION 00 73 15 WAGE RATES: Please delete this section in its entirety and substitute the revised Section 00 73 15, annotated Amendment No. 0003, attached hereto.

e. TECHNICAL SPECIFICATIONS:

(1) PROJECT TABLE OF CONTENTS: Please delete the Project Table of Contents in its entire and substitute the revised Project Table of Contents, annotated Amendment No. 0003, attached hereto.

(2) Section 01 11 00 – SUMMARY OF WORK: Please delete page 01 11 00-2 in its entirety and substitute the revised page 01 11 00-2, annotated Amendment No. 0003, attached hereto.

(3) Section 01 22 00 - MEASUREMENT AND PAYMENT: Please insert new Section 01 22 00, annotated Amendment No. 0003, attached hereto.

(4) Section 01 32 33 - CONSTRUCTION PHOTOGRAPHY: Please delete page 01 32 33-3 in its entirety and substitute revised page 01 32 33-3, annotated Amendment No. 0003, attached hereto.

(5) Section 01 35 26 - GOVERNMENTAL SAFETY REQUIREMENTS: Please delete page 01 35 26-21 in its entirety and substitute the revised page 01 35 26-21, annotated Amendment No. 0003, attached hereto.

(6) Section 01 35 29 - HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR CONTAMINATED SITES: Please delete pages 01 35 29-8 and 01 35 29-9 in their entirety and substitute the revised pages 01 35 29-8 and 01 35 29-9, annotated Amendment No. 0003, attached hereto.

(7) Section 01 57 20 - ENVIRONMENTAL PROTECTION: Please delete pages 01 57 20-8 through 01 57 20-15 in their entirety and insert new pages 01 57 20-8 through 01 57 20-20, in their entirety, annotated Amendment No. 0003, attached hereto.

(8) Section 01 71 23 – SURVEY REQUIREMENTS: Please delete page 01 71 23-8 in its entirety and substitute the revised page 01 71 23-8, annotated Amendment No. 0003, attached hereto.

(9) Section 02110 - SITE CLEARING: Please delete this section in its entirety and substitute the revised Section 02110, annotated Amendment No.

0003, attached hereto.

(10) Section 02630 – STORM DRAINAGE: Please delete page 02630-2 in its entirety and substitute the revised page 02630-2, annotated Amendment No.

0003, attached hereto.

14. DESCRIPTION OF AMENDMENT (continued)

(11) Section 02900 – LANDSCAPING: Please delete pages 02900-9 and 02900-15 in their entirety and substitute the revised pages 02900-9 and 02900-15, annotated Amendment No. 0003, attached hereto.

f. CONTRACT DRAWINGS: Please delete the following drawing in its entirety and substitute the revised drawing of the same number, with the latest revision date of 16 September 2016, attached hereto:

C-21.02

g. Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0003. Failure to acknowledge all amendments may be cause for rejection of the bid.

RFI

Dwg Sheet/ Spec Section Request for Information Response

Would like to request the same drawings in CAD format. Are these files available?

No, PDF drawings are sufficient for bidding purposes. CAD drawings will be issued to winning bidder for their use during the execution of the project.

- Is a security guard required at the site? If so, what hours is the security guard to work?

Security requirements are covered in the specifications. Contractor should bid per the plans and specifications (P&S).

- Is there an available fire hydrant on-site to be used as a water source for dust control? - No utilities onsite.

- The Bidding Schedule, Item No. 8, “Borrow-Cap Final Cover Soil Layer – 51,500 EA”. Should the EA be CY?

“EA” will be changed to “CY”. See Amendment No. 0003

- The Bidding Schedule with the Items and Descriptions, does not include items for Mobilization, Health and Safety or Survey. Can these Lump Sum bid items be added to the bid schedule?

Measurement and payment paragraphs for those items are covered in each section.

Contractor should bid as required per the P&S.

- Regarding the clearing and grubbing, can the trees and stumps be grinded and these chippings be buried beneath the cap in the existing site soils?

Specification Section 02110 – Site Clearing has been modified.

See Amendment No. 0003.

7 - Can the Bid Date be extended two weeks? See Amendment No. 0001.

- In order to provide power to the trailer staging area, power would need to run from one of the poles along East Pumping Station Road to the staging area trailers. Can the Contractor install temporary utility poles in this corridor? Would these temporary poles be installed on private property?

Power requirements are covered in the specs and are the contractor’s responsibility. Contractor should bid per the plans and specifications (P&S).

- Within the specified schedule, can the Contractor enact a winter shut-down, then startup again in the spring?

Specific project schedule is the contractor’s responsibility and in conjunction with the period of performance and listed weather days, the contractor should bid per the P&S.

- Is there a Project Labor Agreement (PLA) in force for this project?

All references to a PLA deleted. See Amendment No. 0001.

11 - Is this project exempt from Pennsylvania State Sales Tax? No sales tax exemption.

Is Perimeter Air Monitoring required? If perimeter air monitoring is required:

Air monitoring requirements are covered in the P&S and the contractor should bid as required.

13 - What number of stations are required? See Amendment No. 0003

14 - Where would they be located? See Amendment No. 0003

- Would the stations operate during working hours only (8 hours per day, 5-days per week)? See Amendment No. 0003

16 - Would we be only monitoring for dust? See Amendment No. 0003

17 - Is remote telemetry required? Remote telemetry is not required

18 - Is a weather station required w/ remote telemetry? Remote telemetry is not required

- Is analytical sampling of airborne contaminants required (i.e. collecting field samples and having them tested by a laboratory)?

As an assistance, a link to the Admin Order and RI will be provided. See Amendment No. 0003.

20 - What is the frequency of this confirmatory air sampling? See Amendment No. 0003

21 - How many sample locations are required? See Amendment No. 0003

22 - What constituents are we testing for? See Amendment No. 0003

Section 52.222-33 (e) states : The offeror shall submit to the Contracting Officer a copy of the project labor agreement with its offer”.

All references to a PLA deleted. See Amendment No. 0001.

1. Is there an existing Project Labor Agreement (PLA) in place for the site or will the selected offeror be required to negotiate the PLA with local labor organizations?

All references to a PLA deleted. See Amendment No. 0001.

25 2. If an existing PLA is in place, please provide.

All references to a PLA deleted. See Amendment No. 0001.

REQUESTS FOR INFORMATION with RESPONSES

Solicitation No. W912BU-16-B-0022

Amendment No. 0003

Amendment No. 0003

Request For Information Page 1

Dwg Sheet/ Spec Section Request for Information Response

3. Is the offeror expected to negotiate and execute a PLA prior to bid submission?

All references to a PLA deleted. See Amendment No. 0001.

- Section 02150, 3.11 Tree Protection – How is the Contractor to estimate the quantity of trees required to be protected. Can a unit price item be added to the bid?

Limits of work determine items of work and are clear on the drawings.

Contractor should bid per the P&S.

Section 007000, 52.232-5 – This section infers that the Government may retain up to 10% for retainage. Is it the intent for the Government to hold 10% retainage during the course of this project?

Requirements are as listed. Contractor should bid per the P&S.

Section 01 11 00, 1.6 Underground Utilities – Requires the Contractor to scan the site with electromagnetic or sonic equipment. Are there existing utilities expected to be encountered within the landfill limits? Can this requirement be waived or modified to reduce the extent of this scan? Will the Contractor be required to relocate any utilities?

No utilities expected onsite. See Amendment No. 0003.

Section 00 73 00, 1.2, b Time extensions – This section indicates the monthly anticipated adverse weather delays anticipated during each month of the year. This does not appear to take into account that for liner installation, temperatures need to be plus 40 degrees. Will the government take this into consideration during construction?

Specific project schedule is the contractor’s responsibility and in conjunction with the period of performance and listed weather days, the contractor should bid per the P&S.

Section 02210, 3.2 Disposal of Site Materials – During the Clearing phase of work, is the Contractor required to dispose of trees and stumps off-site? See Amendment No. 0003.

Section 02900, 3.12 Guarantee Period, para. A – “…At the end of the guarantee period, the contractor shall reset the grades that have settled below the proposed grades on the drawings”? How can the Contractor quantify this work in their bid?

Specification Section 02900 – Landscaping has been modified.

See Amendment No. 0003.

Section 02900, 3.9 Maintenance of the Seeded Areas. In what item is the first and second years of seed maintenance and listed mowings per year included in? Can a separate O&M item be added?

Clarification: Cost for first and second years of maintenance of seeded areas should be part of Landscaping price. An O&M bid item will not be provided.

How is the Contractor compensated for the labor, equipment, fill and restoration that may be needed to restore these grades, which we cannot quantify?

Specification Section 02900 – Landscaping has been modified.

See Amendment No. 0003.

Section 02900, 2.5 Deer Fencing – where is this installed and what quantity?

Specification Section 02900 – Landscaping has been modified.

See Amendment No. 0003.

* Section 02900, 3.12 Guarantee - what is the length of the landscaping guarantee?

Specification Section 02900 – Landscaping has been modified.

See Amendment No. 0003.

* Are the soil import trucks required to be pressure washed upon exiting the site?

Clarification: Yes, see Drawing C90.01, Detail 3.

* Section 1.14 Personal Hygiene and Decontamination: Does the Site Excavation and Relocation Item - 36,000 CY require an EZ and CRZ or can the entire excavation perimeter be an EZ with the equipment remaining inside the EZ perimeter?

Information is provided. Contractor should bid per the P&S.

* Section 1.14 Personal Hygiene and Decontamination: Are EZ and CRZ zones required for the Site Excavation and Relocation Item - 36,000 CY?

Information is provided. Contractor should bid per the P&S.

* Is temporary security fencing required around the entire site perimeter?

Information is provided. Contractor should bid per the P&S.

* Traffic control – is a flagman required at the site entrance during the importation of the fill and topsoil materials?

Information is provided. Contractor should bid per the P&S.

* Can any sediment from the temporary sediment ponds from the dewatering, stormwater and contact water be disposed under the cap?

Clarification: Refer to Drawing C90.03, Detail 1 and Section 02240 – Dewatering.

Amendment No. 0003

Request For Information Page 2

Dwg Sheet/ Spec Section Request for Information Response

Item - Site Excavation and Relocation Item - 36,000 CY: Is daily cover required during the regrading? If daily cover is required during the regrading for odor control, can on-site soils be used? No, not required.

Item - Site Excavation and Relocation Item - 36,000 CY:

Is this item 36,000 CY of excavation and 36,000 CY of on-site backfilling?

Unit price for the 36,000 CY of excavation and relocations should include excavation, relocation, placement, and compaction. See Amendment No. 0003.

Geomembrane – 02340-14, 3.7.D – Conformance Testing: can this testing be performed by the manufacturer before its shipped to the site, instead of obtaining samples at the site after the material has been delivered?

No. Information is provided. Contractor should bid per the P&S.

Geocomposite – 02350-6, 3.1.B – Conformance Testing: can this testing be performed by the manufacturer before its shipped to the site, instead of obtaining samples at the site after the material has been delivered?

No. Information is provided. Contractor should bid per the P&S.

Inquiring on the status of the pre-bid sign-in sheets for the above referenced project. See Amendment No. 0001

Is there anyway the sign-in sheet for the site visit can be released this week? See Amendment No. 0001

Inquiring on the status of the pre-bid sign-in sheets for the above referenced project. See Amendment No. 0001

Is there anyway the sign-in sheet for the site visit can be released this week? See Amendment No. 0001

51 Wondering if you had a bidder’s list you can send me? See Amendment No. 0001

What is the procedure for accessing the site? I would like to visit the site again with my subcontractors.

There are no additional formal Site Visits scheduled.

Due to the complexities of the scope of work, RECON respectfully requests a 2-week extension to the due date. See Amendment No. 0001

Will you be providing a copy of the bidders list who attended the site walk last Friday? See Amendment No. 0001

Will you consider extending the due date for the proposal from 14 September 2016 at 1:00 pm? See Amendment No. 0001

In spec 01 45 00 Section 3.2.1, the CQC System Manager is to report directly to the corporate home office of the prime contractor. In Section 3.4.2 it states that the CQC System Manager must be employed by the prime contractor.

Would a subcontractor that is reporting directly to the prime contractor home office be acceptable if the person is not a direct employee of the prime contractor?

No. Information is provided. Contractor should bid per the P&S.

57 When will the answers to questions be issued? See Amendment No. 0003

Offeror respectfully requests a two-week extension from 14 September 2016 to 28 September 2016 to provide the Government with the most competitive bid possible. See Amendment No. 0001.

The bidding schedule on page 00 10 00-3 uses cubic yards for bid items 5 through 7. Bid item 8 is essentially the same as Bid Items 5-7 in that they contain Borrow Material, however the unit described is Each. Is this correct?

Offeror respectfully requests Bid Item 8 be brought into alignment with bid items 5 through 7.

“EA” will be changed to “CY”. See Amendment No. 0003.

The bidding schedule provided (00 10 00-3) uses both lump sum and unit rate pricing. No measurement and payment section has been identified in the specification that details how the items will be paid for during project implementation. Please provide a measurement and payment section that addresses each of the bid items.

A measurement and payment section has been provided. See Amendment No. 0003.

Amendment No. 0003

Request For Information Page 3

Dwg Sheet/ Spec Section Request for Information Response

FAR Clause 52.232-15 is included in this contract. This section states that “a Progress Payments clause is not included in this solicitation, and will not be added to the resulting contract at the time of award.” Does this mean that monthly payments will not be made during the project?

Given the small business set aside status and the overall length of the project, offeror respectfully requests details related to the payment schedule for this project.

Clause has been deleted. See Amendment No. 0003

Line item 8 Borrow – Cap Final cover soil layer the unit is EACH should it be Cubic Yards (CY) ?

“EA” will be changed to “CY”. See Amendment No. 0003.

Clarify Payment: all items with a quantity more than 1 will be measured in place.

A measurement and payment section has been provided. See Amendment No. 0003.

Hoping to get some clarification on questions and deadlines. Please advise when and where we can view notes from the prebid site tour. As well as when and where the sign in sheet addendum will be posted. See Amendment No. 0001

Landfill Gas Vent detail 1/C100.01. In the detail it says to install the vent pipe to bedrock 10 to 20 feet. Are there any soil boring report made available to the contractor? The bid quantity is for the max. depth of 20 feet. Will the contractor receive additional compensation if the quantity is closer to 170 total feet. The unit price increases when the total depth is lessen.

No. A link to the EPA website, directing bidders to the Remedial Investigation Report (depth to bedrock is indicated in the report) has been provided. See Amendment No. 0003.

We respectfully request an extension in the bid due date to 1:00 p.m. Eastern Time on Fri. 9/23/16. See Amendment No. 0001

In reference to Section 52.214-1 of the Construction Solicitation and Specifications, can you clarify what descriptive literature (e.g., Site Operations Plan/Project Execution Plan) is expected to be provided with the offer?

Clause has been deleted. See Amendment No. 0003

68 Is this work in any way tax exempt? No. Project is not tax exempt.

Will any Saturday work be allowed? What if an impending weather event could impact the geosynthetics installation?

(Spec says Monday - Friday only)

Specific project schedule is the contractor’s responsibility and in conjunction with the period of performance and listed weather days, the contractor should bid per the P&S.

There is no measure for payment section. How will the geosynthetics installation be measured and paid?

A measurement and payment section has been provided. See Amendment No. 0003.

Pursuant to the Special Clauses - Section 00 73 00 - A copy of the Remedial Investigation Report will be provided to the Contractor, upon request to the Contracting Officer or Contracting Officers Representative. At this time we are requesting a copy of the above document.

A link to the EPA website, directing bidders to the Remedial Investigation Report (depth to bedrock is indicated in the report) has been provided. See Amendment No. 0003

72 Is project tax exempt? No. Project is not sales tax exempt.

73 What is the stone size for the toe drain?

Clarification: See Drawing C100.01, Detail 7. See Amendment No. 0003

Can the existing and proposed grades be provided at the monitoring wells?

Clarification: Existing and proposed grades are shown on Contract Drawings.

Bid per P&S.

75 How many sheds are being relocated? See Amendment No. 0003

What area of trees and/or wetlands need protective/temporary fence?

Clarification: The LOD and wetland areas define the work items; they are shown on the drawings.

Can a steel wash rack be supplied in lieu of the precast one?

Yes. As long as it adequately satisfies design intent.

Amendment No. 0003

Request For Information Page 4

Dwg Sheet/ Spec Section Request for Information Response

If hazardous material is encountered would the usace contract it or would a change order to the contract occur?

Hazardous material (i.e., hazardous waste) was not encountered in the landfill during the Remedial Investigation, nor is expected to be encountered. If hazardous waste is encountered, a change order would be provided to handle the waste.

If hazardous material is encountered would the contractor be held harmless?

Not sure what bidder is asking on this one. Harmless from what? They would not be considered a “generator”.

80 When would the groundwater component of the project occur?

Clarification: The groundwater remedial action is underway with injection well and monitoring well construction. We suspect that first round of groundwater injections to occur sometime late fall 2016 to winter. It is the intent to have Phase 1 injections completed at wells on landfill and in landfill property wetlands prior to landfill grading activities.

In reference to Section 52.214-21 of the Construction Solicitation and Specifications, can you clarify what descriptive literature is expected to be provided with the offer? Section 52.214-21 (d) indicates descriptive literature would be provided post award with required submittals under 1.2.1 SD-01 Preconstruction Submittals.

Clause has been deleted. See Amendment No. 0003

Please clarify how will the geosynthetics installation will be measured and paid?

A measurement and payment section has been provided. See Amendment No. 0003.

Will payments be allowed for delivered or stored materials?

If so, how will the payment amount be determined? Full value of the material cost based on a schedule of values, percentage of the material cost, or an alternate method?

A measurement and payment section has been provided. See Amendment No. 0003.

Drawing G00.02, General Note 11 references "Remedial Investigation Report, Watson Johnson Landfill Site, Prepared By Tetra Tech, Inc., May 2006". Specification Section 00 73 00, Paragraph 1.1 also references this report. Please provide a copy of this report for bidder review.

A link to the EPA website, directing bidders to the Remedial Investigation Report has been provided. See Amendment No. 0003.

Would wedge welding of the top layer of the geotextile of the geocomposite be allowed?

The specifications require heat bonding.

Wedge welding is a form of heat bonding, so yes, it is acceptable.

Drawing G00.02, General Note 12 states that "A digital Autocad file will be provided to the contractor for use in field engineering and layout during construction". This note seems to conflict with Specification Section 01 33 00, Paragraph 1.5.2 which states that "The entire set of Source Drawing files (DWG) will not be provided to the Contractor." Please clarify what electronic data will and will not be provided to the Contractor.

Section 01 33 00, paragraph 1.5.2 states "Only those requested by the Contractor to prepare shop drawings may be provided. Request the specific Drawing Number only for the preparation of Shop Drawings. These drawings may only be provided after award."

Specification Section 01 35 26, Paragraph 1.14 identifies "Radiation Safety Requirements". Is there known radioactive waste present at the site? If so, please provide background information on what specific radioactive contaminants of concern may be present and the suspected locations of these contaminants, if known.

There are no known radioactive wastes present at the site.

Amendment No. 0003

Request For Information Page 5

Dwg Sheet/ Spec Section Request for Information Response

Specification Section 01 35 26, Paragraph 3.1.3 states "Contract documents identify materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e. 29 CFR Part 1910.1000)." Please identify which contract documents confirm the presence of these materials or provide a copy of these documents for bidder review.

Specification Section 01 35 26, Paragraph 3.1.3 has been revised. See Amendment No. 0003.

Specification Section 01 35 29, Paragraph 1.13.1 states "Base delineation of work zone boundaries on the contamination characterization data and the hazard/risk analysis to be performed as described in paragraph:

HAZARD/RISK ANALYSIS." Please identify which specification section and paragraph this refers to.

Specification Section 01 35 29, Paragraph 1.13.1 has been revised. See Amendment No. 0003.

While it seems clear that all workers will require 40 hour training and there is at least some level of hazardous material expected to be encountered at the site which will require work to be performed in Level C PPE, it does not seem clear what the basis for bidding is related to required PPE and designated work zones. Is the Government expecting bidders to make individual determinations of the expected working conditions (Level D, Level C) as part of the bid process? If so, please provide sufficient supplemental information related to concentrations and locations of contaminants/areas of concern in order to make an educated determination. If not, please identify what the basis for bidding should be related to expected PPE, designated exclusion zones and decontamination requirements.

A link to the EPA website, directing bidders to the Remedial Investigation Report has been provided. See Amendment No. 0003.

Specification Section 01 57 20, Paragraph 1.11 identifies the need for an HTRW perimeter air monitoring program including submission of a PAMP with capabilities for remote air monitoring and reporting. Paragraph 3.5 of the same section requires control of HTRW emissions meeting or exceeding levels established in the PAMP. Please identify types, levels and locations of HTRW materials that may be encountered on the site.

Specification Section 01 57 20, Paragraph 1.11 has been revised. A link to the EPA website, directing bidders to the Remedial Investigation Report has also been provided. See Amendment No.

0003.

Will the NPDES permit be the responsibility of the Contractor?

Clarification: Contractor is not responsible to obtain a wetlands permit for this project.

Please provide measurement and payment information for Division 02 items on the bid form as there is no information listed within the individual specification sections.

A measurement and payment section has been provided. See Amendment No. 0003.

Are E&S requirements per 01-11-00 section 1.2 E, as it relates to the township and county conservation, to be above, beyond and in addition to those specified in the bid documents?

Specification Section 01 11 00, Paragraph 1.2 has been revised. See Amendment No. 0003.

The details note no fill material shall be placed within 50’ of water. Per the bid we are to excavate, remediate and bring to final design areas delineated as wetlands. What specific areas are we to remain 50’ from disturbing?

A review of drawing details, including electronic word search, was performed on the detail set of the Contract Drawings.

We could not find this statement. That said, assume “water” is the actively flowing Tohickon Creek. Wetlands disturbance, protection, and restoration, along with E&S and dewatering is demonstrated on the Contract Drawings and described in the Specifications.

Amendment No. 0003

Request For Information Page 6

Dwg Sheet/ Spec Section Request for Information Response

As of the site walk, two homeowners had not agreed to participate in this project. First, how will this impact the perimeter E&S measures. Second, If waste is found to extend beyond the property line on the eastern border how will it be handled if permission was not granted?

Based on investigations performed during RI, it is not anticipated that landfill waste will be encountered past limits of disturbance. If wastes are encountered beyond limits of disturbance during construction (not uncommon), course of action will be dependent on nature and size of encounter, and with discussions with property owners and EPA.

Offeror respectfully requests a list of any permits that have been obtained for the project, and any remaining permits required prior to work start.

At minimum, required permits:

• Temporary Construction Entrance Permit: See Drawing G00.02, General Notes 5 and 6.

• Any permits required for temporary facilities.

• Any other required permits to perform Work.

• Contractor is not required to obtain NPDES permit, wetlands permit, nor submit NOI.

Summary of Work, paragraph 1.6 requires a scanning of the entire area. Given the history of the site, the occurrence of utilities is highly unlikely. Offeror respectfully recommends this item be adjusted to accommodate a typical dig-safe call. Offeror respectfully requests specificity regarding the type of scan required.

Specification Section 01 11 00, Paragraph 1.6 has been revised. See Amendment No. 0003.

Section 01 32 33 appears to require construction photography to be done by a professional photographer, which is alluded to in the Sample Photo Label. Is a professional photographer required?

No. A professional photographer is not required.

Section 01 32 33, 3.1.b requires monthly photographs. Item 3.1.d references weekly photographs. Please specify the frequency of the photographs.

Specification Section 01 32 33, Paragraph 3.1.d has been revised. See Amendment No. 0003.

Drawing C21.02 indicates cut and fill volumes in the title block area. Please indicate the documents used to develop these volumes.

Bidders should base bids on quantities listed on the Bidding Schedule.

Drawing C70.01 shows cross sections of waste excavation.

However, cross sections are spaced unusually far apart.

Please specify the depth of excavation for the waste excavation, or provide a ax depth of excavation to base the estimate on.

Clarification: Depth to waste excavation is inconsequential to bidding this project. Bidders should base bids on grading plans and on quantities listed on the Bidding Schedule.

Please confirm that Bid Item 04 represents the existing waste.

Clarification: Bid Item is for excavation of landfill waste and/or soils/aggregate.

For the sheds that require relocation, does the offeror have an inventory of the sheds with sizes and features? If so, please provide.

Revised Drawing C21.02. See Amendment No. 0003.

Drawing C21.03 includes cut and fill quantities in the title block. Offeror respectfully requests a description of how these quantities were developed. Do these quantifies relate to the bid form?

Clarification: Bidders should base bids on quantities listed on the Bidding Schedule.

Detail 1 of Drawing C90.03 Does the section (without the spillway components) represent the section through the Sediment Trap longitudinal side embankments or is there another section / detail applicable? Are the required widths of the linear traps provided in any detail or table?

Clarification: The traps should be constructed per the contours on the plans.

Amendment No. 0003

Request For Information Page 7

Dwg Sheet/ Spec Section Request for Information Response

Detail 1 on Drawing 90.03 uses the abbreviations HQ and EV.

Please define these.

Clarification: Tohickon Creek is not classified for special protection (High Quality (HQ) or Exceptional Value (EV)).

If is classified for CWF and MF (cold water fish and migratory fish, respectively. Construct the detail as shown (with the compost layer). The site is not in an HQ/EV watershed.

Detail 1 on Drawing 90.03, Please clarify the application of the upper sectional view. Does this section represent staggered baffles, the turbidity curtain, or both? Are these sections constructed of plywood, or are other materials acceptable?

Clarification: We believe question refers to Detail 2, not 1. Detail represents both and calls out plywood.

Other material, such as super silt fence, may be used as stated in the detail text (2nd sentence).

It’s unclear if the staggered baffle for Trap 1c on Drawing C21.03 Staggered Baffles exists. Please confirm its position.

Clarification: The baffles should be placed per the size (11’x3’) and distance (every 40’) as listed in the detail and the table (Drawing C90.03, Detail 2). This would be in addition to the turbidity curtain shown on the plan.

14. It’s unclear if the staggered baffle for Trap 4b on Drawing C90.03 listed as 11’ when it is viewed on Drawing C21.03. Are the Staggered Baffles listed shown to scale?

Clarification: Use the values (11’x3’) listed in the Detail and Table (Drawing C90.03, Detail 2).

The staggered baffles on C21.03 appear to be free standing in water. Is the location of the staggered baffles accurate?

Clarification: These baffles should be staggered against the side walls as shown in the Detail 2, Drawing C90.03 (every 40 feet).

Please confirm that the baffles can be made from material other than plywood.

Clarification: Other material, such as super silt fence, may be used as stated in the detail text (2nd sentence).

Please clarify the material type of the turbidity curtain adjacent to the stone outlets shown on Drawing 23.03.

Clarification: Plywood or super silt fence.

Please specify the wetland pond areas that need to be dewatered as referenced in Phase 1, Item 4 on Drawing C90.05.

Clarification: The amount of dewatering of wetlands will vary by season, including localized and seasonal ponds.

Dewatering may be required wherever there is disturbance in wetlands/ponds, or directly adjacent to that disturbance.

Specification Section 02210, 3.14 A, 1: Requires all existing subgrades to be compacted to 90% maximum dry density. However considering that the character of on-site materials may not be conducive to effective compaction, it appears that Section 02220, Paragraphs 3.2 A and 3.4 provide alternate criteria requiring compaction using multiple passes of a landfill trash compactor for existing as well as relocated materials. Please indicate which criteria will be operative.

Clarification: Section 02210, Paragraph 3.14A includes the wording “…unless otherwise specifically specified elsewhere.” Therefore, Section 02220 will dictate compaction of the excavated and relocated site materials.

Detail 7, Drawing C100.01: Detail calls out both AASHTO #2 & #4 Stone for Cap Toe Drain. Please clarify apparent conflict.

Clarification: As indicated on Detail 7, the outer 2 feet width is No. 2 Stone, the rest is No. 4 Stone.

Detail 2, Drawing C90.03: Section shows a 1’-thick layer on the bottom of the channel. What material is that layer? Is this layer consistent throughout the sediment traps? Please provide a typical cross-section of sediment trap channels.

Clarification: 1 foot is the burial depth of the baffle or curtain. The traps should be constructed per the contours on the plans.

Amendment No. 0003

Request For Information Page 8

Dwg Sheet/ Spec Section Request for Information Response

Drawing 100.01, Detail 5: This detail shows the triangular #57 stone drain embedment 1’-6” deep into the foundation fill layer. In Detail 6, C100.01, the foundation fill layer is shown 12” deep. Accordingly, the geomembrane appears to be excavated 6” into the existing/shaped subgrade material.

Please confirm that this is the desired detail and dimensions for the cap pipe drain.

Clarification: Dimensions of cap pipe drain shown on detail are correct.

Drain excavation shall be such to provide 6-inches of Cap Foundation Fill material below pipe drain.

Drawing C21.01: The drawn length of the temporary elliptical culverts along East Pumping Station Road appears to be closer to 83’ each rather than 60’ as noted. Please confirm. Clarification: Use 60 feet.

Please confirm that this project is exempt from Federal, State, and Local sales and use taxes. No. Project is not tax exempt.

25. Please confirm that there is no work required on the Johnson Farm driveway within the scope of this project.

The Drawings indicate no Work to be conducted on the current Johnson Farm driveway, except for areas within the temporary security fence and LOD. All areas of driveway and farm field, within the easement areas, shall be restored to pre-construction condition when construction is complete.

Detail 2, Drawing C90.05: Detail appears to indicate a separate 8” “subgrade” layer however there is no description of what comprises that layer other than it is to be compacted to 95%. Is the detail showing that the existing material is to be compacted or is there an additional 8” course of a subgrade material to be supplied.

If an additional course is necessary, please provide a specification for that material.

Clarification: The 8-inches refers to compaction of existing material. As indicated on Drawings, the detail provides minimum requirements.

Contractor is responsible to provide and maintain temporary access road in a manner to provide suitable access for all construction vehicles and loads.

Specification 01 50 00, 2.2.3 requires orange HDPE safety fence to be erected around all excavations. That fence is to be capable of restraining a force of 250 pounds. This type of fence cannot achieve that level of restraint, please adjust the force restraining requirement to align with the material selected.

Specification Section 02630, Paragraph

2.1 has been revised. See Amendment No.

0003.

Specification 01 50 000, 2.4 requires that the government office to have flushing toilets and running water.

Paragraph 3.12.3 requires field-type sanitary facilities.

As this project site is in a remote site without municipal utilities, please confirm that field-type units are acceptable.

No. Minimum field-type sanitary facilities approved by the Contracting Officer are for Contractor's use.

Government toilet facilities will not be available to Contractor's personnel.

Information is provided. Contractor should bid per the P&S.

Specification 01 50 00, 3.7 d:

a. Requirement is for an 8’ fence around the government office and parking area. This fence is not indicated on the drawings. Since the site is already enclosed by a 6’ temporary fence, is this separate 8’ fence required?

b. Requirement is for 5 government parking spaces while Paragraphs 2.2.1 b and 2.5 require 2 spaces. Please resolve conflict.

Requirement is room for 5 government parking spaces inside fenced enclosure, with temporary gravel surfaced parking areas to accommodate 2 vehicles.

Specification 02630, 2.1 A: Considering the relatively shallow depth of the elliptical pipes at Stabilized Construction Entrance #1, please confirm that Class III pipe is adequate.

Revised Section 02630, Paragraph 2.1.

See Amendment No. 0003.

What are the permit requirements for wetlands disturbance and restoration?

Clarification: Contractor is not responsible to obtain a wetlands permit for this project.

Amendment No. 0003

Request For Information Page 9

Dwg Sheet/ Spec Section Request for Information Response

2. Specification Section 02900.2.5: Materials for Deer Fencing – The specifications call for deer fencing, but no waterfowl protection measures. Given the location of the project, there is a possibility of waterfowl predation, especially for herbaceous wetland species. Will USACE require installation of waterfowl exclusion measures as well? Clarification: No.

Specification Section 02900.3.8.B - "maintenance" shall consist of …watering… Part D states “the contractor shall monitor, adjust, and use existing irrigation facilities, if available, and furnish any additional material, equipment, or water to ensure adequate irrigation. Is there an existing irrigation facility available? Clarification: No.

130 Is there a water source for dust control available on site? Clarification: No.

Specification Section 02900.3.12.A states “At the end of the guarantee, the contractor shall reset grades that have settled below the proposed grades on the drawings." Does this requirement pertain to trees and shrubs that are directly affected by settlement? Also, is the contractor expected to repair the cover system where differential settlement has occurred throughout the landfill footprint?

Revised Section 02900, Paragraph 3.12.

See Amendment No. 0003.

Drawing C110.04/Detail 2 shows deer fence at 6' high.

However, Specification Section 02900.2.5.C states that “fence height to be 7’ nominal unless alternatively specified for individual Garden Site. Are Deer Fences #1-#3 on Drawings C110.01 and C110.02 considered “individual Garden Sites”?

Revised Section 02900, Paragraph 2.5.

See Amendment No. 0003.

Drawings C110.01 and C110.02 – Site Restoration Plant Schedule calls for “bare root” root conditions for several species of plants for various sizes. The contractor is concerned about the regional availability of the quantity and size of species in bare root. Upon award, may the contractor propose alternative root conditions (i.e.

appropriately sized containers) understanding the required guarantee period specified in Specification Section 02900.3.12?

The Site Restoration Plant Schedule on Drawings C110.01 and C110.02 allows for Ball & Burlap substitution. Landscape Architect will also accept equivalent container sized plants as long as they are sourced from licensed Nurseries.

Amendment No. 0003

Request For Information Page 10

Watson Johnson Landfill Site Remedial Design – Landfill Component

Amendment No. 0003

IFB W912BU-16-B-0022

BIDDING SCHEDULE

(To be attached to SF 1442)

Item Estimated Unit Estimated No. Description Quantity Unit Price Amount

00 10 00-3

BASE BID ITEMS

1. Monitoring Well Modifications 1 JOB LS $____________

2. Site Clearing 1 JOB LS $____________

3. E&S and Storm Drainage Controls 1 JOB LS $____________

4. Site Excavation and Relocation 36,000 CY $________ $____________

5. Borrow - E&S and SWM 3,000 CY $________ $____________

6. Borrow - Establishment of Cap Subgrade 5,000 CY $________ $____________

7. Borrow - Cap Foundation Fill Layer 32,500 CY $________ $____________

8. Borrow - Cap Final Cover Soil Layer 51,500 CY $________ $____________

9. Landfill Gas Vents 350 LF $________ $____________

10. Landfill Gas Vent Riser Assembly 17 EA $________ $____________

11. Cap Geotextile Fabric 100,000 SY $________ $____________

12. Geocomposite Gas Venting Panels 10,000 LF $________ $____________

13. Geocomposite Drainage Layer (Double Sided) 18,000 SY $________ $____________

14. Geocomposite Drainage Layer (Single Sided) 82,000 SY $________ $____________

15. Geomembrane - Smooth 86,500 SY $________ $____________

16. Geomembrane - Textured 13,500 SY $________ $____________

17. Cap Toe Drains (TD) 1 JOB LS $____________

18. Cap Pipe Drains (TD) 1 JOB LS $____________

19. Topsoil 23 ACRE $________ $____________

20. Permanent Seeding - Seed Mix 1, Wetland Meadow 1,700 SY $________ $____________

21. Permanent Seeding - Seed Mix 2, Permanent Swale 17,735 SY $________ $____________

22. Permanent Seeding - Seed Mix 3, Landfill 121,500 SY $________ $____________

23. Permanent Seeding - Seed Mix 4, Cover Crop 21,000 SY $________ $____________

24. Chain-Link - Fencing 3,600 LF $________ $____________

25. Chain-Link - Fencing Gates 1 JOB LS $____________

Watson Johnson Landfill Site Remedial Design – Landfill Component IFB W912BU-16-B-0022

BIDDING SCHEDULE

(To be attached to SF 1442)

Item Estimated Unit Estimated No. Description Quantity Unit Price Amount

00 10 00-4

26. Landscaping 1 JOB LS $____________

27. Landfill Access Roads 2,750 LF $________ $____________

TOTAL ESTIMATED BASE BID AMOUNT $______________________

Notes:

1. Bidders must submit a price on all items.

Section 00 21 00 - Instructions

52.211-10 Commencement, Prosecution, and Completion of Work APR 1984 52.214-3 Amendments To Invitations For Bids DEC 1989 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids MAR 1997 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-12 Preparation Of Bids APR 1984 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996

52.214.21 Clause Deleted

52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.216-1 Type Of Contract APR 1984 52.219-28 Post-Award Small Business Program Rerepresentation JUL 2013 52.222-5 Construction Wage Rate Requirements--Secondary Site of the MAY 2014

Work 52.222-18 Certification Regarding Knowledge of Child Labor for Listed FEB 2001

End Products 52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.225-10 Notice of Buy American Requirement--Construction

Materials

MAY 2014

52.228-1 Bid Guarantee SEP 1996 52.232-15 Clause Deleted 52.232-16 Progress Payments Alternate I (MAR 2000) APR 2012 52.232-38 Submission of Electronic Funds Transfer Information with

Offer

JUL 2013

52.233-2 Service Of Protest SEP 2006 52.236-27 Site Visit (Construction) FEB 1995 52.252-1 Solicitation Provisions Incorporated By Reference FEB 1998 52.252-5 Authorized Deviations In Provisions APR 1984 52.252-6 Authorized Deviations In Clauses APR 1984 252.232-7006 Wide Area WorkFlow Payment Instructions MAY 2013

W912BU-16-B-0022 INDEX – 00 21 00 - i

This page was intentionally left blank for duplex printing.

W912BU-16-B-0022 00 21 00 - 1

Section 00 21 00 Instructions

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 540 calander days after receipt of the Notice to Proceed.

The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 1989)

(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.

(b) Bidders shall acknowledge receipt of any amendment to this solicitation (1) by signing and returning the amendment, (2) by identifying the amendment number and date in the space provided for this purpose on the form for submitting a bid, (3) by letter or telegram, or (4) by facsimile, if facsimile bids are authorized in the solicitation.

The Government must receive the acknowledgment by the time and at the place specified for receipt of bids.

(End of provision)

52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)

Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments.

The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.

52.214-5 SUBMISSION OF BIDS (MAR 1997)

(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.

(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.

(c) Telegraphic bids will not be considered unless authorized by the solicitation; however, bids may be modified or withdrawn by written or telegraphic…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .